ID Task Mode Task Name Duration Start 02 Apr '23 16 Apr '23 30 Apr '23 14 May '23 28 May

;23 16 Apr '23 30 Apr '23 14 May '23 28 May '23 11 Jun '23
W S T M F T S W S T M F T S W S T M F
1 Underground pipe work 44 days Mon Underground pipe work
10-04-23 10-04

2 PROJECT START 44 days Mon PROJECT START


10-04-23 10-04

3 Layout 3 days Mon


10-04-23 10-04 12-04
Layout
4 Excavation 5 days Thu 13-04-23
13-04 18-04
Excavation
5 Pipe Procurement 9 days Mon
10-04-23 10-04 19-04
Pipe Procurement
6 Pipe Lay 15 days Sun 07-05-23
07-05 23-05
Pipe Lay
7 Back filling & 15 days Thu 18-05-23
compaction 18-05 04-06
Back filling & compaction
8 Surface construction 20 days Wed
24-05-23 24-05
Surface construction
9 PROJECT FINISH 0 days Thu 15-06-23

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project1
Milestone Inactive Summary Start-only Critical
Date: Fri 22-07-22
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1