1.0 Introduction
Rapidclimb Frames provide a simple method of
converting RMD Kwikform (RMDK) formwork into
a crane handled climbing system.
This guidance note is for the erection, use and
dismantling of Rapidclimb equipment in a typical
scheme – “Rapidclimb”.
This document is not to be used as a working
method statement. It is the customer’s
responsibility to assimilate this information into a
working method statement specific to the site
conditions.
2.0 References
This guidance note shall be read in conjunction
with the RMDK drawings.
Please refer to the RMDK Climbing Formwork
brochure, Rapidclimb Technical Data Sheets, the
attendant RMDK Risk Assessment and the
Equipment Guidance Notes for the formwork
system to be employed.
Reference should also be made to the contract method statement and construction
drawings provided by the contractor for specific details and sequence.
The tolerance for location of anchors from that indicated on the drawing is +/- 10mm
horizontally. Vertically anchors shall not deviate more than 2mm from a line joining all of
the anchors to a particular platform.
Fix the anchors to the wall formwork as shown on the RMDK drawing ensuring they are
secure and straight. It may be necessary to locally displace some reinforcement. Coat the
anchor cones liberally with Anchor Screw Grease to aid later removal.
5. Fit wind ties as shown on the RMDK drawing. Ratchet lashing wind ties should be lightly
tensioned. Avoid over-tightening as this can apply excessive force to components and
anchorages.
6. Remove the formwork from the other side of the wall clean, oil and store ready for
reuse.
7. Add the platforms to the other side of the wall and secure with the safety pins.
8. Fit the wind ties as shown on the RMDK drawing.
9. Engage the wedge brakes on all Rapidclimb Trolleys. Crane in the formwork to one side
of the wall having fitted and well greased the Rapidclimb anchors ready for support of the
following lift. Bolt the form to the plumbing jacks and add the plumbing turnbuckles
ensuring that all are orientated with the right hand thread end at the bottom. Plumb the
formwork and release the crane.
10. Release the wedge brakes and advance the formwork to contact the wall by rotating
the pinion spindle. Drive the wedge brakes into position to lock the trolleys.
Adjust the level of the formwork by rotating the spindle on the trolley jack. Adjust the
sideways transit of the forms by slackening the bolted connection to the trolley jack and
using a podger bar (spud wrench) to slide the formwork in the slots. Re-tighten the fixings.
Check the form for plumb and adjust if necessary.
11. Fix the reinforcement against the formwork and secure. Place the tie rods and spacer
tubes leaving the ties retracted into the tubes at this stage.
12. Crane in the other form, fix, plumb and align it as before.
13. Advance the formwork as before inserting the ties through the pre-drilled holes with the
process.
14. Tighten the ties, place the concrete and allow curing
7.3. Third Lift
15. Remove any bolts connecting the Rapidclimb anchors to the plywood. Slacken and
remove the tie rods and store safely ready for the next use. Shorten the plumbing
turnbuckles in sequence to crack the form face from the new concrete. Retract the
formwork and secure with the wedge brakes.
Fit the wall brackets to the newly exposed second lift concrete. Access can be secured
from the top platform on the retracted formwork a ladder from the platform or a form-
mounted access platform (see 5.0). Fit the next lift Rapidclimb anchors to the form and
grease well.
16. Fix the Hanging Tube Adapters to the Rapidclimb Frames, and attach the hanging
tubes with a single bolt. The tubes will be inclined at this time with the lower end resting on
the ground. Fit the next lift of concrete anchors to the forms.
17. Remove the wind ties
18. Raising the platforms - The forms may be removed from the first lift wall at any time
after the second lift is cured. The equipment shall, however, not be raised and placed onto
the second lift wall brackets until the second lift concrete has reached the minimum cube
strength indicated on the RMDK drawings.
The position to which the formwork is retracted prior to lifting is important as it affects the
angle at which the assembly hangs. Position the formwork such that the assembly hangs
vertically. Trial lifting may be necessary to identify the precise configuration. The position
may vary for different platforms. Mark the position to speed future cycles.
The lifting points are indicated on the RMDK drawings. Connect the lifting equipment to the
lifting points. Remove the Rapidclimb Safety Pins from the wall brackets. Attach tag lines.
And make appropriate adjustments to the guardrails at the ends of the platforms. All
personnel shall leave the platforms prior to lifting.
Lift the formwork and frames off the wall brackets as one unit and engage the frames into
the second lift wall brackets. Use the top pouring accesses on opposing panels of
formwork from which to guide the equipment onto the lift 3 wall brackets. The Hanging
Access Tubes will drop to the vertical.
Once the gang of equipment is in position personnel may go on to the platform and fix the
Rapidclimb Safety Pins to the wall brackets.
19. Fit the Hanging Access Transoms, platforms & guardrails. Fit the second bolts
between the Hanging Access Tubes and the Hanging Tube Adapters.
20. Fit the wind tie
21. Retract and secure the opposite form as before and add the wall brackets.
22. Remove the wind tie and add the greased Rapidclimb anchors.
23. Raise and secure the opposite side platform as before, fit the safety pins and make
necessary adjustments to the platform stop-end guardrails.
24. Fit the suspended access platforms and wind ties
25. Advance and secure one side of formwork and fix the reinforcement against it
26. Close the forms, place ties, pour concrete and cure
27. Retract the formwork, add wall brackets and anchors as before. Attach the crane to the
lift points. Detach the wind ties and remove the wall brackets and anchors from the first
pour. Raise the platform as before and continue the cycle to complete the wall. After each
use the formwork should be cleaned and mould oil or release agent applied.