TIME SCHEDULE

PEKERJAAN PEMBUATAN SUMUR BOR


PT ARAI RUBBER SEAL INDONESIA
1 2 3 4 5 6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
NO ITEM PEKERJAAN STATUS KETERANGAN
06/02/23 13/02/23 20/02/23 27/02/23 06/03/23 13/03/23 20/03/23 27/03/23 03/04/23 10/04/23 17/04/23 24/04/23 01/05/23 08/05/23 15/05/23 22/05/23 29/05/23 05/06/23 12/06/23 19/06/23 26/06/23 03/07/23 10/07/23 17/07/23
12/02/23 19/02/23 26/02/23 05/03/23 12/03/23 19/03/23 26/03/23 02/04/23 09/04/23 16/04/23 23/04/23 30/04/23 07/05/23 14/05/23 21/05/23 28/05/23 04/06/23 11/06/23 18/06/23 25/06/23 02/07/23 09/07/23 16/07/23 23/07/23
A PENENTUAN TITIK BOR DONE BY PT ARSI DONE
B PERSETUJUAN BOR ON PROGRESS 05/03/23
C PELAKSANAAN
1 PERSIAPAN DONE 15/02/23
2 PEMBUATAN SPULBAK DONE 15/02/23
ON PROGRESS
3 PENGEBORAN 67.81% 26/02/23
67.81%
4 PEMASANGAN CASSING 05/03/23
5 PENYETORAN GRAVEL PACK 12/03/23
6 PEMASANGAN POMPA & PIPA 12/03/23
7 PEMASANGAN PANEL & KABEL 12/03/23
8 TES DEBIT AIR 19/03/23
9 TES AIR DI LAB PDAM/ESDM 09/04/23
10 LAPORAN PELAKSANAAN ON PROGRESS 09/04/23
ON PROGRESS
11 STUDY KELAYAKAN SUMUR 16/04/23
(DRAFT)
D PEMBUATAN SIPA ON PROGRESS 23/07/23

Bekasi, 20 Februari 2023


PT ARTHA LEO PUTRA

Yusak Leo Yosteen Sagala


Direktur