COMMISSIONING SCHEDULE FOR CPP-II UNIT

ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
1 65MW Captive Power Plant [CPP-II] 78 days Tue 14-04-20 Tue 30-06-20 65MW Captive Power Plant [CP
0%
2 LOCKDOWN COMPLETED 1 day Tue 14-04-20 Tue 14-04-20 LOCKDOWN COMPLETED
0%
3 Project Start after Lockdown 1 day Tue 14-04-20 Tue 14-04-20
0%
4 Civil Activity 26 days Wed 15-04-20 Sun 10-05-20 Civil Activity
0%
5 TT3 Building 16 days Wed 15-04-20 Thu 30-04-20 3
0%
6 FlyAsh Silo 26 days Wed 15-04-20 Sun 10-05-20 3
0%
7 PNV 25 days Wed 15-04-20 Sat 09-05-20 3
0%
8 Ash Cooler J Seal Fan 21 days Wed 15-04-20 Tue 05-05-20 3
0%
9 Sea Water Pipeline/CT Makeup 22 days Wed 15-04-20 Wed 06-05-20 3
0%
10 Sea Intake Transformer Foundation 15 days Wed 15-04-20 Wed 29-04-20 3
0%
11 Condenser Pipe line 15 days Sat 25-04-20 Sat 09-05-20 3FS+10
0%
days
12 Switchyard Charging 26 days Fri 01-05-20 Tue 26-05-20 Switchyard Charging
0%
26-05
13 Transfer & Equipment Supply 1 day Fri 01-05-20 Fri 01-05-20
0%
14 Transformer Received at Site 1 day Fri 01-05-20 Fri 01-05-20 3FS+16
0%
days
Critical Manual Task Baseline Milestone External Tasks
Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 1
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
15 NGR NIFPS System 1 day Fri 01-05-20 Fri 01-05-20 3FS+16
0%
days
16 Civil 15 days Wed 06-05-20 Wed 20-05-20
0%
17 Cable Trench/Foundation 15 days Wed 06-05-20 Wed 20-05-20 14FS+4
0%
days
18 NIFPS System foundation 3 days Wed 06-05-20 Fri 08-05-20 14FS+4
0%
days
19 E&I 18 days Sat 09-05-20 Tue 26-05-20
0%
20 Panels Installation Commissioning 7 days Sat 09-05-20 Fri 15-05-20 15,18
0%
21 Cable tray & Cable laying, 10 days Sun 17-05-20 Tue 26-05-20 17FS-4
0%
Termination & Loop Checking days
22 Structure & Equipment Installation 3 days Sat 16-05-20 Mon 18-05-20 14FS+5
0%
days
23 Testing Of all switch yard equip. 3 days Sat 16-05-20 Mon 18-05-20 20
0%
24 Transformer Installtion & Commissioning 14 days Thu 07-05-20 Wed 20-05-20 20FF,14FS+5
20-05
days,23FF
25 DCS Readiness 25 days Wed 15-04-20 Sat 09-05-20 DCS Readiness
0%
26 E&I 25 days Wed 15-04-20 Sat 09-05-20
0%
27 System Desk & Work Station 5 days Tue 21-04-20 Sat 25-04-20 3FS+6 days
0%
installation

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 2
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
28 Ups Readiness 4 days Tue 21-04-20 Fri 24-04-20 3FS+6 days
0%
29 Cable Laying, Earthing & Termination 25 days Wed 15-04-20 Sat 09-05-20 3
0%
30 IMCC Pannel system rediness 10 days Tue 21-04-20 Thu 30-04-20 3FS+6 days
0%
31 System Charging & Commissioning 7 days Fri 01-05-20 Thu 07-05-20 30
0%
32 Existing CHP System Upgradation 2 days Fri 08-05-20 Sat 09-05-20 31
0%
33 CHP MCC room 18 days Fri 08-05-20 Mon 25-05-20 CHP MCC room
0%
34 E&I 18 days Fri 08-05-20 Mon 25-05-20
0%
35 Cable tray, Cable Laying, Earthing & 10 days Sat 16-05-20 Mon 25-05-20 54FF,3
0%
Lighting
36 Electrical Panels installation testing 10 days Sat 16-05-20 Mon 25-05-20 154FF
0%
commissioning
37 Remote System for Ash handling & 5 days Fri 08-05-20 Tue 12-05-20 31
0%
CHP
38 Boiler & ESP Area 58 days Tue 14-04-20 Wed 10-06-20 Boiler & ESP Area
0%
39 Mechanical 48 days Tue 14-04-20 Sun 31-05-20
0%
40 Pressure Part 30 days Wed 15-04-20 Thu 14-05-20 3
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 3
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
41 Refractory 40 days Wed 15-04-20 Sun 24-05-20 3
0%
42 Bunker 36 days Wed 15-04-20 Wed 20-05-20 3
0%
43 Ducting 36 days Wed 15-04-20 Wed 20-05-20 3
0%
44 Rotary Parts, Fans, BFP Pump etc. 26 days Wed 15-04-20 Sun 10-05-20 3
0%
45 Non Pressure Part 36 days Tue 14-04-20 Tue 19-05-20 8FF
0%
46 Feed water piping 36 days Wed 15-04-20 Wed 20-05-20 3
0%
47 DM Water Supply 20 days Fri 01-05-20 Wed 20-05-20 3FS+16
0%
days
48 ESP Boxup & Commissioning 5 days Tue 26-05-20 Sat 30-05-20 36
0%
49 Ldo Piping 20 days Fri 01-05-20 Wed 20-05-20 3FS+16
0%
days
50 Balance St. Platform 47 days Wed 15-04-20 Sun 31-05-20 3
0%
51 CPP Insulation 57 days Wed 15-04-20 Wed 10-06-20
0%
52 ESP, Boiler, Turbine, Critical Piping 57 days Wed 15-04-20 Wed 10-06-20 3
0%
etc Insulation
53 E&I 52 days Wed 15-04-20 Fri 05-06-20
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 4
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
54 Cable Tray & Cable laying, 41 days Wed 15-04-20 Mon 25-05-20 3
0%
Termination
55 JB & Field Pannel installation & 7 days Tue 19-05-20 Mon 25-05-20 54FF
0%
commissioning
56 Instument Air line work 6 days Fri 22-05-20 Wed 27-05-20 125FF+3
0%
days
57 Burner Management system 5 days Thu 28-05-20 Mon 01-06-20 55,56,31,49
0%
Rediness
58 Instrument Calibration, Installation & 5 days Tue 26-05-20 Sat 30-05-20 31,55
0%
Commissioning
59 Loop Checking 5 days Tue 26-05-20 Sat 30-05-20 54
0%
60 Motor Trials 2 days Tue 26-05-20 Wed 27-05-20 31,54,154,44
0%
61 ESP MCC installation testing & 4 days Tue 26-05-20 Fri 29-05-20 35
0%
commissioning
62 Esp PLC readiness 4 days Tue 26-05-20 Fri 29-05-20 35
0%
63 ESP Transformer Charging 2 days Sat 30-05-20 Sun 31-05-20 61,62
0%
64 Logic, Interlocks Testing & Triping 5 days Mon 01-06-20 Fri 05-06-20 60,63
0%
Checking
65 Individual Trials 2 days Thu 28-05-20 Fri 29-05-20 44,31,60
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 5
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
66 Group Trials 2 days Mon 01-06-20 Tue 02-06-20 65FS+2
0%
days,43,45,48
67 CHP Area 55 days Wed 15-04-20 Mon 08-06-20
0%
68 Mechanical 46 days Wed 15-04-20 Sat 30-05-20
69 Modification of Ext. CHP 20 days Wed 15-04-20 Mon 04-05-20 3
0%
70 Screeen House 12 days Wed 15-04-20 Sun 26-04-20 3
0%
71 Crusher House 15 days Wed 15-04-20 Wed 29-04-20 3
0%
72 Conveyor Gallery & Techonological 40 days Wed 15-04-20 Sun 24-05-20 3
0%
Structure Screen House to Coal
Bunker
73 Conveyor Gallery & Techonological 50 days Wed 15-04-20 Wed 03-06-20 5FF
0%
Structure TT3 to Crusher House
74 E&I 47 days Thu 23-04-20 Mon 08-06-20
0%
75 Cable Tray Cable laying & Earthing, 45 days Thu 23-04-20 Sat 06-06-20 72FF+3
0%
Lighting days,73FF+3
76 Instruments calibraton installation 27 days Wed 13-05-20 Mon 08-06-20 days
75FF+2
0%
days
77 Field Pannels & JB installation 10 days Wed 27-05-20 Fri 05-06-20 73FF+2
0%
days,72FF+2

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 6
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
78 Branch Instrumentation Air line 5 days Mon 25-05-20 Fri 29-05-20 125
0%
79 Motor No Load/Load Trials 2 days Tue 26-05-20 Wed 27-05-20 154,37
0%
80 Logic & Interlock testing with OEM 4 days Wed 13-05-20 Sat 16-05-20 37
0%
81 Group Commissioning 2 days Tue 09-06-20 Wed 10-06-20 80,79,69,70,71,72,73,75,76
10-06
82 ASH Handling Area 42 days Fri 01-05-20 Thu 11-06-20 ASH Handling Area
0%
83 Mechanical 30 days Fri 01-05-20 Sat 30-05-20
0%
84 Piping with Structure 25 days Fri 01-05-20 Mon 25-05-20 6FS-10
0%
days
85 Equipment installation 16 days Fri 15-05-20 Sat 30-05-20 84FF+5
0%
days
86 E&I 37 days Wed 06-05-20 Thu 11-06-20
0%
87 Cable Tray Cable laying & Earthing, 20 days Wed 06-05-20 Mon 25-05-20 84SS+5
0%
Lighting days
88 Insrument Air line branching 6 days Mon 25-05-20 Sat 30-05-20 125
0%
89 Instrument installation Calibration 16 days Wed 13-05-20 Thu 28-05-20 84FF+3
0%
days
90 Motor No Load/Load Trials 5 days Fri 29-05-20 Tue 02-06-20 89,84,154,37
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 7
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
91 Logic & Interlock testing with OEM 8 days Wed 03-06-20 Wed 10-06-20 90,37
0%
92 Commissioning 1 day Thu 11-06-20 Thu 11-06-20 91,84,85
0%
93 PHE, CWP, AUX Cooling System 50 days Wed 15-04-20 Wed 03-06-20 PHE, CWP, AUX Cooling System
0%
94 Mechanical 38 days Wed 15-04-20 Fri 22-05-20
0%
95 Equipment, tank, Piping erection with 38 days Wed 15-04-20 Fri 22-05-20 3,9FF,10FF
0%
structure
96 BOP SECTION INSTRUMENTS 1 day Fri 01-05-20 Fri 01-05-20
0%
SUPPLY
97 JB, Transmitters & accessories 1 day Fri 01-05-20 Fri 01-05-20 3FS+16
0%
days
98 E&I 40 days Sat 25-04-20 Wed 03-06-20
0%
99 Cable Tray Cable laying & Earthing, 30 days Sat 25-04-20 Sun 24-05-20 95SS+10
0%
Lighting days
100 Instrument installation Calibration 20 days Sat 02-05-20 Thu 21-05-20 95SS+16
0%
days,97
101 Motor No Load/Load Trials 5 days Tue 26-05-20 Sat 30-05-20 31,154,99,95
0%
102 Logic & Interlock testing with OEM 2 days Sun 31-05-20 Mon 01-06-20 101
0%
103 Group Trial Commissioning 2 days Tue 02-06-20 Wed 03-06-20 102,101
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 8
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
104 SEA Water Pipe Line (GRP) 44 days Mon 20-04-20 Tue 02-06-20 SEA Water Pipe Line (GRP)
0%
105 Mechanical 43 days Mon 20-04-20 Mon 01-06-20
0%
106 Piping Fabrication & Erection with 41 days Mon 20-04-20 Sat 30-05-20 9SS+5 days
0%
structure
107 Hydro test 2 days Sun 31-05-20 Mon 01-06-20 106FF+2
0%
days,110
108 E&I 32 days Sat 02-05-20 Tue 02-06-20
0%
109 Cable tray, Cable laying Earthing & 10 days Sat 23-05-20 Mon 01-06-20 106FF+2
0%
Termination days,9FF+12
110 2nos. 2MVA Tranformers erection 6 days Sat 02-05-20 days
Thu 07-05-20 10FS+2
0%
testing commissioning days
111 Interlocking with electrical panel, 3 days Fri 08-05-20 Sun 10-05-20 110
0%
installation testing commissioning
112 Group Trial Commissioning 1 day Tue 02-06-20 Tue 02-06-20 107,110,111
0%
113 Cooling Tower 64 days Wed 15-04-20 Wed 17-06-20 Cooling Tower
0%
114 Mechanical 57 days Wed 15-04-20 Wed 10-06-20
0%
115 Fan assembly Erection, V Bar, Fills, 47 days Wed 15-04-20 Sun 31-05-20 3
0%
Eleminator installation

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 9
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
116 Riser Piping 25 days Sun 17-05-20 Wed 10-06-20 115FF+10
0%
days,95FF
117 E&I 52 days Sat 25-04-20 Mon 15-06-20
0%
118 Cable Tray Cable laying & Earthing, 47 days Sat 25-04-20 Wed 10-06-20 116FF
0%
Lighting
119 Instrument installation Calibration 15 days Wed 27-05-20 Wed 10-06-20 118FS-15
0%
days,97
120 Motor No Load/Load Trials 2 days Thu 11-06-20 Fri 12-06-20 31,116,154,119,118
0%
121 Logic & Interlock testing with OEM 3 days Sat 13-06-20 Mon 15-06-20 120
0%
122 Group Commissioning 2 days Tue 16-06-20 Wed 17-06-20 120,121,112
17-06
123 Air Compressor 46 days Wed 15-04-20 Sat 30-05-20 Air Compressor
0%
124 Mechanical 40 days Wed 15-04-20 Sun 24-05-20
0%
125 St. Shed with Equipment & Piping 40 days Wed 15-04-20 Sun 24-05-20 3
0%
erection
126 E&I 36 days Sat 25-04-20 Sat 30-05-20
0%
127 Cable Tray Cable laying & Earthing, 30 days Sat 25-04-20 Sun 24-05-20 125SS+10
0%
Lighting days
128 Instrument installation Calibration 16 days Sun 10-05-20 Mon 25-05-20 127SS+15
0%
days,97
Critical Manual Task Baseline Milestone External Tasks
Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 10
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
129 Load Trial run with commissioning 5 days Tue 26-05-20 Sat 30-05-20 128,31,125
0%
130 Fire System 70 days Wed 15-04-20 Tue 23-06-20 Fire System
0%
131 Mechanical 70 days Wed 15-04-20 Tue 23-06-20
0%
132 Piping Fabrication & Erection with 60 days Wed 15-04-20 Sat 13-06-20 3
0%
structure
133 Hydro test 10 days Sun 14-06-20 Tue 23-06-20 132
0%
134 E&I 35 days Thu 30-04-20 Wed 03-06-20
0%
135 Cable laying & Termination 25 days Thu 30-04-20 Sun 24-05-20 132SS+15
0%
days
136 Field instruments & pannels, 20 days Fri 15-05-20 Wed 03-06-20 135FF+10
0%
installation & commissioning days
137 TG Building 65 days Wed 15-04-20 Thu 18-06-20 TG Building
0%
138 SUPPLY OF PANELS 11KV EXTEN, 1 day Wed 15-04-20 Wed 15-04-20
0%
ICOG,LV BUS DUCT
139 Supply 1 day Wed 15-04-20 Wed 15-04-20 3
0%
140 Mechanical 62 days Wed 15-04-20 Mon 15-06-20
0%
141 Oil piping 11 days Wed 15-04-20 Sat 25-04-20 3
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 11
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
142 Oil Flushing 31 days Tue 28-04-20 Thu 28-05-20 141FS+2
0%
days
143 Main steam piping with temperory 47 days Wed 15-04-20 Sun 31-05-20 3
0%
steam blowing arrangement
144 Critical Piping 62 days Wed 15-04-20 Mon 15-06-20 3
0%
145 Turbine Barring Gear 10 days Mon 01-06-20 Wed 10-06-20 142FS+3
0%
days
146 Other Equipment Induvisual Trial 7 days Tue 26-05-20 Mon 01-06-20 154,47,46,31
0%
147 Other Equipment Group Trial 5 days Tue 02-06-20 Sat 06-06-20 146
0%
148 Governer trial 1 day Sun 07-06-20 Sun 07-06-20 147,142
0%
149 E&I 65 days Wed 15-04-20 Thu 18-06-20
0%
150 Cable tray & Cable laying, 45 days Wed 15-04-20 Fri 29-05-20 3
0%
Termination & Loop Checking
151 Panels Installation 5 days Thu 16-04-20 Mon 20-04-20 139
0%
152 Instrument Air line Branching 20 days Tue 05-05-20 Sun 24-05-20 125FF,97
0%
153 Transformers with Bus Duct Testing & 15 days Thu 16-04-20 Thu 30-04-20 139
0%
Commissioning

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 12
COMMISSIONING SCHEDULE FOR CPP-II UNIT
ID Task Task Name Duration Start Finish Predecessors 1st Quarter 2nd Quarter 3rd Qua
Mode Feb Mar Apr May Jun Jul Aug
154 Testing/Relay setting of 25 days Fri 01-05-20 Mon 25-05-20 153,151
0%
Panels(HT/LT/VFD/DCDB/11KV
Extn./ICOG/Bus Duct
155 Turbine Instrument Calibration 60 days Sun 19-04-20 Wed 17-06-20 144FF+2
0%
installation days
156 Turbine/Generator Logics 12 days Sun 07-06-20 Thu 18-06-20 147
0%
interlocking testing/Tripping with OEM
157 CPP-II Commissioning 27 days Thu 04-06-20 Tue 30-06-20 CPP-II Commissioning
0%
158 Refractory Dry Out 6 days Thu 04-06-20 Tue 09-06-20 41FS+3
0%
days,43,48,151,66,103
159 Alkali Boilout 5 days Wed 10-06-20 Sun 14-06-20 158,49,57,129
0%
160 Steam Blowing 8 days Mon 15-06-20 Mon 22-06-20 42,81,103,52,66,143,159,158,11
22-06
161 Safety Floating 1 day Tue 23-06-20 Tue 23-06-20 160
0%
162 TG rolling & Testing 4 days Fri 26-06-20 Mon 29-06-20 161FS+2
0%
days,160,122,148,144
163 TG SYNC 1 day Tue 30-06-20 Tue 30-06-20 162
0%

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline

Page 13