A18026 - DRAWINGS DIFFUSION - REVISION 00 - 12/12/2018

LIST OF DETAILED DRAWINGS FOR LOCAL MANUFACTURE

Validated for
Delivery date construction
Project Document typ n° Revision Document sTitle Author Date of revision Send date Qty Unit mass (kg)Total mass (kgDFL N° Set N° on site Y/N
SEPARATION UNIT
DEWATERING SCREEN
EFJV-CML3-PHASE3-STP DWG + PDF 58070 IFC CHUTE 18X36 MMT / JT 5/26/2015 3/11/2019 6 525 3150 17 5
EFJV-CML3-PHASE3-STP DWG + PDF 107671 IFC SAND CHUTE CNO 5/3/2019 5/9/2019 6 254 1524 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107684 IFC SAND CHUTE CNO 5/7/2019 5/9/2019 1 174 174 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107685 IFC SAND CHUTE CNO 5/2/2019 5/9/2019 1 7 7 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107670 IFC SAND CHUTE CNO 5/2/2019 5/9/2019 5 213 1065 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107675 IFC INSPECTION HOLE CNO 5/2/2019 5/9/2019 5 10 50 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107679-00001 IFC SAND CHUTE H=410mm CNO 5/2/2019 5/9/2019 1 53 53 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107679-00002 IFC SAND CHUTE H=570mm CNO 5/2/2019 5/9/2019 1 69 69 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107679-00003 IFC SAND CHUTE H=690mm CNO 5/2/2019 5/9/2019 1 82 82 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107679-00004 IFC SAND CHUTE H=8900mm CNO 5/2/2019 5/9/2019 1 102 102 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107694-00001 IFC STEEL PLATE TH=4mm L=450mm CNO 5/7/2019 5/9/2019 12 1 12 18 6
EFJV-CML3-PHASE3-STP DWG + PDF 107694-00002 IFC STEEL PLATE TH=4mm L=1150mm CNO 1/6/1900 5/9/2019 12 1 12 18 6

PIPES

WASHING

104925 A STAIR TOWER ASSEMBLY


EFJV-CML3-PHASE3-STP DWG + PDF 58055 A IFC STAIRWAY POLE VR 11/25/2015 12/21/2018 4 310 1240 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 58062 IFC TRANSITIONAL STAIR FV / CS 6/3/2015 12/21/2018 6 144 864 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 10 7 70 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 58064 IFC STAIRWAY BRACE 2 FV / CS 6/3/2015 12/21/2018 16 32 512 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 58065 IFC STAIRWAY BRACE 1 FV / CS 6/3/2015 12/21/2018 2 27 54 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 61953-04000B IFC STANDARD STAIRWAY WIDTH 800 INT. (STEP 700) HEIGHT=04000mm CNO 12/1/2017 12/21/2018 1 381 381 2 2
58061 LANDING LEVEL 0 ASSEMBLY
EFJV-CML3-PHASE3-STP DWG + PDF 58057 IFC LEVEL LANDING FV / CS 6/2/2015 12/21/2018 1 339 339 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00890 IFC HANDRAIL LENGHT=00890mm BG 2/14/2014 12/21/2018 2 14 28 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01180 IFC HANDRAIL LENGHT=01180mm BG 2/14/2014 12/21/2018 1 20 20 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-01000 IFC HANDRAIL LENGHT=01000mm BG 2/14/2014 12/21/2018 1 15 15 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 2 7 14 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/21/2018 2 5 10 2 2
58058 TRANSITIONAL LANDING LEVEL ASSEMBLY
EFJV-CML3-PHASE3-STP DWG + PDF 58059 IFC TRANSITIONAL LANDING FV / CS 6/3/2015 12/21/2018 3 222 666 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00800 IFC HANDRAIL LENGHT=00800mm BG 2/14/2014 12/21/2018 6 13 78 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 6 7 42 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01700 IFC HANDRAIL LENGHT=01700mm BG 2/14/2014 12/21/2018 3 24 72 2 2
58056 LANDING LEVEL 1 ASSEMBLY
EFJV-CML3-PHASE3-STP DWG + PDF 58057 IFC LEVEL LANDING FV / CS 6/2/2015 12/21/2018 2 339 678 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01950 IFC HANDRAIL LENGHT=01950mm BG 2/14/2014 12/21/2018 2 25 50 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01090 IFC HANDRAIL LENGHT=01090mm BG 2/14/2014 12/21/2018 2 19 38 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00120 IFC HANDRAIL LENGHT=00120mm BG 2/14/2014 12/21/2018 2 9 18 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00190 IFC HANDRAIL LENGHT=00190mm BG 2/14/2014 12/21/2018 2 9 18 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 4 7 28 2 2
58060 LANDING LEVEL 3 ASSEMBLY
EFJV-CML3-PHASE3-STP DWG + PDF 58057 IFC LEVEL LANDING FV / CS 6/2/2015 12/21/2018 1 339 339 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01950 IFC HANDRAIL LENGHT=01950mm BG 2/14/2014 12/21/2018 1 25 25 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00120 IFC HANDRAIL LENGHT=00120mm BG 2/14/2014 12/21/2018 1 9 9 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00190 IFC HANDRAIL LENGHT=00190mm BG 2/14/2014 12/21/2018 1 9 9 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 3 7 21 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-01000 IFC HANDRAIL LENGHT=01000mm BG 2/14/2014 12/21/2018 1 15 15 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00890 IFC HANDRAIL LENGHT=00890mm BG 2/14/2014 12/21/2018 1 14 14 2 2
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/21/2018 1 5 5 2 2
104936 TROMMEL FRAME
EFJV-CML3-PHASE3-STP DWG + PDF 57862 IFC HEA180 STANDING FOOT FV / CS 5/19/2015 12/21/2018 4 256 1024 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57863 IFC HEA120 CROSS BEAM FV / CS 5/19/2015 12/21/2018 2 122 244 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57864 IFC HEA120 SHORT CROSS BEAM FV / CS 5/19/2015 12/21/2018 1 93 93 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57865 IFC HEA120 LOW SHORT CROSS BEAM FV / CS 5/19/2015 12/21/2018 1 87 87 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57866 IFC IPE120 CROSS BEAM FV / CS 5/19/2015 12/21/2018 3 39 117 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57867 IFC IPE120 CROSS BEAM BRACKET FV / CS 5/19/2015 12/21/2018 12 1 12 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57868 IFC HEA100 WIND BRACING FV / CS 5/20/2015 12/21/2018 2 86 172 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57869 IFC HEA100 LOW WIND BRACING FV / CS 5/20/2015 12/21/2018 2 51 102 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57870 IFC HEA100 HIGH WIND BREACING FV / CS 5/20/2015 12/21/2018 2 65 130 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57871 IFC HEA100 LOW WIND BRACING - STAIRS SIDE FV / CS 5/20/2015 12/21/2018 2 49 98 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57872 A IFC GANGWAY TRAPDOOR ACCESS FV / CS 6/25/2015 12/21/2018 1 88 88 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57873 IFC HEA100 WIND BRACING - TRAPDOOR SIDE FV / CS 5/20/2015 12/21/2018 2 71 142 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57874 IFC HEA120 LOW CROSS BEAM - TRAPDOOR SIDE FV / CS 5/20/2015 12/21/2018 1 70 70 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57875 IFC HEA100 HIGH WIND BRACING - TRAPDOOR SIDE FV / CS 5/20/2015 12/21/2018 1 65 65 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57876 IFC HEA100 HIGH HALF WIND BRACING - TRAPDOOR SIDE FV / CS 5/20/2015 12/21/2018 1 33 33 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57877 IFC HEA100 LOW HALF WIND BRACING - TRAPDOOR SIDE FV / CS 5/21/2015 12/21/2018 1 32 32 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57878 IFC TRAPDOOR ACCESS GANGWAY SUPPORT FV / CS 5/7/2015 12/21/2018 1 23 23 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57879 A IFC STAIRS TRAPDOOR ACCESS FV / CS 6/25/2015 12/21/2018 1 113 113 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57880 IFC TRAPDOOR ACCESS GANGWAY SUPPORT FV / CS 5/7/2015 12/21/2018 3 3 9 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57900 IFC STAIRS ADAPTER TRAPDOOR ACCESS FV / CS 5/7/2015 12/21/2018 1 2 2 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57901 IFC GANGWAY ADAPTER TRAPDOOR ACCESS FV / CS 5/7/2015 12/21/2018 1 4 4 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57902 IFC GANGWAY PLINTH TRAPDOOR ACCESS FV / CS 5/7/2015 12/21/2018 1 8 8 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 57903 IFC PLINTH LEVEL BELOW VALVES FV / CS 5/7/2015 12/21/2018 1 11 11 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/21/2018 3 5 15 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02780 IFC HANDRAIL LENGHT=02780mm BG 2/14/2014 12/21/2018 1 35 35 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00850 IFC HANDRAIL LENGHT=00850mm BG 2/14/2014 12/21/2018 1 16 16 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02370 IFC HANDRAIL LENGHT=02370mm BG 2/14/2014 12/21/2018 1 32 32 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 2 7 14 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00720 IFC HANDRAIL LENGHT=00720mm BG 2/14/2014 12/21/2018 1 12 12 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02690 IFC HANDRAIL LENGHT=02690mm BG 2/14/2014 12/21/2018 1 34 34 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00530 IFC HANDRAIL LENGHT=00530mm BG 2/14/2014 12/21/2018 1 12 12 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01890 IFC HANDRAIL LENGHT=01890mm BG 2/14/2014 12/21/2018 1 25 25 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00400 IFC HANDRAIL LENGHT=00400mm BG 2/14/2014 12/21/2018 1 11 11 7 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00550 IFC HANDRAIL LENGHT=00550mm BG 2/14/2014 12/21/2018 1 12 12 7 2
SLURRY MANAGEMENT
104765 S.U. SLURRY MANAGEMENT RACK PIPES
104767 S.U. RACK 1

740257625.xlsx
Validated for
Delivery date construction
Project Document typ n° Revision Document sTitle Author Date of revision Send date Qty Unit mass (kg)Total mass (kgDFL N° Set N° on site Y/N
EFJV-CML3-PHASE3-STP DWG + PDF 56946 IFC RACK 1 JT / MM 4/28/2015 12/14/2018 1 1035 1035 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105053 IFC RACK BENT CNO 12/3/2018 12/14/2018 1 1288 1288 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105054 IFC WIND BRACING CNO 12/3/2018 12/14/2018 3 62 186 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57309 IFC SUPPORT PIPE FLOOR 1 RACK 1 JT / MM 4/29/2015 12/14/2018 5 4 20 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57310 IFC SUPPORT PIPE FLOOR 2 RACK 1 JT / MM 4/29/2015 12/14/2018 5 12 60 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57196 IFC PIPE 1 WASHING B4 RACK 1 JT / MM 4/29/2015 12/14/2018 1 43 43 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57200 IFC PIPE 1 WATERING TROMMEL RACK 1 JT / MM 4/29/2015 12/14/2018 1 43 43 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57093 IFC PIPE DESANDING UNIT B2 RACK 1 JT / MM 4/29/2015 12/14/2018 1 359 359 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57528 IFC WALKWAY SUPPORT JT / MM 4/30/2015 12/14/2018 6 11 66 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57236 A IFC WALKWAY 1 ACCESS RACK 1 CNO 12/4/2018 12/14/2018 1 129 129 5 1
EFJV-CML3-PHASE3-STP DWG + PDF C22-977 IFC WALKWAY PLATE VR 2/15/2011 12/14/2018 2 1 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02910 IFC HANDRAIL LENGHT=02910mm BG 2/14/2014 12/14/2018 1 35 35 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02600 IFC HANDRAIL LENGHT=02600mm BG 2/14/2014 12/14/2018 1 33 33 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00720 IFC HANDRAIL LENGHT=00720mm BG 2/14/2014 12/14/2018 1 13 13 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02020 IFC HANDRAIL LENGHT=02020mm BG 2/14/2014 12/14/2018 1 29 29 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02590 IFC HANDRAIL LENGHT=02590mm BG 2/14/2014 12/14/2018 1 33 33 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/14/2018 2 7 14 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/14/2018 2 5 10 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 48757 IFC LEVEL SENSOR SUPPORT BG 2/14/2013 12/14/2018 1 13 13 5 1
104769 S.U. RACK 2
EFJV-CML3-PHASE3-STP DWG + PDF 56951 IFC RACK 2 JT / MM 5/6/2015 12/14/2018 1 1525 1525 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105053 IFC RACK BENT CNO 12/3/2018 12/14/2018 1 1288 1288 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105054 IFC WIND BRACING CNO 12/3/2018 12/14/2018 2 62 124 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57307 IFC SUPPORT PIPE FLOOR 1 RACK 2 JT / MM 4/30/2015 12/14/2018 5 4 20 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57311 IFC SUPPORT PIPE FLOOR 2 RACK 2 JT / MM 4/30/2015 12/14/2018 1 12 12 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57312 IFC SUPPORT 2 PIPE FLOOR 2 RACK 2 JT / MM 4/30/2015 12/14/2018 6 12 72 5 1
EFJV-CML3-PHASE3-STP DWG + PDF C22 900 IFC SUPPORT PIPE FLOOR 4 RACK 3 VR 2/2/2011 12/14/2018 2 12 24 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57197 IFC PIPE 1 WASHING B4 RACK 2 JT / MM 5/4/2015 12/14/2018 1 54 54 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57305 IFC PIPE 2 WASHING B4 RACK 2 JT / MM 5/4/2015 12/14/2018 1 20 20 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57201 IFC PIPE 1 WASHING TROMMEL RACK 2 JT / MM 5/4/2015 12/14/2018 1 55 55 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57306 IFC PIPE 2 WASHING TROMMEL RACK 2 JT / MM 5/4/2015 12/14/2018 1 20 20 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57094 IFC PIPE DESANDING UNIT B2 RACK 2 JT / MM 5/4/2015 12/14/2018 1 305 305 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57095 IFC PIPE 2 DESANDING UNI B2 TANK RACK 2 JT / MM 4/30/2015 12/14/2018 1 231 231 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57528 IFC WALKWAY SUPPORT JT / MM 4/30/2015 12/14/2018 9 11 99 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105119 IFC WALKWAY 1 ACCESS 1 RACK 2 CNO 12/3/2018 12/14/2018 1 182 182 5 1
EFJV-CML3-PHASE3-STP DWG + PDF C22 977 IFC WALKWAY PLATE VR 2/15/2011 12/14/2018 2 1 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01660 IFC HANDRAIL LENGHT=01660mm BG 2/14/2014 12/14/2018 1 23 23 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-03000 IFC HANDRAIL LENGHT=03000mm BG 2/14/2014 12/14/2018 4 36 144 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00700 IFC HANDRAIL LENGHT=00700mm BG 2/14/2014 12/14/2018 1 12 12 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 56681-01800 IFC HANDRAIL LENGHT=01800mm MM 3/4/2015 12/14/2018 1 42 42 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57255 IFC WALKWAY 1 ACCESS 2 RACK 2 JT / MM 5/4/2015 12/14/2018 1 36 36 5 1
EFJV-CML3-PHASE3-STP DWG + PDF C22 981 IFC SAFETY LADDER VR 2/15/2011 12/14/2018 1 27 27 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01500 IFC HANDRAIL LENGHT=01500mm BG 2/14/2014 12/14/2018 2 22 44 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 41150 A IFC AGITATOR SUPPORT BEAM BASE SR4660 CLE 4/19/2017 12/14/2018 2 22 44 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105126 IFC AGITATOR SUPPORT CNO 12/4/2018 12/14/2018 2 568 1136 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57950 IFC HALF PIPE CLAMP BEAM AGITATOR SR 4680 JT / MM 5/12/2015 12/14/2018 2 1 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 39681 IFC LOCKING SUPPORT MT 11/3/2010 12/14/2018 2 2 4 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 39682 IFC LOCKING FINGER MT 11/3/2010 12/14/2018 2 1 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57949 IFC BEAM SUPPORT AGITATOR JT / MM 5/11/2015 12/14/2018 2 10 20 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 47983 A IFC STEM VR 5/11/2015 12/14/2018 2 14 28 5 1
104770 S.U. RACK 3
EFJV-CML3-PHASE3-STP DWG + PDF 56955 IFC RACK 3 JT / MM 4/14/2015 12/14/2018 1 1562 1562 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105053 IFC RACK BENT CNO 12/3/2018 12/14/2018 1 1288 1288 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105054 IFC WIND BRACING CNO 12/3/2018 12/14/2018 4 62 248 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57275 IFC SUPPORT PIPE FLOOR 1 RACK 3 JT / MM 5/6/2015 12/14/2018 5 4 20 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57276 IFC SUPPORT PIPE FLOOR 2 RACK 3 JT / MM 7/5/2015 12/14/2018 5 12 60 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57277 IFC SUPPORT PIPE FLOOR 3 RACK 3 JT / MM 4/5/2015 12/14/2018 7 12 84 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57313 IFC SUPPORT 2 PIPE FLOOR 2 RACK 3 JT / MM 5/6/2015 12/14/2018 1 12 12 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57198 IFC PIPE 1 WASHING B4 JT / MM 5/6/2015 12/14/2018 1 64 64 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57202 IFC PIPE 1 WASHING TROMMEL RACK 2 JT / MM 5/13/2015 12/14/2018 1 64 64 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57110 IFC PIPE 1 DESANDING B2 TANK JT / MM 4/14/2015 12/14/2018 1 204 204 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57105 IFC PIPE 1 DESANDING UNIT B3 JT / MM 5/5/2015 12/14/2018 1 166 166 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57108 IFC PIPE 2 DESANDING UNIT B3 JT / MM 5/5/2015 12/14/2018 1 99 99 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57106 IFC BOX DESANDING B3 TANK RACK 3 JT / MM 4/14/2015 12/14/2018 1 216 216 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57107 IFC COVER DESANDING UNIT B3 RACK 3 JT / MM 5/5/2015 12/14/2018 1 38 38 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57208 IFC PIPE EVENT JT / MM 5/6/2015 12/14/2018 1 8 8 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57117 IFC PIPE 3 DESANDING UNIT B3 JT / MM 5/5/2015 12/14/2018 1 124 124 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57266 IFC PIPE 1 B3 B2 JT / MM 5/6/2015 12/14/2018 1 145 145 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105060 IFC PIPE 2 B3 B2 RACK 3 CNO 12/3/2018 12/14/2018 1 51 51 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57268 IFC PIPE 3 B3 B2 JT / MM 5/6/2015 12/14/2018 1 43 43 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57269 IFC PIPE 1 B4 B2 JT / MM 5/6/2015 12/14/2018 1 231 231 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105059 IFC PIPE 2 B4 B2 RACK 3 CNO 12/3/2018 12/14/2018 1 70 70 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57271 IFC PIPE 3 B4 B2 JT / MM 5/15/2015 12/14/2018 1 69 69 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57272 IFC PIPE 1 B5 B2 JT / MM 5/6/2015 12/14/2018 1 219 219 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105058 IFC PIPE 2 B5 B2 RACK 3 CNO 12/3/2018 12/14/2018 2 57 114 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57274 IFC PIPE 3 B5 B2 JT / MM 5/6/2015 12/14/2018 1 69 69 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57528 IFC WALKWAY SUPPORT JT / MM 4/15/2015 12/14/2018 9 11 99 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105121 IFC WALKWAY 1 ACCESS RACK 3 JBA 10/23/2017 12/14/2018 1 177 177 5 1
EFJV-CML3-PHASE3-STP DWG + PDF C22 977 IFC WALKWAY PLATE VR 2/15/2011 12/14/2018 2 1 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-03000 IFC HANDRAIL LENGHT=03000mm BG 2/14/2014 12/14/2018 3 36 108 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02500 IFC HANDRAIL LENGHT=02500mm BG 2/14/2014 12/14/2018 2 33 66 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02100 IFC HANDRAIL LENGHT=02100mm BG 2/14/2014 12/14/2018 1 30 30 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 56680-00900 IFC HANDRAIL LENGHT=00900mm MM 3/4/2015 12/14/2018 1 24 24 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 41150 A IFC AGITATOR SUPPORT BEAM BASE SR4660 CLE 4/19/2017 12/14/2018 1 22 22 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105126 IFC AGITATOR SUPPORT CNO 12/4/2018 12/14/2018 1 568 568 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57950 IFC HALF PIPE CLAMP BEAM AGITATOR SR 4680 JT / MM 5/12/2015 12/14/2018 1 1 1 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 39681 IFC LOCKING SUPPORT MT 11/3/2010 12/14/2018 1 2 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 39682 IFC LOCKING FINGER MT 11/3/2010 12/14/2018 1 1 1 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57949 IFC BEAM SUPPORT AGITATOR JT / MM 5/11/2015 12/14/2018 1 10 10 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 47983 A IFC STEM VR 5/11/2015 12/14/2018 1 14 14 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105231 IFC PIPE 2 B6 B2 RACK 3 CNO 12/3/2018 12/14/2018 1 81 81 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105234 IFC PIPE 1 B6 B2 RACK 3 CNO 12/4/2018 12/14/2018 1 205 205 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 48757 IFC LEVEL SENSOR SUPPORT BG 2/14/2013 12/14/2018 1 13 13 5 1
104772 S.U. RACK 4
EFJV-CML3-PHASE3-STP DWG + PDF 56957 IFC RACK 4 JT / MM 4/14/2015 12/14/2018 1 1403 1403 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105053 IFC RACK BENT CNO 12/3/2018 12/14/2018 1 1288 1288 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105054 IFC WIND BRACING CNO 12/3/2018 12/14/2018 4 62 248 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57314 IFC SUPPORT PIPE FLOOR 1 RACK 4 JT / MM 5/12/2015 12/14/2018 6 12 72 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57199 IFC PIPE 1 WASHING B4 RACK 4 JT / MM 5/11/2015 12/14/2018 1 16 16 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57278 IFC PIPE 2 WASHING B4 RACK 4 JT / MM 5/11/2015 12/14/2018 1 53 53 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57203 IFC PIPE 1 WASHING TROMMEL RACK 4 JT / MM 5/11/2015 12/14/2018 1 16 16 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105169 A IFC PIPE WP4-TR CNO 12/5/2018 12/14/2018 1 52 52 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105172 IFC PIPE WP4-TR ABS 12/3/2018 12/14/2018 1 44 44 5 1

740257625.xlsx
Validated for
Delivery date construction
Project Document typ n° Revision Document sTitle Author Date of revision Send date Qty Unit mass (kg)Total mass (kgDFL N° Set N° on site Y/N
EFJV-CML3-PHASE3-STP DWG + PDF 105170 IFC PIPE WP4-TR ABS 12/3/2018 12/14/2018 1 21 21 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 104774 IFC PIPE 1 B3 B2 RACK 4 ABS 12/3/2018 12/14/2018 1 45 45 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57281 IFC PIPE PIPE 1 B4 B2 RACK 4 JT / MM 5/12/2015 12/14/2018 1 51 51 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57282 IFC PIPE 2 B4 B2 RACK 4 JT / MM 5/12/2015 12/14/2018 1 244 244 5 1
EFJV-CML3-PHASE3-STP DWG 57283 IFC PIPE 1 B5 B2 RACK 4 JT / MM 5/12/2015 12/14/2018 2 44 88 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57284 IFC PIPE 2 B5 B2 RACK 4 JT / MM 5/12/2015 12/14/2018 1 234 234 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57528 IFC WALKWAY SUPPORT JT / MM 4/15/2015 12/14/2018 11 11 121 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105122 IFC WALKWAY 1 ACCESS 1 RACK 4 CNO 12/3/2018 12/14/2018 1 180 180 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105103 IFC WALKWAY 2 ACCESS 1 RACK 4 CNO 12/3/2018 12/14/2018 1 34 34 5 1
EFJV-CML3-PHASE3-STP DWG + PDF C22 977 IFC WALKWAY PLATE VR 2/15/2011 12/14/2018 2 1 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-03000 IFC HANDRAIL LENGHT=03000mm BG 2/14/2014 12/14/2018 4 36 144 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02500 IFC HANDRAIL LENGHT=02500mm BG 2/14/2014 12/14/2018 2 33 66 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00300 IFC HANDRAIL LENGHT=00300mm BG 2/14/2014 12/14/2018 1 6 6 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00620 IFC HANDRAIL LENGHT=00620mm BG 2/14/2014 12/14/2018 2 12 24 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00360 IFC HANDRAIL LENGHT=00360mm BG 2/14/2014 12/14/2018 1 10 10 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 49523 IFC ANGLE HANDRAIL 45° MM 4/18/2013 12/14/2018 2 7 14 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/14/2018 2 5 10 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 48757 IFC LEVEL SENSOR SUPPORT BG 2/14/2013 12/21/2018 1 13 13 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 41150 A IFC AGITATOR SUPPORT BEAM BASE SR4660 CLE 4/19/2017 12/14/2018 1 22 22 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105126 IFC AGITATOR SUPPORT CNO 12/4/2018 12/14/2018 1 568 568 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57950 IFC HALF PIPE CLAMP BEAM AGITATOR SR 4680 JT / MM 5/12/2015 12/14/2018 1 1 1 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 39681 IFC LOCKING SUPPORT MT 11/3/2010 12/14/2018 1 2 2 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 39682 IFC LOCKING FINGER MT 11/3/2010 12/14/2018 1 1 1 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 57949 IFC BEAM SUPPORT AGITATOR JT / MM 5/11/2015 12/14/2018 1 10 10 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 47983 A IFC STEM VR 5/11/2015 12/14/2018 1 14 14 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105230 IFC PIPE B6 B2 RACK 4 CNO 12/4/2018 12/14/2018 1 219 219 5 1
105147 S.U. PIPEWORK BETWEEN B4 B5 PUMPS ROOMS AND RACK
EFJV-CML3-PHASE3-STP DWG + PDF 105148 IFC PIPE WP4-B2 ABS 12/3/2018 12/14/2018 1 111 111 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105149 IFC PIPE WP4-TR ABS 12/3/2018 12/14/2018 1 31 31 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105150 IFC PIPE MP5 B2 ABS 12/3/2018 12/14/2018 1 123 123 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105166 IFC PIPE WP4B HP ABS 12/3/2018 12/14/2018 1 27 27 5 1
EFJV-CML3-PHASE3-STP DWG + PDF 105441 IFC PIPE SUPPORT YT 2/11/2019 2/20/2019 2 35 70 5 3
EFJV-CML3-PHASE3-STP DWG + PDF 105442 IFC PIPING SUPPORT YT 2/11/2019 2/20/2019 1 3 3 5 3
104679 S.U. ACCESS RACK
EFJV-CML3-PHASE3-STP DWG + PDF 61953-03000B IFC STANDARD STAIRWAY WIDTH 800 INT. (STEP 700) HEIGHT=03000mm CNO 12/1/2017 12/21/2018 2 283 566 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 61953-02800B IFC STANDARD STAIRWAY WIDTH 800 INT. (STEP 700) HEIGHT=02800mm CNO 12/1/2017 12/21/2018 1 265 265 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104677 IFC LOW PLATFORM ABS 12/4/2018 12/21/2018 1 55 55 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104678 IFC LOW PLATFORM EXTENSION ABS 12/4/2018 12/21/2018 1 319 319 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104675 IFC HIGH PLATFORM ABS 12/4/2018 12/21/2018 1 36 36 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104692 IFC HIGH PLATFORM SUPPORT ABS 12/14/2018 12/21/2018 1 310 310 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00910 IFC HANDRAIL LENGHT=00910mm BG 2/14/2014 12/21/2018 2 14 28 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00850 IFC HANDRAIL LENGHT=00850mm BG 2/14/2014 12/21/2018 2 14 28 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01780 IFC HANDRAIL LENGHT=01780mm BG 2/14/2014 12/21/2018 1 24 24 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/21/2018 4 5 20 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 59605 IFC HANDRAIL PLATE MM 8/13/2015 12/21/2018 1 6 6 1 2
PUMPS LOCAL
104595 S.U. PUMP(S) ROOM (MUD DISCHARGE)
EFJV-CML3-PHASE3-STP DWG + PDF 104596 IFC SUCTION PIPE MP-T ABS 12/18/2018 12/21/2018 1 121 121 4 2
EFJV-CML3-PHASE3-STP DWG + PDF 104597 IFC RECYCLING PIPING 1 MP-T1 ABS 12/18/2018 12/21/2018 1 66 66 4 2
105309 CONTROL ROOM
105317 CONTROL ROOM ACCESS ASSEMBLY
EFJV-CML3-PHASE3-STP DWG + PDF 105328 IFC BUNGALOW WALKWAY 1 CNO 12/14/2018 12/21/2018 1 174 174 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105319 A IFC BUNGALOW WALKWAY 2 CNO 12/19/2018 12/21/2018 1 64 64 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105318 IFC BUNGALOW WALKWAY 3 CNO 12/14/2018 12/21/2018 1 82 82 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00770 IFC HANDRAIL LENGHT=00770mm BG 2/14/2014 12/21/2018 1 13 13 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00810 IFC HANDRAIL LENGHT=00810mm BG 2/14/2014 12/21/2018 1 13 13 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00110 IFC HANDRAIL LENGHT=00110mm BG 2/14/2014 12/21/2018 1 8 8 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-03000 IFC HANDRAIL LENGHT=03000mm BG 2/14/2014 12/21/2018 1 8 36 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02910 IFC HANDRAIL LENGHT=02910mm BG 2/14/2014 12/21/2018 1 8 35 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02560 IFC HANDRAIL LENGHT=02560mm BG 2/14/2014 12/21/2018 1 8 33 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02520 IFC HANDRAIL LENGHT=02520mm BG 2/14/2014 12/21/2018 1 8 33 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 2 7 14 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01860 IFC HANDRAIL LENGHT=01860mm BG 2/14/2014 12/21/2018 1 24 24 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105417 IFC STEEL PLATE JUNCTION CNO 12/14/2018 12/21/2018 2 9 18 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 61953-00600B IFC STANDARD STAIRWAY WIDTH 800 INT. (STEP 700) HEIGHT=00600mm CNO 12/1/2017 12/21/2018 1 73 73 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105418 IFC STAIRCASE SHIMS CNO 12/14/2018 12/21/2018 2 2 4 6 2
105261 S.U. ROOM FRAME
EFJV-CML3-PHASE3-STP DWG + PDF 105260 A IFC FRAME BGT 12/19/2018 12/21/2018 1 292 292 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105259 A IFC FRAME ROOM BGT 12/19/2018 12/21/2018 1 972 972 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105275 A IFC FRAME ROOM BGT 12/19/2018 12/21/2018 1 972 972 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105273 IFC FRAME CNO 12/14/2018 12/21/2018 1 482 482 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105272 IFC FRAME BGT 12/14/2018 12/21/2018 2 89 178 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105289 IFC FRAME BGT 12/14/2018 12/21/2018 3 53 159 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105262 IFC FRAME BGT 12/14/2018 12/21/2018 4 48 192 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105267 IFC FRAME BGT 12/14/2018 12/21/2018 8 68 544 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105264 A IFC FRAME ROOM BGT 12/19/2018 12/21/2018 4 58 232 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105420 IFC WALKWAY SUPPORT BGT 12/14/2018 12/21/2018 3 14 42 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 105359 IFC STEEL PLATE FOR BUNGALOW BGT 12/14/2018 12/21/2018 8 2 16 6 2
EFJV-CML3-PHASE3-STP DWG + PDF 37566 IFC STEEL PLATE FOR BUNGALOW CS 10/8/2010 12/21/2018 4 1 4 6 2
104563 S.U. TANKS
TANKS
EFJV-CML3-PHASE3-STP DWG + PDF 104604 B1 TANK MAIN STORAGE SLURRY - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 101372 R1 IFC B3 Storage of excess slurry (for B1 construction) KJT 12/1/2017 12/21/2018 1 12884 12884 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 104605 TANK B1A - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 1 0 0 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 104606 TANK B1B - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 1 0 0 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 104622 A B3 TANK STORAGE OF EXCESS SLURRY - LOCATION PRICKINGS ABS 12/18/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 101372R1 IFC B3 Storage of excess slurry (for B3 construction) KJT 12/1/2017 12/21/2018 1 12884 12884 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 104631 A B4 TANK FRESH WATER - LOCATION PRICKINGS ABS 12/18/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 058325 R2 IFC CLEAR WATER B4 (for B4 construction) TP 9/15/2015 12/21/2018 1 11455 11455 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 104630 B5 TANK BENTONITE - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 058326 R2 IFC BENTONITE B5 (for B5 construction) TP 9/15/2015 12/21/2018 1 14759 14759 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 105026 B6-1 FILTRATES TANK - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 340G2JVC050D128-1 IFC SILOS B6-1 AND B6-2 FOR STP (for B6-1 construction) MA 2/19/2018 12/21/2018 1 0 0 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 105027 B6-2 PH TREATMENT TANK - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 340G2JVC050D128-1 IFC SILOS B6-1 AND B6-2 FOR STP (for B6-1 construction) MA 2/19/2018 12/21/2018 1 0 0 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 104956 B6-3 TANK - RECYCLED WATER PH CONTROLLED - LOCATION PRICKINGS ABS 12/4/2018 12/21/2018 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 101374 R2 IFC B8 TANK EMERGENCY (for B6-3 construction) KJT 1/31/2018 12/21/2018 1 8538 8538 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 101374 R2 IFC B8 TANK EMERGENCY (for B8 construction) KJT 1/31/2018 12/21/2018 1 8538 8538 3 2
EFJV-CML3-PHASE3-STP DWG + PDF 17685 B IFC LEVEL SENSOR SUPPORT YT 5/14/2012 12/21/2018 4 15 60 3 2
104608 S.U. B2 CASE UNIT (ACCESS)
EFJV-CML3-PHASE3-STP DWG + PDF 104609 IFC B2 VERFLOW ABS 11/20/2018 12/21/2018 1 562 562 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 12/21/2018 1 5 5 1 2

740257625.xlsx
Validated for
Delivery date construction
Project Document typ n° Revision Document sTitle Author Date of revision Send date Qty Unit mass (kg)Total mass (kgDFL N° Set N° on site Y/N
EFJV-CML3-PHASE3-STP DWG + PDF 57256 IFC WALKWAY 1 TANK B2 MM 5/21/2015 12/21/2018 1 70 70 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104963 IFC LADDER ABS 11/20/2018 12/21/2018 1 26 26 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104965 IFC SAFETY BOW ACCESS ABS 11/20/2018 12/21/2018 1 19 19 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02150 IFC HANDRAIL LENGHT=02150mm BG 2/14/2014 12/21/2018 1 30 30 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02690 IFC HANDRAIL LENGHT=02690mm BG 2/14/2014 12/21/2018 2 34 68 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52502-03000 IFC HANDRAIL LENGHT=03000mm BG 2/14/2014 12/21/2018 1 36 36 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00860 IFC HANDRAIL LENGHT=00860mm BG 2/14/2014 12/21/2018 1 14 14 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 12/21/2018 3 7 21 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 56680-00760 IFC HANDRAIL LENGHT=00760mm MM 3/4/2015 12/21/2018 2 24 48 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 56680-00970 IFC HANDRAIL LENGHT=00970mm MM 3/4/2015 12/21/2018 1 25 25 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 27365-00090B IFC HANDRAIL 90° KCG 12/6/2017 12/21/2018 2 5 10 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 57137 IFC PIPE 1 DESANDING TANK B2 MM 5/21/2015 12/21/2018 1 91 91 1 2
106483 S.U. B1B TANK ACCESS
EFJV-CML3-PHASE3-STP DWG + PDF 106477 IFC B1B WALKWAY CNO 2/21/2019 2/26/2019 1 653 653 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 106509 IFC ACCESS B1B SAFETY LADDER CNO 2/21/2019 2/26/2019 1 162 162 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 41536 C IFC ANGLE HANDRAIL 90° VR 1/6/2011 2/26/2019 4 7 28 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 17516 A IFC POST FOR RAILING AP 5/9/2003 2/26/2019 2 5 10 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 52501-01320 IFC HANDRAIL LENGHT=01320mm BG 2/14/2014 2/26/2019 2 21 42 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 59906 1 IFC LEVEL SENSOR SUPPORT SPECIAL MM 8/14/2015 2/26/2019 1 10 10 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 57575 2 IFC SUPPORT SAFETY LADDER B1B ACCESS MM 8/14/2015 2/26/2019 4 9 36 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 52502-02660 IFC HANDRAIL LENGHT=02660mm BG 2/14/2014 12/21/2018 2 34 36 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 52502-03000 IFC HANDRAIL LENGHT=03000mm BG 2/14/2014 12/21/2018 1 36 36 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00780 IFC HANDRAIL LENGHT=00780mm BG 2/14/2014 12/21/2018 1 13 13 16 4
EFJV-CML3-PHASE3-STP DWG + PDF 52500-00940 IFC HANDRAIL LENGHT=00940mm BG 2/14/2014 12/21/2018 1 14 14 16 4
PIPES
EFJV-CML3-PHASE3-STP DWG + PDF 104619 IFC PIPE B1A B1 ABS 12/4/2018 12/21/2018 1 588 588 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104620 IFC PIPE B1 B1B ABS 12/4/2018 12/21/2018 1 144 144 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104616 IFC PIPE B1A B1B ABS 12/4/2018 12/21/2018 1 522 522 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104632 IFC MP5-B2 SUCTION PIPING ABS 12/4/2018 12/21/2018 1 154 154 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104645 IFC PIPE B3 B1A ABS 12/4/2018 12/21/2018 1 39 39 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104646 IFC PIPE B1A B3 ABS 12/4/2018 12/21/2018 1 60 60 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104634 IFC WP4 SUCTION PIPE ABS 12/4/2018 12/21/2018 1 165 165 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 57909 IFC PIPE SUPPORT 5 MM 5/13/2015 12/21/2018 2 8 16 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 57911 A IFC PIPE SUPPORT 7 MM 8/18/2015 12/21/2018 2 14 28 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 57921 A IFC PIPE SUPPORT 8 MM 8/18/2015 12/21/2018 2 11 22 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 57928 IFC PIPE SUPPORT 9 MM 5/13/2015 12/21/2018 1 9 9 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 60038 IFC COVER MANHOLE MM 8/18/2015 12/21/2018 10 36 360 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 104659 IFC B4 FEED PIPE 1 ABS 12/5/2018 12/21/2018 1 261 261 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 58052 IFC PIPE 2 FEEDING WATER TANK B4 MM 5/21/2015 12/21/2018 1 50 50 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102058 IFC PIPE B6-2 WP6-PHCT 1 CNO 2/13/2018 12/21/2018 2 85 170 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102060 A IFC PIPE B6-2 WP6-PHCT-2 ABS 12/14/2018 12/21/2018 1 179 179 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102061 IFC PIPE B6-2 WP6-B2-1 CNO 2/13/2018 12/21/2018 2 62 124 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102062 A IFC PIPE B6-2 WP6-B2-2 ABS 12/14/2018 12/21/2018 1 136 136 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102067 IFC PIPE WP6 PHCT TANK 3 CNO 2/13/2018 12/21/2018 3 113 339 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 105068 IFC PIPE WP6 PHCT TANK 4 ABS 12/4/2018 12/21/2018 2 113 226 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102069 IFC PIPE WP6 PHCT TANK 4 CNO 2/13/2018 12/21/2018 3 234 702 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102072 IFC PIPE WP6 PHCT TANK 7 CNO 2/13/2018 12/21/2018 1 77 77 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102073 IFC PIPE WP6 PHCT TANK 8 CNO 2/13/2018 12/21/2018 1 203 203 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102079 A IFC DISCHARGE PIPE WP6 HP 1 ABS 12/14/2018 12/21/2018 1 18 18 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 105067 IFC PIPE WP6 PHCT TANK 6 ABS 12/4/2018 12/21/2018 1 111 111 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102104 IFC FLOWFIT SUPPORT CNO 2/13/2018 12/21/2018 1 1 1 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 101979 IFC PIPE SUPPORT B6-2 CNO 2/13/2018 12/21/2018 2 38 76 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102109 IFC PIPE SUPPORT B6-1 CNO 2/13/2018 12/21/2018 4 29 116 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102112 IFC PIPE SUPPORT DN250 CNO 2/13/2018 12/21/2018 8 9 72 1 2
EFJV-CML3-PHASE3-STP DWG + PDF 102080 A IFC DISCHARGE PIPE WP6 HP 2 ABS 12/14/2018 12/21/2018 1 14 14 1 2
105543 S.U. RECIRCULATION PIPEWORK
EFJV-CML3-PHASE3-STP DWG + PDF 105549 IFC PIPE SUPPORT YT 2/11/2019 2/20/2019 4 27 108 11 3
EFJV-CML3-PHASE3-STP DWG + PDF 105636 IFC RECYCLING PIPING B5 YT 2/11/2019 2/20/2019 1 34 34 11 3
EFJV-CML3-PHASE3-STP DWG + PDF 105637 IFC RECYCLING PIPING B5 YT 2/11/2019 2/20/2019 1 90 90 11 3
EFJV-CML3-PHASE3-STP DWG + PDF 105638 IFC RECYCLING PIPING B5 YT 2/11/2019 2/20/2019 1 82 82 11 3
EFJV-CML3-PHASE3-STP DWG + PDF 105639 IFC RECYCLING PIPING B5 YT 2/11/2019 2/20/2019 1 66 66 11 3
EFJV-CML3-PHASE3-STP DWG + PDF 105645 IFC RECYCLING PIPING B5 YT 2/11/2019 2/20/2019 1 133 133 11 3
105580 S.U. PIPEWORK WP1-B3
EFJV-CML3-PHASE3-STP DWG + PDF 105817 IFC DISCHARGE PIPE WP1-B3 YT 2/11/2019 2/20/2019 1 10 10 13 3
EFJV-CML3-PHASE3-STP DWG + PDF 105818 IFC DISCHARGE PIPE WP1-B3 YT 2/11/2019 2/20/2019 1 32 32 13 3
EFJV-CML3-PHASE3-STP DWG + PDF 105819 IFC DISCHARGE PIPE WP1-B3 YT 2/11/2019 2/20/2019 1 14 14 13 3
EFJV-CML3-PHASE3-STP DWG + PDF 105819 IFC DISCHARGE PIPE WP1-B3 YT 2/11/2019 2/20/2019 1 49 49 13 3
EFJV-CML3-PHASE3-STP DWG + PDF 105822 IFC PIPE SUPPORT DN80 H2200 YT 2/11/2019 2/20/2019 1 22 22 13 3
105832 S.U. PIPEWORK WP4B-COAGULANT
EFJV-CML3-PHASE3-STP DWG + PDF 105869 IFC PIPING WP4B-COAGULANT YT 2/11/2019 2/20/2019 1 14 14 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105870 IFC PIPING WP4B-COAGULANT YT 2/11/2019 2/20/2019 1 12 12 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105871 IFC PIPING WP4B-COAGULANT YT 2/11/2019 2/20/2019 1 13 13 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105872 IFC PIPING WP4B-COAGULANT YT 2/11/2019 2/20/2019 1 14 14 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105873 IFC PIPING WP4B-COAGULANT YT 2/11/2019 2/20/2019 1 40 40 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105887 IFC PIPING WP4B-COAGULANT YT 2/11/2019 2/20/2019 1 23 23 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105834 IFC PIPE SUPPORT YT 2/11/2019 2/20/2019 2 3 6 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 105822 IFC PIPE SUPPORT YT 2/11/2019 2/20/2019 1 22 22 14 3
EFJV-CML3-PHASE3-STP DWG + PDF 40547 IFC REDUCE DN65-DN40 SRT 11/30/2010 2/20/2019 1 3 3 14 3
105579 S.U. PIPEWORK BX-B5
EFJV-CML3-PHASE3-STP DWG + PDF 105581 IFC PIPE SUPPORT YT 2/11/2019 2/20/2019 5 29 145 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105797 IFC DISCHARGE PIPE BX-B5 YT 2/11/2019 2/20/2019 1 52 52 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105800 IFC DISCHARGE PIPE BX-B5 YT 2/11/2019 2/20/2019 3 91 273 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105802 IFC DISCHARGE PIPE BX-B5 YT 2/11/2019 2/20/2019 1 51 51 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105803 IFC DISCHARGE PIPE BX-B5 YT 2/11/2019 2/20/2019 2 100 200 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105808 IFC DISCHARGE PIPING YT 2/11/2019 2/20/2019 1 21 21 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105809 IFC DISCHARGE PIPING YT 2/11/2019 2/20/2019 1 39 39 12 3
EFJV-CML3-PHASE3-STP DWG + PDF 105810 IFC DISCHARGE PIPE BX-B5 YT 2/11/2019 2/20/2019 1 37 37 12 3
BENTOMIX & LIME REACTOR
EFJV-CML3-PHASE3-STP DWG + PDF 58317 A IFC BENTONITE POWDER STORAGE SILO ASSEMBLY YT 6/19/2015 1 18000 18000 4 2
EFJV-CML3-PHASE3-STP DWG + PDF 58318 A IFC BENTONITE POWDER STORAGE SILO YT 6/19/2015 12/21/2018 4 2
EFJV-CML3-PHASE3-STP DWG + PDF 58319 A IFC BENTONITE POWDER STORAGE SILO ACCESS YT 6/19/2015 12/21/2018 4 2
105578 S.U. PIPEWORK WP4-BX
EFJV-CML3-PHASE3-STP DWG + PDF 105585 IFC PIPE SUPPORT YT 2/11/2019 2/20/2019 4 26 104 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105588 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 81 81 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105589 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 124 124 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105591 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 82 82 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105592 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 115 115 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105593 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 33 33 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105597 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 83 83 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105596 IFC FEED PIPE WP4 BX YT 2/11/2019 2/20/2019 1 122 122 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105594 IFC FEED PIPE WP4 BX DN100 YT 2/11/2019 2/20/2019 1 40 40 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105595 IFC FEED PIPE WP4 BX DN100 YT 2/11/2019 2/20/2019 1 23 23 10 3

740257625.xlsx
Validated for
Delivery date construction
Project Document typ n° Revision Document sTitle Author Date of revision Send date Qty Unit mass (kg)Total mass (kgDFL N° Set N° on site Y/N
EFJV-CML3-PHASE3-STP DWG + PDF 105598 IFC FEED PIPE WP4 BX DN100 YT 2/11/2019 2/20/2019 1 36 36 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105599 IFC FEED PIPE WP4 BX DN100 YT 2/11/2019 2/20/2019 1 18 18 10 3
EFJV-CML3-PHASE3-STP DWG + PDF 105600 IFC FEEDING PIPING YT 2/11/2019 2/20/2019 1 72 72 10 3
S.U. PIPEWORK TB-GB 105204
EFJV-CML3-PHASE3-STP DWG + PDF 105840 IFC ELBOW CNO 2/13/2019 2/20/2019 1 35 35 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105841 IFC ELBOW CNO 2/13/2019 2/20/2019 2 50 100 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105842 IFC ELBOW CNO 2/13/2019 2/20/2019 2 80 160 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 106360 IFC ELBOW CNO 2/20/2019 2/20/2019 1 66 66 15 3
105203 S.U. PIPEWORK GB-TB PART 1
EFJV-CML3-PHASE3-STP DWG + PDF 105202 IFC PIPES SUPPORT YT 2/13/2019 2/20/2019 18 57 1026 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105403 IFC PIPE DN150 L6M YT 2/13/2019 2/20/2019 42 122 5124 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105205 IFC PIPE DN200 L6M ABS 2/13/2019 2/20/2019 21 204 4284 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105473 IFC SUPPORT CABLE PATH YT 2/13/2019 2/20/2019 21 4.7 98.7 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105472 IFC WIND BRACING YT 2/13/2019 2/20/2019 18 21 378 15 3
105210 S.U. PIPEWORK GB-TB PART 2
EFJV-CML3-PHASE3-STP DWG + PDF 105202 IFC PIPES SUPPORT YT 2/13/2019 2/20/2019 2 57 114 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105212 IFC PIPE DN150 YT 2/13/2019 2/20/2019 1 91 91 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105211 IFC PIPE DN150 YT 2/13/2019 2/20/2019 1 99 99 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105214 IFC PIPE DN200 ELBOW 50 YT 2/13/2019 2/20/2019 1 159 159 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105466 IFC PIPE DN150 YT 2/13/2019 2/20/2019 1 34 34 15 3
105225 S.U. PIPEWORK TANK B6
EFJV-CML3-PHASE3-STP DWG + PDF 105221 IFC PIPE DN200 ELBOW 50 YT 2/13/2019 2/20/2019 1 75 75 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105205 IFC PIPE DN200 L6M ABS 2/13/2019 2/20/2019 7 204 1428 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105248 IFC PIPE DN200 ELBOW 90 YT 2/13/2019 2/20/2019 1 80 80 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105408 IFC PIPE WP6-B2 YT 2/13/2019 2/20/2019 1 92 92 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105412 IFC PIPE WP-FT-B6-1 YT 2/13/2019 2/20/2019 1 232 232 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105067 IFC PIPE WP6-PHCT-TANK 6 ABS 12/4/2018 2/20/2019 1 111 111 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105524 IFC PIPE YT 2/13/2019 2/20/2019 1 216 216 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105439 IFC PIPE SUPPORT YT 2/13/2019 2/20/2019 5 32 160 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105473 IFC SUPPORT CABLE PATH YT 2/13/2019 2/20/2019 5 4.7 23.5 15 3
105520 S.U. STRENGHT LEG
EFJV-CML3-PHASE3-STP DWG + PDF 105505 IFC BRACKET YT 2/13/2019 2/20/2019 9 24 216 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105508 IFC CLEVIS YT 2/13/2019 2/20/2019 9 4 36 15 3
106366 S.U. PIPEWORK GB TB - 2
EFJV-CML3-PHASE3-STP DWG + PDF 105212 IFC PIPE DN150 YT 2/13/2019 2/20/2019 2 91 182 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 106363 IFC PIPE DN150-3 CNO 2/13/2019 2/20/2019 1 132 132 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 106362 IFC PIPE DN150-2 CNO 2/13/2019 2/20/2019 1 72 72 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 106364 IFC PIPE DN150-4 CNO 2/13/2019 2/20/2019 2 23 46 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105214 IFC PIPE DN200 ELBOW 50 YT 2/13/2019 2/20/2019 1 159 159 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 106365 IFC PIPE DN200 2 ELBOW - 1 CNO 2/13/2019 2/20/2019 1 190 190 15 3
EFJV-CML3-PHASE3-STP DWG + PDF 105202 IFC PIPES SUPPORT YT 2/13/2019 2/20/2019 2 57 114 15 3
EXCESS SLURRY TREATMENT
SILOS
102057 S.E. LIME SILO
EFJV-CML3-PHASE3-STP DWG + PDF 67777 IFC LIME SILO ABS 12/18/2018 12/21/2018 1 7000 7000 4 2
EFJV-CML3-PHASE3-STP DWG + PDF 58315 A IFC MF STORAGE SILO ASSEMBLY MM 6/19/2015 1 8000 8000 4 2
EFJV-CML3-PHASE3-STP DWG + PDF 58316 A IFC MF STORAGE SILO (SILO) MM 6/19/2015 12/21/2018 4 2
FILTER PRESS
PIPES

MUD FEED
PIPES

CIVIL WORKS

169858.2