Professional Documents
Culture Documents
GUIDE WIRE
INSTALLATION
MTC10, MTC13 (NTA030SA) [A868, A872];
MTC15 (NTA040SA) [A869, A873];
MTC18 (NTA040DA) [A870, A874];
MTC13 (NTA030SB) [B868];
MTC15 (NTA035SB) [B869]; SS030BF [A474];
FS030BF [A497]; OSO30EA [A801]; OSO30EB [B801];
OSO30EC [C801]; OS/SS030BC [B826];
OS/SS030BD [C826]; OS030EF [D801];
OS/SS030BE [D826]; OS030BF [E826]
• DISCONNECT THE BATTERY CONNECTOR before doing any maintenance or repair on electric lift
trucks. Disconnect the battery ground cable on internal combustion lift trucks.
• Always use correct blocks to prevent the unit from rolling or falling. See HOW TO PUT THE LIFT
TRUCK ON BLOCKS in the Operating Manual or the Periodic Maintenance section.
• Keep the unit clean and the working area clean and orderly.
• Always use YALE APPROVED parts when making repairs. Replacement parts must meet or exceed
the specifications of the original equipment manufacturer.
• Make sure all nuts, bolts, snap rings, and other fastening devices are removed before using force to
remove parts.
• Always fasten a DO NOT OPERATE tag to the controls of the unit when making repairs, or if the unit
needs repairs.
• Gasoline, Liquid Petroleum Gas (LPG), Compressed Natural Gas (CNG), and Diesel fuel are
flammable. Be sure to follow the necessary safety precautions when handling these fuels and when
working on these fuel systems.
• Batteries generate flammable gas when they are being charged. Keep fire and sparks away from the
area. Make sure the area is well ventilated.
NOTE: The following symbols and words indicate safety information in this manual:
WARNING
Indicates a hazardous situation which, if not avoided, could result in death or
serious injury.
CAUTION
Indicates a hazardous situation which, if not avoided, could result in minor
or moderate injury and property damage.
On the lift truck, the WARNING symbol and word are on orange background.
The CAUTION symbol and word are on yellow background.
Guide Wire Installation Table of Contents
TABLE OF CONTENTS
General................................................................................................................................................................ 1
Description .......................................................................................................................................................... 1
Guide Wire Physical Installation .......................................................................................................................... 2
Equipment ........................................................................................................................................................... 10
Specifications ...................................................................................................................................................... 13
Wire Slot and Expansion Loop Specifications................................................................................................. 13
Material and General Specifications ............................................................................................................... 14
System II Wire Guidance Specifications.............................................................................................................. 17
Pre-Installation Information Form ........................................................................................................................ 18
General
This manual has the correct procedures/methods for wire installation therefore requires a review and com-
installing the guide wire and wire driver for operation plete understanding of this procedure before initial
of the Yale Wire Guided Vehicles. The procedure is checking of the site. A list of required tools, equipment
in a sequential step format in the order the steps are and supplies, as well as specifications are included in
usually done. Some steps can be performed out of this manual.
sequence if the application and circumstances indicate.
Adequate preparation for an economical and durable For adjustments of the wire driver, refer to the section
Wire Driver Manual 2200 YRM 1229.
Description
There are several things that must be done before be- 8. Location and capacity of electrical outlets.
ginning the actual installation of the guide wire. Careful 9. The location and type of connectors necessary to
planning can prevent costly and time consuming mis- connect a garden hose to the cold water source(s).
takes. It may be easier and cheaper for the wire in-
staller to repair any minor floor irregularities in the truck If possible, the drawing should include a 12.2 m (40 ft)
path during guide wire installation. It is best the racks straight section of guide wire outside the rack aisle for
can be installed and approved by the customer and Yale truck testing and alignment. All dimensions must be ref-
Company before the installation of the guide wire. If the erenced to the approved racks or to the agreed on per-
racks cannot be installed before the guide wire instal- manent benchmark points and be given in inches or feet
lation, rack location must be referenced to one or more and inches. The drawing must be mutually approved by
permanent benchmark points. These points must be the customer and Yale Company.
established and agreed upon by the customer and Yale
At least two weeks before the date of installation of the
Company. All dimensions for the guide wire installation
wire, a pre-installation information form must be com-
must be referenced to the approved racks or the bench-
pleted by the dealer. At this time, the working hours
marks. When the guide wire path is known, a physical
will be tentatively scheduled with the customer and the
inspection of the floor must be done by the customer
amount of customer help (if any) will be determined. If
and dealer to establish the following:
possible, establish cutting hours when customer per-
1. Location of racks or benchmark points. Possible
sonnel and vehicle traffic through the cutting area are
location of the wire driver.
at a minimum. Alternate traffic patterns must be devel-
2. Location of areas of floor to be repaired.
oped to avoid congestion during installation. See Fig-
3. Location of all expansion joints and cracks in the
ure 2.
wire path.
4. Location of studs, conduit, rebar, water or drain The amount of normal traffic through the work area, the
lines, rails, or other material in the concrete of the number of people close enough to the saw cutting to
wire path that will require special procedures during require ear protection, protection of electrical and wa-
cutting or installation. ter lines from vehicle traffic, and venting for the exhaust
if a gasoline powered saw is used, are things to be con-
An accurate wire path drawing based on the previously
sidered in establishing the working hours. Establish ar-
planned aisle layout must be made by either the cus-
eas for breaks and lunch for the work party. If neces-
tomer, the dealer, or Yale Company. The purpose of this
sary, define any off-limit areas and determine security
wire and rack installation drawing is to plan the contin-
arrangements for entering and exiting the work site, es-
uous wire path of up to 1524 m (5000 ft) per line driver.
pecially during odd hours.
The drawing will also be used to show:
At this time, the movement or protection of any material
1. Dimensions for wire routing.
or equipment in the work area must be agreed to by
2. Walls and traffic aisles.
the customer. Determine from the customer a suitable
3. Location of wire driver in a visible area.
dump site for the slurry from the cutting operation.
4. Total estimated wire length.
5. Total saw cut length. Make sure container handling and transportation will be
6. Location and type of floor discontinuities. available for handling the slurry from the installation site
7. Location of desired expansion loops. to the dump site. Make sure the floor is smooth enough
1
Guide Wire Physical Installation 2200 YRM 1230
for the casters on the 208.2 liter (55 gal) drum of the
vacuum. See Figure 1. Slurry must NOT be dumped
in sewer or storm drains. Make sure the flow from the
water source will not be interrupted during the cutting
operations.
2
2200 YRM 1230 Guide Wire Physical Installation
Figure 3. Benchmark
Figure 5. "Snapping" Chalk Line
3
Guide Wire Physical Installation 2200 YRM 1230
4
2200 YRM 1230 Guide Wire Physical Installation
12. Turn the saw and water on and adjust the travel
speed and water flow. The speed must be gradually Figure 10. Keep Saw on Path
increased until the saw starts to lug down. Reduce
the speed until the blade runs freely. While cutting, 15. The slurry must be vacuumed immediately, to keep
increase the water flow until the water coming out it from re-hardening in the slot. A squeegee and
of the cut slot is clear. Reduce the flow until the if necessary, another vacuum is used to keep the
color is a slight milky color. The speed and flow slurry from flowing over the floor. See Figure 11.
5
Guide Wire Physical Installation 2200 YRM 1230
20. Just prior to laying the wire, the slot must be cleared
using an ice pick or similar instrument. Then vac-
uum the slot and surrounding area, to make sure
there are no granules left in the slot. See Figure 13.
Figure 11. Vacuum Slurry Immediately Figure 12. Electric Hand Saw
WARNING
If water is used with the electric hand saw, the saw
MUST have an insulated case and care must be
taken to prevent electrical shock.
6
2200 YRM 1230 Guide Wire Physical Installation
7
Guide Wire Physical Installation 2200 YRM 1230
27. All cracks and breaks in the floor must have been
previously marked. The entire guide path must be
inspected. Fill the slot using elastic caulking for a
minimum of 50.8 mm (2 in.) each side at all expan-
sion loops, cracks, and over any splices. Fill the slot
flush with the surface. Generally, it is better to use
too much than too little caulking. This step must be
completed before grouting begins. See Figure 19.
8
2200 YRM 1230 Guide Wire Physical Installation
9
Equipment 2200 YRM 1230
Equipment
Table 1. Equipment
Layout Equipment
1. At least one 30.5 m (100 ft) tape
measure.
2. Chalk line
3. Chalk (including refills Red preferred, blue acceptable. Yellow or white NOT
acceptable since they are not as permanent.
4. Clear sealer to seal chalk line Clear spray "paints" commonly available in spray cans work
well. Tank type sprayers using bulk concrete sealer can be
used. Sealer must preserve chalk line before and during
cutting of groove.
5. A normal transit, piano wire or laser To ensure straight lines. Sufficient piano wire or string for the
beam longest aisle can be substituted for the transit. A laser beam
can also be used.
6. Felt tip (fine) marker Appropriate color ink for marking reference points on floor.
Cutting Equipment
1. A self propelled concrete saw Electric (preferred) or gasoline powered. A 355.6 mm (14 in.)
blade capacity and 18 horsepower is preferred. Must have an
infinite and positive depth adjustment and be equipped for
water cooling the blade. Provide extra gasoline, funnel, and
etc. if gasoline powered machine is used.
10
2200 YRM 1230 Equipment
2. Two (minimum) general purpose One cutting and a minimum of one replacement or spare.
355.6 mm (14 in.) diamond blades More blades can be required for large installations. Type
of blade can vary depending on floor composition. A
carborundum blade can be necessary to cut steel plate, rails,
or other large pieces of metal in the floor.
3. A wet-dry vacuum To pick up slurry before it sets and to clean slot before
installing wire. A vacuum to fit a 208.2 liter (55 gal) capacity
drum mounted on a caster base is recommended. Smaller
wet-dry vacuums can also be necessary to prevent water
flow on the floor.
4. An electric hand saw with concrete blade Used for short cuts and minor corrections to depth or
straightness. Minimum one spare or replacement blade.
5. An electric rotary/hammer hand drill with For drilling vertical expansion loop holes.
3/4 inch bit capacity
6. 1/2 and 3/4 inch carbide tipped impact For rotary/hammer drill.
masonry bits
7. Electric grinder (right angle) For grinding metal or epoxy flush with the surface.
8. Carbide grinding wheel(s) For grinder. Sufficient quantity to complete installation.
9. 20 amp capacity extension cords Sufficient length(s) to reach furthest point from power source
to equipment.
10. Standard garden hose For concrete saw blade cooling. Sufficient length to reach
furthest point from water source.
11. Hose/pipe adapter or connectors To adapt water source outlet to garden hose connector.
Repair connectors to repair the hose if it is damaged during
cutting operation.
12. Portable water tank For water source to cool hand saw blade. Can be water type
fire extinguisher or garden sprayer filled with water.
13. Floor squeegee For moving saw slurry on floor (containment until removed).
Provide extra replaceable squeegee blades for the squeegee
head or sufficient squeegees to complete the job. The
squeegee blades wear rapidly.
14. Safety goggles, ear protection, flashlight For saw operator(s). OSHA can require ear protection for
others near saw cutting operation if cutting is too loud.
Flashlight for chalk path visibility.
15. 208.2 liter (55 gal) drum For dumping slurry from vacuum to transport dump site.
Caster base for moving drum.
Wire Installation Tools and Supplies
1. Wire Sufficient length of wire for all guide paths (no splices in
guided areas), return paths, and test paths.
2. Ice pick For scraping, loosening particles in slot before vacuuming
just before wire installation. A keyhole saw ground smooth or
similar tool can be substituted.
11
Equipment 2200 YRM 1230
3. Pliers, wire strippers, solder, and solder For making wire splices.
gun or iron
4. Heat shrinkable tubing, electrical tape, Sufficient length of specified tubing to insulate and protect
and sealant splices ( 101.6 mm (4 in.) minimum per splice). Tape for
protecting wire insulation at corners. Specified sealant to
protect splices.
5. Commercial heat gun (hot air) To shrink tubing. Soldering iron can be used if there is enough
heat without direct contact to tubing.
6. Smooth tipped tool For pressing wire into slot. A stiff piece of bent wire or keyhole
saw (ground smooth) will do.
7. Pieces of cork or thick cardboard Used to keep wire in the bottom of the slot before grouting.
May be unnecessary depending on width of cut.
Grouting Tools and Supplies
1. Specified grout For filling slot over wire. Sufficient quantity to finish job.
2. Specified caulking For filling over crack or expansion joints. Sufficient quantity
to finish job.
3. Caulking gun For dispensing caulking.
4. Epoxy concrete patching compound For patching, filling, or leveling small areas of the floor.
5. Pails or trays For mixing grout or epoxy patch compound. For the epoxy
products, containers must be disposable or have disposable
liners and be in sufficient quantity to complete job.
6. Trowels and grout tools For working grout into slots and cracks. For finishing grout
smooth at all floor repairs. A shovel can be necessary
depending on the type of grout.
7. Plastic ketchup bottles or funnels, chalk For getting grout mix into slot.
bottle tops and golf tube
8. Knee pads or kneeling pad Recommended for knee protection during grouting operation.
Testing Equipment
1. A volt/ohmmeter (VOM). For checking guide wire continuity and wire driver output.
Beckman HD 100 Recommended. Meter MUST have a reading resolution of 100 uV and an RMS
Fluke 8020A acceptable at 6.25 KHz or accuracy of ±5 percent at the frequency of the wire driver.
less
12
2200 YRM 1230 Specifications
Specifications
WIRE SLOT AND EXPANSION LOOP
SPECIFICATIONS
Figure 23 shows the wire slot and expansion loop spec-
ifications.
13
Specifications 2200 YRM 1230
Material Specification
1. Wire 6 AWG, stranded 19/29 copper type B, 0.010 PVC insulation, any color,
1.98.12 mm (5/64 or 0.078 in.) diameter
Suggested vendors:
Beldon 9980
Alpha 1858/19
Newark 27F3223WM or 37F571WM
2. Solder Tin 60%, lead 40%, non-activated rosin core, 16 gauge
Suggested vendors:
Kester
Ersin Multicore
Newark 33F228, 33F315, 33F217, 81N1591
Duratec TLR6016-1
3. Heat Shrinkable Tubing 3.175 mm (1/8 or 0.125 in.) diameter, any color, PVC, polyolefin or teflon
Suggested vendors:
Voltrex PVS-008, TTS-514, SST-008, FPS-008
Alpha FIT-221-1/8
Newark 37F6992, 81N2701, 37N1170
4. Sealant (Wire Splice) Provide splice corrosion protection from moisture, oil, or acid.
Suggested product (equivalent products acceptable):
Spray Tec "Crystal Clear Insulating Acrylic"
Type 32N291 (MIL-TT-0048)
Newark P/N 00Z245
3M "IVI-Spray" Electrical Sealer No. 2530
Suggested vendor:
Newark Electronics Chicago
Graybar
5. Caulking Must remain elastic and not shrink or dry out.
Suggested product:
G.E. Silastic Silicone or equivalent
6. Grout Must not shrink. Can be water mix "mortar" type or epoxy.
Suggested product:
5-Star Epoxy Grout (U.S. Grout Corportation)
3-6-M (Dural International Corporation)
ROCKITE Grout
14
2200 YRM 1230 Specifications
Material Specification
7. Thin Wall E.M.T. Conduit U.L. approved, galvanized electrical metallic tubing.
Trade size: 1/2 inch
Outside diameter: 0.76 +0.005 inch
Inside diameter: 0.622 inch nominal
Wall thickness: 0.042 inch nominal
Suggested vendors:
Graybar
8. Thin Wall E.M.T. Fitting Steel insulated throat.
Size: 1/2 inch
Suggested vendors:
Graybar Appleton - TW 50SCI, TW-50-SI 98T050
T & B - 5123, 5131
Raco - 2912, 2122, 1992
Gould - 750B, 720B
Steel City - TC-711, TC-721, TC-741
Bridgeport - 250-I, 230-I, 215-I
O.Z./Gedney - 7050 SIT, 4050 SIT
15
Specifications 2200 YRM 1230
16
2200 YRM 1230 System II Wire Guidance Specifications
17
Pre-Installation Information Form 2200 YRM 1230
Telephone Number:
Installation Address:
Person to contact for access to installation site and other arrangements for the installation:
Name(s) (Print):
Date of Installation:
Working Times for Installation:
Number of customer employees helping during
installation (if any):
Amount and type of normal traffic through installation area:
Alternate patterns for traffic during installation. If possible, note on the drawing or draw a map.
Number of customer employees requiring ear
protection:
Determine what methods will be used to protect electrical and water lines from necessary vehicle traffic (lengths
and number of "ramps").
18
2200 YRM 1230 Pre-Installation Information Form
Yes No
Number needed: Type: Size(s):
Define off-limit areas for people making wire installation:
Define security arrangements for entering and leaving work site. Person to contact if daily escort is needed.
Name (Print):
Procedures:
Locate and arrange for movement or protection of any customer equipment or material in work area. Customer
agreement to have moved or protected by installation date.
Customer or representative initials:
Determine location of dump site or provision for disposing of slurry. Slurry must NOT be dumped in sewer or
storm drains. Path to dump site must be smooth enough for caster travel or equipment available to transport full
55-gallon drums.
Establish responsibility of installing power for the wire driver prior to the installation date. Provide customer
a copy of The Wire Driver Manual (Form 599565).
Initials of person responsible:
Determine if there are areas of the floor that require repair. Will repairs be done by customer?
Yes No
Will repairs be done during installation by installation crew?
Yes No
19
NOTES
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
20