SUPERVICION ENGINEER

TIME SCHEDULE

BOBOT MASA PELAKSANAAN


NO. U R A I A N SKALA
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13
100 %

90 %
1 Pe. Pondasi 4,00 2,000 2,000
2 Pek. Beton/Dinding 6,00 1,500 1,500 1,500 1,500 80 %

3 Pek. Kap/Atap 8,00 2,000 2,000 2,000 2,000 70 %

4 Pek. Teras 8,00 4,000 4,000 60 %

5 Pek. Plester Dinding 9,00 3,000 3,000 3,000 50 %

6 Pek. Lantai 35,00 7,000 7,000 7,000 7,000 7,000 40 %

7 Pek Pintu dan Jendela 5,00 2,500 2,500


30 %

8 Pek. Pengecatan 20,00 5,000 5,000 5,000 5,000


20 %
9 Pek. Pagar Keliling 5,00 2,500 2,500
10 %
100,00
RENCANA PROGRES MINGGUAN 2,000 3,500 1,500 1,500 4,500 5,000 12,000 9,000 16,500 18,500 16,000 7,500 2,500 0%

KUMULATIF RENCANA PROGRES 2,000 5,500 7,000 8,500 13,000 18,000 30,000 39,000 55,500 74,000 90,000 97,500 100,000
REALISASI PROGRES 2,000 3,000 1,000 1,000 4,000 5,000 10,000
KUMULATIF REALISASI PROGRES 2,000 5,000 6,000 7,000 11,000 16,000 26,000
DEVIASI PROGRES 0,000 -0,500 -1,000 -1,500 -2,000 -2,000 -4,000