WEEKLY WORK PROGRESS REPORT

Project Name : Perkin Elmer (A&A)

Project Number :

Project Start Date :-

Planned Completion Date :-

Report No. : 001

Progress Report Date :24/07/2022

PROJECT ENGINEER

Name: Vinay Shukla

Mobile No :

Email ID:project3@pcianalytics.in

CONTENTS
Sl. No. DESCRIPTION PAGE NO.
1 PO DETAILS 2
2 PROJECT KEY MILESTONE / SCOPE OF WORK 2
3 INVOICE RECEVING STATUS 2
4 MATERIAL SUPPLY STATUS 3
5 Installation of work / Floor wise 3
6 INSTALLATION STATUS SERVICE WISE 4
7 MANDAYS 4
8 SITE WORKING PROGRESS 5
9 Next Week Plan 5
10 MOM 5
11 SITE CONCERNS / CLEARANCE / DEPENDENCY 6
12 SITE PROGRESS PHOTOGRAPH 6

Page 1 of 11
WEEKLY WORK PROGRESS REPORT

1. PO DETAILS:-
Receipt Of Purchase Order Purchase Order Number

Purchase Order

Purchase Order

2. PROJECT KEY MILESTONE / SCOPE OF WORK :-

Sr. No. Activity’s Remarks

1 Gas Bank Work Under Progress


2
3
4
5
6
7

3. INVOICE RECEVING STATUS:-


Sr. No Invoice No Date Invoice Receiving / Pending Submitted to office
(Status)
1 Not Known
2
3
4
5
6

4. MATERIAL SUPPLY STATUS:-

Page 2 of 11
WEEKLY WORK PROGRESS REPORT

Communicated
Received on Pending status
Sr. No. Description to responsible Remark
site (Not received)
person
Dubey and
1 Acetylene Change Over No Yes Mayur
Dubey and
2 Blower Stand No Yes Mayur
Dubey and
3 GDP No Yes Mayur
4
5
6
7
8
9
10
11
12
13

5. Installation of work / Floor wise : -


Sr. No. Work Header Header Dropping Dropping Remark If
Description / Status (Mtrs Pending Status Pending any
Floor No or %) Status (Mtrs or %) Status
(Mtrs or %) (Mtrs or %)
1. 8th Floor 60% 40 % 0% 100% Still outlet
is pending
for header
2. Gas Bank 80% 20% 40 60% Under
Progress
CA will
Remain
Pending

6. INSTALLATION STATUS SERVICE WISE.

Page 3 of 11
WEEKLY WORK PROGRESS REPORT

Sr. No. Service’s Status


1 Header Work Done But Outlet Header is pending
2 Gas Bank Structure Installed And change-over also
3 Tube Laying Header is done but outlet header is pending
4 Gas Bank tubing Work Under Progress
5
6
7
8

7. MANDAYS
NAME MON TUE WED THU FRI SAT SUN TOTAL TOTAL
DAYS HOURS
Vinay Shukla p P p 3 27

Saif Qureshi P P P P 4 36

Prashant Kochare P P P P 4 36
NA
Abhijeet Ram P P P A 3 27

Rajkumar P P P P 4 36

Nikhil P P A A 2 18

TOTAL MAN HOURS:-180


TOTAL MAN DAYS:- 20

8. SITE WORKING PROGRESS :-


Page 4 of 11
WEEKLY WORK PROGRESS REPORT

1 Gas Bank work is under progress

9. NEXT WEEK PLAN :-

1 Completion of Gas Bank Work

2 Blower Installation Connection

3 Looping In Trainig room

10. MINUTES OF MEETINGS :-


1

11. SITE CONCERNS / CLEARANCE / DEPENDENCY :-

1 Blower Stand

2 Site work is not matching to drawing we have two drawing which one is final?

3 Acetylene Changeover

12. SITE PROGRESS PHOTOGRAPH :-

Page 5 of 11
WEEKLY WORK PROGRESS REPORT

Page 6 of 11
WEEKLY WORK PROGRESS REPORT

Page 7 of 11
WEEKLY WORK PROGRESS REPORT

Page 8 of 11
WEEKLY WORK PROGRESS REPORT

Page 9 of 11
WEEKLY WORK PROGRESS REPORT

Page 10 of 11
WEEKLY WORK PROGRESS REPORT

Page 11 of 11