Constructive Section:
3. Filtered water availability to Followed By: Warm water available to in newly Other 4 water troughs to be connected
cows at temperature Haleem constructed 4 water troughs and soon
parlor.
Also connect water line with
dairy water tank
4. Registration Book of MF-240 ASAP All relevant documents provided
Followed By:
Khalid Sardar
5. Fixation of cow weighing scale ASAP Cow crush and weighing scale fixation
and building of crush Followed By: done.
Haleem
6. Cow foot dip tank ASAP Done
Followed By:
Haleem
7. Shutter in front of Commodity Nov 30, 2010 Shutter rate is Rs.150,000.
Barn
Followed By: We decided to purchase pipe and built
Haleem it ourselves
1
Cost Rs. 40,000 est.
8. Arrangements for winter ASAP - Workers dresses: Provided
- Tarpal to avoid wind for animals:
Followed By: done
Haleem - Geyser for workers: Will be installed
in next three days as soon as we get
boiler
9. Purchase of Grinder, Mixture Under process Order placed
and machinery for wanda
Rs.100,000/- pending to deposit in
Paster account as advance
Followed By:
Haleem
13. Charging of Bio Gas Plant ASAP All constructive work of bio gas plant
done
Followed By:
Nafees
14. Hiring of Security Supervisor Immediate To be discuss
and 2 guards
Followed By:
KM Nadeem as
discussed
15. Silo Bunkers Followed By: Under process
Haleem
40% work completed
16. Sewerage pipe of wasted Followed By: Gulzar is working on it.
water Haleem
Mian Khalid is also working on it.
2
The serious issue, we have to take
decision.