You are on page 1of 24

Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

We ExamPundit Team, have created a separate website to provide the Best Free PDF Study Materials
on All Topics of Reasoning, Quantitative Aptitude & English Section. This Boost Up PDFs brings you
questions in different level, Easy, Moderate & Hard, and also in New Pattern Questions. Each PDFs
contains 50 Questions along with Explanation. For More PDF Visit: pdf.exampundit.in

DI & CASELETS BASED ON TIME & WORK

Directions (1 – 5): Following bar graph shows b) 947/734 days


working efficiency of four people to complete the c) 780/249 days
work. d) 698/233 days
e) 587/144 days
Number of Days 3. If D and A starts working together and after 2 days,
20
they both left the work and B alone works on third day,
18
16 then find the remaining portion of the work after 3 days.
14 a) 1/10
12
10 b) 21/40
8 c) 1/12
6
4
d) 11/25
2 e) 2/5
0
4. If at the place of B, E joins the work with A, C and D,
A B C D
then work will be completed in 48/13 days. Working
1. A and B starts working together and after 2 days, both
efficiency of E is –
of them left the work. Then in how many days the
a) 12 days
remaining work will be completed by D?
b) 30 days
a) 13/6 days
c) 27 days
b) 41/5 days
d) 36 days
c) 44/5 days
e) 20 days
d) 47/5 days
5. If A works for 3 days, B works for 4 days, C works for
e) 49/5 days
2 days and D works for 2 days, who completed minimum
2. In how many days the total work will be completed, if
fraction of work?
all the four persons starts working together?
a) D
a) 720/247 days
b) C
Page 1 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

c) A a) 6 7/17
d) B b) 7 7/17
e) None of these c) 9 7/17
Directions (6 – 10): The bar graph given below d) 8 7/17
represents the time taken(in days) by 5 persons e) None of these
individually to finish a work when they work at a 7. When all of them work at their actual efficiency, then
certain percentage of their actual efficiencies that is who will take minimum time to finish the work?
given in the table. Read the data carefully and answer a) Shivam
the following questions. b) Aayush
70 c) Amit
d) Mohit
60 e) Anurag
8. Veer(working at his actual efficiency) takes 25% more
50
time than time taken by Aayush and Mohit

40 together(working with their actual efficiency). What is


the total time taken by Veer and Amit together to finish
30 the work when both (Veer and Amit) work at their actual
efficiency?
20
a) 5 days
b) 8 days
10
c) 6 days
0 d) 9 days
Amit Mohit Aayush Shivam Anurag
e) 12 days
Person Amit Mohit Aayush Shivam Anurag 9. Time taken by Mohit(working at actual efficiency) to
Percentage 62 57 60% 63 53 do the work is what percent of time taken by Amit and
of Actual ½% 1/7% 7/11% 1/3% Anurag together (both work at their actual efficiency) to
Efficiency do the same work?
a) 145%
6. What is the time taken by Amit, Mohit and Anurag b) 165%
together to finish the work when they work at their actual c) 155%
efficiency? d) 135%
Page 2 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

e) 185% d) 27 days
10. If Deepak, Shivam and Anurag together(all of them e) 54 days
working at their actual efficiencies) can finish the work 13. Find the time taken by R and S together to complete
in 11 15/19 days, then find the time taken by Deepak and the whole work.
Amit together(both working at actual efficiency) to finish a) 20 days
the same work? b) 18 days
a) 420/43 days c) 12 days
b) 530/43 days d) 15 days
c) 490/43 days e) None of these
d) 340/43 days 14. If the ratio of the efficiency of S to T is 5:x, S started
e) 840/43 days the work alone and after 14 days T joined him and the
11. If Mohit, Shivam and Aayush work on a project remaining work was completed in 10 days. Find the time
(with their actual efficiencies) and get a total salary of Rs taken by T to complete the work alone.
4221, then find the share of Shivam? a) 25 days
a) Rs 1134 b) 30 days
b) Rs 1085 c) 36 days
c) Rs 1875 d) 24 days
d) Rs 980 e) 32 days
e) Rs 1254 Directions (15 – 20): Four different JCB machines are
Directions (12 – 14): Answer the questions based on used to complete a piece of work. Study the following
the information given below. table and answer the questions.
There are 4 persons P, Q, R and S. P and Q start a work JCB No of days Mileage Hours Rent
together. After 9 days, P is replaced by R who can do the in which a (Number (worked charges
work alone in half of the time in which S can do alone. particular of hours in a day) for a day
After 4 days more, R left the work and remaining work is JCB can worked/
completed by Q alone in 7 days. P did 100/3% of the complete litre of
total work. S is 25% less efficient than P. the whole fuel)
12. Find the time taken by Q to complete the work alone. work alone
a) 45 days JCB 12 4 8 Rs 500
b) 30 days 1
c) 18 days
Page 3 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

JCB 6 3 6 Rs 700 b) Rs. 2440


2 c) Rs. 2560
JCB 8 4 4 Rs 600 d) Rs. 2060
3 e) None of these
JCB 4 2 8 Rs 400 18. If JCB 4 was given to complete the whole work. But
4 after two days of work, the JCB 4 broke down and JCB 3
was called to complete the remaining work. Find the
If total payment given to a particular JCB is = Rent number of days JCB 3 will take the complete the
charges + Cost of fuel used during the work. remaining work.
Cost price of diesel = Rs 60/litre a) 2
Mileage is defined as number of hours worked by a JCB b) 4
per litre of the fuel. c) 5
15. If JCB 3 is used to complete the whole work. Find d) 3
the total payment given to it? e) None of these
a) Rs. 5500 19. If during calculation of total payment of JCB 1, the
b) Rs. 5280 rent per day was taken as Rs. 600 per day by mistake.
c) Rs. 5240 Find the extra payment given to JCB 1 for the whole
d) Rs. 5250 work.
e) None of these a) Rs. 100
16. When JCB 4 was used to complete the whole work, b) Rs. 200
the price of diesel rose. If the total payment given to JCB c) Rs. 600
4 is Rs. 2752, find the percentage increase in the price of d) Rs.1200
the fuel as compared to its initial value. e) None of these
a) 10% 20. If JCB 1 and JCB 4 are used to complete the whole
b) 20% work. If for first 3 days, JCB 1 is used and then the
c) 25% remaining work is done by JCB 4. Find the ratio of the
d) 30% payment given to JCB 1 and JCB 4.
e) None of these a) 29 : 31
17. Find the sum of the cost of the fuel consumed by JCB b) 31 : 37
1 and JCB 2, if they complete the work alone separately. c) 31 : 32
a) Rs. 2160 d) 27 : 31
Page 4 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

e) None of these a) 10 days


Directions (21 – 23): Answer the questions based on b) 8 days
the information given below. c) 6 days
The table given below shows the number of people d) 7 days
required for various projects to be completed in various e) None of these
days. Directions (24 – 28): Study the given line chart
Situations Situation 1 Situation 2 carefully and answer the following questions
Projects Number Days Number Days Line chart shows the time taken by 5 boys to complete a
of required of required work.
workers workers 25
A X + 20 30 X 45
B Y+5 Y–5 Y Y–1 20
2 2
C Z 175 M 252

15
21. If 75 people were working on project A, how many
days did it take to complete the work?
10
a) 16 days
b) 20 days
5
c) 24 days
d) 26 days
0
e) None of these A B C D E
22. If 0.6Y people work on project B for 20 days and
The following table shows the ratio of time taken by
then 5 more people join the project after 20 days. How
boys and girls
many days will it take to complete the project B?
Persons Time
a) 30 days
Ratio
b) 32 days
A:F 5:7
c) 35 days
d) 27 days B:G 3:4

e) None of these C:H 4:5

23. Find the time taken by a team of 5Z × 6M members D:I 6:5

to complete the project C. E:J 5:6


Page 5 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

II. Before leaving the work B has completed 13(1/3)%


24. A and G started a work. After 3 days A left the work a) I only
and D joined the work. After One more day G also left b) II only
find in how much time D complete the remaining work. c) Either I or II
a) 9(4/9) days d) Neither I nor II
b) 8 days e) Both I and II
c) 10 (3/11) days 28. Given below are quantities named A and B. Based on
d) 4(5/9) days the given information, you have to determine the relation
e) None of these between the two quantities.
25. B, C and J started a work, B left the work after ‘n’ Quantity A: Time taken by A, E and G together to
days. C and J completed the remaining work in 3(2/5) complete a work.
days. Find after how many days B left the work. Quantity B: Time taken by D, E and J together to
a) 3(1/2) days complete the same work
b) 3 days a) Quantity A < Quantity B
c) 4 days b) Quantity A > Quantity B
d) 2 days c) Quantity A ≤ Quantity B
e) None of these d) Quantity A ≥ Quantity B
26. F, I and E starts work together I and E left the work 2 e) Quantity A = Quantity B or no relation
days before the completion of the work, then the whole Directions (29 – 31): Answer the questions based on
work will be finished in how many days? the information given below.
a) 4(44/79) days There are four friends P, Q, R and S. The time taken by P
b) 6(44/79) days alone to complete the work is x days, the time taken by R
c) 5(44/79) days alone to complete the work is (x + 14) days. P started the
d) 3(48/39) days work alone, after 11 days Q joined him and after 15 more
e) None of these days both of them left the work and the rest work is
27. This question is accompanied by two statements (I), completed by S in 10 days. The efficiency of R is 25%
and (II). You have to determine which statement(s) is/are more than the efficiency of Q, and the ratio of the
sufficient/necessary to answer the question. efficiency of Q to S is 6:7.
B, D and H starts the work together, find in how many 29. What is the value of x?
days whole work will be completed? a) 30
I. B left after 2 days. b) 42
Page 6 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

c) 70 33. Find in how many days 10 males and 12 females


d) 56 together can complete the same work.
e) 60 a) 19(31/38)
30. Find the time taken by S alone to complete the 60% b) 17(31/38)
of the total work. c) 19(29/38)
a) 24 days d) 17(37/38)
b) 40 days e) 17(29/38)
c) 42 days 34. how many days 16 females complete the whole work.
d) 36 days a) 27(5/8)
e) None of these b) 31(7/38)
31. Find the time taken by P and Q together to complete c) 31(1/8)
the work together. d) 28(3/8)
a) 28.20 days e) 28(1/8)
b) 27.50 days Directions (35 – 39): Read the below data carefully
c) 26.25 days and answer the following questions :
d) 30 days The line graph indicates the no. of days taken by six boys
e) None of these to complete a work.
Directions (32 – 34): Read the passage carefully and 16
answer the following questions. 14
X women can do a work in 2Y days. 1.5X men can do a
12
work in Y days. 8 males, 8 Females and 8 children
10
together can do the work in 22.5 days. 3X child can do
the work in 4Y days. 8

32. If 2.5X females can complete the work in 24 days. 6

Then Find the value of Y? 4


a) 35 2
b) 37
0
c) 29 Punit Ashu Nikku Pulkit Pradeep Paras

d) 30
The chart below shows the number of days taken by
e) 28
six girls to complete a work.

Page 7 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

24 A) 10* 4/5 days


25 24
B) 10* 5/6 days
20 20
15 C) 10* 3/4 days
15
10 D) 11 days
10 9 E) 11 3/4 days
5
38. How many days will it take to complete the work if
0
Punit does the 25% of the work alone and 10% is done
Purvi Neha
Hema Happy
Ruhi by Nikku alone and the remaining is done by Suman ??
Suman
A) 19 days
35. If pulkit and paras started to work and after 2 days B) 16 days
they were replaced by neha, ruhi and happy then they c) 13 days
stopped , how much work is still left ? (Neha, Ruhi and D) 17 days
Happy worked for 2 days together) E) 15 days
A) 1/10 39. Ashu started working alone at his normal efficiency
B) 1/6 but after 5 days of starting he found that he has done
C) 1/9 only 25% work so to complete the remaining work on
D) 1/12 time by how much percentage he should increase his
E) 1/13 efficiency?
36. If all the boys work together then time taken by them A) 12.5%
will be how much less than the time taken by purvi, B) 15%
hema , neha and happy together to do the work ? C) 10%
A) 2 * 2/5 days D) 20%
B) 2 * 3/5 days e) 22%
C) 2 * 1/5 days Directions (40 – 44): Given below table shows number
D) 2* 4/5 days of days taken by P & Q together, Q & R together, P
E) 3 days & R together and S alone to complete four different
37. Pradeep and Nikku started work. Pradeep worked at work X, Y, Z & W. Read the data carefully and
120% of his efficiency and Nikku at 5/6 of his normal answer the question.
routine work. They started work on alternate days
starting with Pradeep. How many days will be taken by
them to complete the work?
Page 8 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

e) 8 1/3 days
43. P & Q start work X and did it for first 24 days
alternatively after that P left the work and Q & R work
for next 16 days alternatively on same work and then left
the work, then find in how many days S will be
completed remaining work alone?
a) 2 2/3 days
40. What is ratio of time taken by R & S together to b) 7 2/3 days
complete the work Y to time taken by Q, R & S to c) 5 2/3 days
complete the work Z? d) 1 2/3 days
a) 7 : 9 e) 9 2/3 days
b) 7 : 5 44. All P, Q, R & S start work D, which is 200% more
c) 16 : 7 than work W with same efficiency at they all do work W
d) 7 : 11 expect R. If R work with 300% more efficiently with P,
e) 7 : 13 Q & S together, then find in how many days work D will
41. Find the difference between time taken by R & S be completed?
together to complete work X and time taken by S & P to a) 20days
complete work Z? b) 18days
a) 21 1/48 days c) 30 days
b) 18 1/52 days d) 24 days
c) 16 1/56 days e) 28 days
d) 12 28/51 days Directions (45 – 50): Study the following information
e) 14 1/64 days and answer the questions given below:
42. If P & R work for 8 days on work W and after that P Name of Days taken to Finish job
left the work and R & Q work together for 12 days, find worker Work- Work- Work- Work- Work-
in how many days remaining work will be completed by P Q R S T
S with the help of R? Rahul 144 770 315 84 225
a) 5 ¼ days Sachin 80 924 420 168 180
b) 5 1/8 days Virat 90 420 252 105 150
c) 5 17/19 days Sourav 60 462 90 70 120
d) 7 1/3 days
Page 9 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

Dhoni 48 385 105 140 300 c) 118 3/11 Days


d) 18 4/11 Days
45. Rahul completed 40% of Job-Q alone and then the e) None of these
remaining part of the job was done by Virat and Sourav 48. How long will it take to complete all the five jobs
together. For doing 40% of the job, Rs. 62000 is offered. when all the five men start working on Job-P together
Find out the value of wage, Virat and Rahul together get and once the Job-P is completed all five start working on
per day for doing the remaining part of Job-Q? Job-Q from next day onward and same pattern is
a) Rs.700 followed to complete Job-R, Job-S and Job-T?
b) Rs.352.27 a) 208 days
c) Rs.715 b) 209 days
d) Rs.702.54 c) 210 days
e) None of these d) 211 days
46. Rahul, Sachin and Virat were all hired to complete e) None of these
Job-R together but after 100 days Rahul left the Job, 49. Virat appointed 150 men to finish a work in job R.
Virat left the Job 50 days before completion and only After 152 days he found that 3/5 of work had already
Sachin continued to work till the job was completed. In been done. How many persons we need more, so that the
how many days the job was completed? work can be finished on time?
a) 135 3/4 Days a) 7 men
b) 135 1/4 Days b) 2 men
c) 138 1/4 Days c) 3 men
d) 136 3/4 Days d) 5 men
e) None of these e) None
47. Dhoni and Sourav together work on Job-S and Job-T 50. what is the average number of days taken by all the
on alternate days, starting with Job-S. Once a job is workers to complete the work Q ?
completed, from the very next day Virat joined them and a) 492.3 days
they work every day on the next job together. How long b) 592.2 days
did it take to complete both the work? c) 392.4 days
a) 130 1/11 Days d) 292.2 days
b) 118 2/11 Days e) 191.6 days

Page 10 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

Detailed Explanation

1. Answer: C) (A + D)’s 1 day’s work = 1/8 + 1/16

Given, = 3/16

A's 1 day's work = 1/8 (A + D)’s 2 days’ work = 2 × 3/16 = 3/8

B's 1 day's work = 1/10 Total work done in 3 days = 3/8 + 1/10 = 19/40

(A + B)’s 1 day's work = 1/8 + 1/10 = 9/40 Remaining portion of work after 3 days = 1 – 19/40 =
21/40
(A + B)’s 2 days’ work = (9/40) × 2 = 9/20
4. Answer: D)
Remaining work after 2 days = 1 – 9/20 = 11/20
Given,
Days taken by D to complete 1/10th of the work = 16 ×
11/20 = 44/5 days A's 1 day's work = 1/8

2. Answer: A) C's 1 day's work = 1/18

A's 1 day's work = 1/8 D's 1 day's work = 1/16

B's 1 day's work = 1/10 Let E's 1 day's work = 1/E

C's 1 day's work = 1/18 Then,

D's 1 day's work = 1/16 1/8 + 1/18 + 1/16 + 1/E = 13/48

(A + B + C + D)’s 1 day’s work = 35/144 + 1/E = 13/48

= 1/8 + 1/10 + 1/18 + 1/16 1/E = 1/36

= (90 + 72 + 40 + 45)/720 E can complete the work in 36 days.

= 247/720 5. Answer: B)

Time taken by all four together to complete the work is Given,


720/247 days.
A's 1 day's work = 1/8
3. Answer: B)
A's 3 days’ work = 3/8
Given,
B's 1 day's work = 1/10
A's 1 day's work = 1/8
B's 4 days’ work = 2/5
D's 1 day's work = 1/16
C's 1 day's work = 1/18

Page 11 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

C's 2 days’ work = 1/9

D's 1 day's work = 1/16

D's 2 days’ work = 1/8


10. Answer: E)
From above, C completed less fraction of work.

(6 – 10): Common Explanation:

11. Answer: A)
6. Answer: C)

7. Answer: B)

As we can see from the above table, Aayush will take (12 – 14): Common Explanation:
minimum time.
Let the total amount of the work = 180 units
8. Answer: D)
P worked for 9 days and he did 100/3% of the work. So
he can complete the whole work in 27 days.

Amount of the work done by P in one day = 180/27 =


20/3 units

Amount of the work done by S in one day = 20/3 × 75%


= 5 units

Amount of the work done by R in one day = 5 × 2 = 10


units
9. Answer: C)
Let the amount of the work done by Q in one day = x
units

Page 12 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

(20/3 + x) × 9 + (x + 10) × 4 + 7 × x = 180 JCB 3 can complete the whole work in 8 days and
worked for 4 hours per day, hence worked for total (8 ×
60 + 9x + 4x + 40 + 7x = 180 4) = 32 hours
20x = 80 Payment given to a particular JCB is = Rent charges +
x = 4 units Cost of fuel used during the work

The time taken by P alone to complete the work =180/20 Rent of JCB 3 = Rs 600 per day
× 3 = 27 days
⇒ For 8 days it will be = 600 × 8 = Rs 4800
The time taken by Q alone to complete the work = 180/4
Cost of fuel = Total hours of work/Mileage × cost of
= 45 days
diesel per litre
The time taken by R alone to complete the work =
∴ Total payment = 4800 + 32/4×60 = Rs.5280
180/10 = 18 days
16. Answer: B)
The time taken by S alone to complete the work = 180/5
= 36 days JCB 4 worked for 4 days

12. Answer: C) Rent charges for JCB 4 = Rs. 400 per day

Required time taken = 45 days Rent charges for 4 days = 400 × 4 = Rs. 1600

13. Answer: C) Cost of fuel = Total hours of work/Mileage × cost of


diesel per litre
Required time = 180/(10 + 5) = 180/15 = 12 days
Let the new cost of diesel = Rs x/litre
14. Answer: B)
⇒ 32/2 × x = 16x
According to the question,
Total payment = 2752 (given)
5 × 14 + (5 + x) × 10 = 180
Total payment = Rent charges + Cost of fuel used during
70 + 50 + 10x = 180
the work
10x = 60
⇒ 2752 = 1600 + 16x
x=6
⇒ 1152 = 16x
Time taken by T to complete the work alone = 180/6 =
⇒ x = 72
30 days
New price of fuel = Rs. 72/litre
15. Answer: B)
∴ Percentage increase in the price of the fuel = (72 – 60)
/60 × 100 = 20%

Page 13 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

17. Answer: A) JCB 4 can complete the whole work in = 4 × 8 = 32


hours
Cost of fuel = Total hours of work/Mileage × cost of
diesel per litre Ratio of efficiency of JCB 1 and JCB 4 = 1 : 3

Cost of fuel by JCB 1 = (12×8) /4 × 60=1440 Total work can be assumed as 96 units

Cost of fuel by JCB 2 = (6×6) /3 × 60=720 Work done by JCB 1 in 3 days = 8 × 3 units

∴ The sum of the Cost of fuel of JCB 1 and JCB 2 = Work left to be done by JCB 4 = 96 – 24 = 72 units
1440 + 720 = Rs. 2160
JCB 4 will complete 72 units of work in = 72/(3×8) = 3
18. Answer: B) days

JCB 4 can complete the whole work in 4 × 8 = 32 hours Total Payment given to JCB 1 = Rent charges + Cost of
fuel
JCB 3 can complete the whole work in 8 × 4 = 32 hours
Rent charges = 3 × 500 = Rs. 1500
⇒ Total work can be assumed as = 32 units
Cost of fuel = Total hours of work/Mileage×cost of
⇒ Work done by JCB4 in 2 days = 2 × 8 = 16 units diesel per litre
⇒ Work left to be done by JCB 3 = 32 – 16 = 16 units ⇒(3×8)/4×60=Rs. 360
∴ JCB 3 will complete 16 units in = 16/4 = 4 days (JCB Total payment given to JCB 1 = 1500 + 360 = Rs.1860
3 do 4 units of work in a day)
Total payment given to JCB 4 = Rent charges + Cost of
19. Answer: D) fuel
Total payment = Rent charges + Cost of fuel Rent charges = 3 × 400 = Rs. 1200
Payment made due to wrong calculation: Cost of fuel = Total hours of work/Mileage×cost of
⇒ Total Payment = 600 × (12) + (12×8) /4×60 = Rs. diesel per litre
8640 ⇒ (3×8) /2×60=Rs. 720
Actual Payment which should have been done = 500 × Total payment given to JCB 4 = 1200 + 720 = Rs. 1920
(12) + (12×8) /4 × 60 = Rs. 7440
The ratio of the total payment given to JCB 1 and JCB 4
∴ Extra payment given to JCB 1 =8640 – 7440 = Rs. = 1860/1920 = 31/32
1200
∴ Ratio is 31 : 32
20. Answer: C)
21. Answer: C)
JCB 1 can complete the whole work in = 12 × 8 = 96
hours According to question

Page 14 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

30 × (X + 20) = 45X Let total work = LCM (10, 18, 20) = 180 unit

30X + 600 = 45X One day work of A = 180/10 = 18 unit

X = 40 One day work of G = 180/20 = 9 unit

Total work = 40 × 45 = 1800 units One day work of D = 180/18 = 10 unit

Desired number of days = 1800/75 = 24 days Work done by A and G in 3 days = (18 + 9) × 3 = 81 unit

22. Answer: C) Work done by G and D in 1 day = (10 + 9) × 1= 19 unit

According to question, Remaining work = 180 - (81 + 19) = 80 unit

(Y – 5) × (Y + 5) = Y × (Y – 1) ∴ Time taken by D to complete the remaining work =


80/10 days = 8 days
Y2 – 25 = Y2 – Y
25. Answer: B)
Y = 25
Time taken by J to do the work = 20/5 × 6 = 24 days
So, total amount of work = 25 × (25 – 1) = 25 × 24 = 600
units Let total work = LCM (15, 12, 24) = 120 unit

Amount of work done by 0.6Y (15 people) in 20 days = One day work of B = 120/15 = 8 unit
15 × 20 = 300 units
One day work of C = 120/12 = 10 unit
Amount of work left = 600 – 300 = 300 units
One day work of J = 120/24 = 5 unit
Desired time = 20 + 300/(15 + 5) = 20 + 15 = 35 days
Work done by C and J in 3(2/5) days = (10 + 5) × 17/5 =
23. Answer: D) 51 unit

According to question, Remaining work = 120 – 51 = 69 unit

175 × Z2 = 252 × M2 No. of day for which B, C and J worked together = 69/ (8
+ 10 + 5) = 69/23 = 3 day
(Z/M)2 = 252/175 = 36/25
∴ B left the work after 3 days.
Z/M = 6/5
26. Answer: B)
5Z = 6M
Time taken by F to do whole work alone = 10/5 × 7 = 14
Total number of workers = 5Z × 6M = 6M × 6M = 36M2
Time taken by I to do whole work alone = 18/6 × 5 = 15
Desired time = (252M2)/(36M2) = 7 days
Let total work = LCM (14, 15, 20) = 420 unit
24. Answer: B)
One day work of F = 420/14 = 30 unit
Time taken by G to do work = 15/3 × 4 = 20
Page 15 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

One day work of I = 420/15 = 28 unit Let the total work be 180 unit

For the last 2 days F worked alone, One day work of A = 180/10 = 18 unit

So work done by F in last 2 days = 30 × 2 = 60 unit One day work of E = 180/20 = 9 unit

Remaining work = 420 – 60 = 360 unit One day work of G = 180/20 = 9 unit

360 unit of work done by F, I and E together in = One day work of D = 180/18 = 10 unit
360/(30 + 28 + 21) = 4 (44/79)
One day work of J = 180/24 = 7.5 unit
27. Answer: C)
Quantity A:
Time taken by H to do work = 12/4 × 5 = 15 days
Time taken by A, E and G = 180/(36) = 5 days
Let total work = LCM (15, 18, 15) = 90 unit
Quantity B:
One day work of B = 90/15 = 6 unit
Time taken by D, E and J = 180/(26.5) = 6(42/53) days
One day work of D = 90/18 = 5 unit
∴ Quantity A < Quantity B
One day work of H = 90/15 = 6 unit
(29 – 31): Common Explanation:
From I,
Time taken by P alone to complete the work = x days
Work done by B, D and H in 2 days = (6 + 6 + 5) × 2 =
34 unit Time taken by R alone to complete the work = (x + 14)
days
Remaining work = 90 – 34 = 56 unit
Efficiency of R = 1/(x + 14)
Work done by D and H = 56/11 = 5(1/11) days
Efficiency of Q = 1/(x + 14) × 100/125 = 4/[5(x + 14)]
Total time taken = 2 + 5(1/11) days
Efficiency of S = 4/[5(x + 14)] × 7/6 = 14/[15(x + 14)]
From II,
According to the question,
13(1/3)% of work = 13(1/3)% of 90 = 12 unit
11/x + {1/x + 4/5(x + 14)} × 15 + {14/15(x + 14)} × 10
12 unit of work done by B in = 12 /6 = 2 days =1

This means that B has worked for 2 days, 11/x + 15/x + 12/(x + 14) + 28/3(x + 14) = 1

We can find the answer using this statement too. 26/x + 64/3(x + 14) = 1

∴ Question can be answered using either of the (3x + 42) × 26 + 64x = 3x2 + 42
statement.
78x + 1092 + 64x = 3x2 + 42x
28. Answer: A)
3x2 – 100x – 1092 = 0
Page 16 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

3x2 – 126x + 26x – 1092 = 0 (32 – 34): Common Explanation:

3x(x – 42) + 26(x – 42) = 0 M = Man, W = Women, C = Child

(x – 42)(x + 26) = 0 X women can do a work in 2Y days and 1.5X man can
do the work in Y days.
x = 42, x = - 26
⇒ 2XY W = 1.5XY M
So, x = 42
⇒ M/W = 4/3
Time taken by P alone to complete the work = 42 days
X women can do a work in 2Y days and 3X child can do
Time taken by R alone to complete the work = (42 + 14)
the work in 4Y days.
= 56 days
⇒ 2XY W = 12XY C
Time taken by Q alone to complete the work = 5(42 +
14)/4 = 70 days ⇒ W/C = 6/1

Time taken by S alone to complete the work = 15(42 + ∴M:W:C=8:6:1


14)/14 = 60 days
8 males, 8 females and 8 children together can do the
29. Answer: B) work in 22.5 days.

Required value of x = 42 Total work = 22.5(8 × 8 + 8 × 6 + 8 × 1) = 2700

30. Answer: D) 32. Answer: D)

S takes 60 days to complete the work alone. 2.5X females complete the work in 24 days.

The time taken by S to complete the 60% of the total 2.5X × 24 = 2700
work = 60 × 60% = 36 days
⇒ X = 45
31. Answer: C)
X women can do a work in 2Y days.
Let the total work = 420 units
⇒ 2XY = 2700
Amount of the work done by P in one day = 420/42 = 10
units ⇒ 2 × 45 Y = 2700

Amount of the work done by Q in one day = 420/70 = 6 ⇒ Y = 30


units
33. Answer: E)
Amount of the work done by P and Q in one day = 10 +
Number of days taken by 10 males and 12 females
6 = 16 units
together to complete the work = 2700/(10 × 8 + 12 × 6) =
Time taken by P and Q to complete the work = 420/16 = 17(29/38)
26.25 days
34. Answer: E)
Page 17 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

Number of days taken by 12 females together to now, Pradeep works at 120% of 15 = 18 units
complete the work = 2700/(16 × 6) = 28(1/8)
Nikku at 5/6 of 18 = 15 units
35. Answer: B)
Pradeep + Nikku’s 2 days’ work = 33
Let work = 180 units
In 10 days ……………….33*5 = 165 units
pulkit’ 1 day’s work ……….20 ( work/ no. of days
taken) Remaining ………15 units ….Pradeep does…18 days a
day so to do 15 units He will take 5/6 days therefore total
paras’s 1 day’s work ……..20 time taken = 10* 5/6 days

neha’s 1 day’s work……….7.5 38. Answer: D)

happy’s 1 days work……..7.5 Punit’s 1 day’s work ………15 units so to do 25% work
( assumed total work = 180) = 45 he will take 3 days
ruhi’s 1 day’s work ……..20
to do 10% work..i.e 18 units nikku will take 1 days
paras and pulkit worked for 2 days…..(20+20)*2 = …noe remaining work = 180-63 = 117
80…remaining work = 100
to do 117 , suman will take 117/9 = 13 days ( suman’s 1
now for 2 days ( 7.5+7.5+20)*2 = 70 …..remaining work day’s work = 180/20 = 9 units)
= 30 ..so 30/180 = 1/6
Total days = 3+1+13 = 17 days
36. Answer: C)
39. Answer: A)
total days taken by boys to do the work = 180/100 = 9/5
days Ashu’s 1 day’s work …180/15 = 12 units

days taken by 4 girls = 180/45 = 4 days …difference = 4- In 5 days he should have done …60 units
9/5 = 11/5 days
but he did……………….180/4 = 45 units
37. Answer: B)
so remaining work = 135 units so complete it in 10 days
Pradeep’s one day’s work ………..180/12 = 15 units he should do 135/10 = 13.5 units per day

N one day’s work…………….180/10 = 18 units therefore increased efficiency … 13.5 – 12 = 1.5 >>
1.5*100/12 = 12.5%
40. Answer: C)

Page 18 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

41. Answer: D)

42. Answer: C)

Page 19 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

43. Answer: A)

Page 20 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

44. Answer: D)

Page 21 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

45. Answer: E)

Let time taken by Virat and Rahul together to complete 60% of Job-Q = t

So, time taken by Virat and Sourav together to complete Job-Q = t/0.6

Therefore, 1/462 + 1/420 = 0.6/t

t = 132 days

Payment for 40% of the job = Rs. 62000

So, Payment for 60% of the job = 62000*6/4 = Rs. 93000

Therefore, daily payment to Virat and Sourav together = Rs. 93000/132 = Rs. 704.54

46. Answer: E)

Let Total Number of days to complete job = t

100/315 + (t-50)/252 + t/420 = 1

400+5(t-50) +3t/1260 =1

150+8t = 1260 =138 3/4days


Page 22 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

47. Answer: A)

Part of Job-S done in one day when Dhoni and Sourav work together = 1/140 + 1/70 = 3/140

Part of Job-T done in one day when Dhoni and Sourav work together = 1/300 + 1/120 = 7/600 7/600 < 3/140

So, Job-S will be completed first.

Number of days spent on Job-S = 140/3 = 46.6777 i.e., 47 days

Number of days spent on Job-T before Virat joined in Job-T = 46 days

Portion of Job-T done in 46 days = 46*7/600

Remaining portion of Job-T = 1 – 46*7/600 = 278/600

Let in t days the remaining portion of Job-T done will be by Dhoni, Sourav and Virat.

So, in one day the amount of work done by three of them working together is=1/300 + 1/120 + 1/150.

(1/t)(278/600) = 1/300 + 1/120 + 1/150 => 278/t = 11 = t = 278/11

Therefore, total number of days = 47+46+278/11 = 130 1/11 days

48. Answer: D)

Time taken to complete Job-P = A

1/A = 1/144 + 1/80 + 1/90 + 1/60 + 1/48 => A = 720/49 i.e. 15 days

Time taken to complete Job-Q = B

1/B = 1/770 + 1/924 + 1/420 + 1/462 + 1/385 => B = 4620/44 i.e. 105 days

Time taken to complete Job-R = C

1/C = 1/315 + 1/420 + 1/252 + 1/90 + 1/105 => C = 1260/38 i.e. 34 days

Time taken to complete Job-S = D

1/D = 1/84 + 1/168 + 1/105 + 1/70 + 1/140 => D = 840/41 i.e. 21 days

Time taken to complete Job-T = E 1/E = 1/225 + 1/180 + 1/150 + 1/120 + 1/300 => E = 1800/51 i.e. 36 days

Therefore, total number of days =15+105+34+21+36 = 211 days

49. Answer: B)

[ M1×D1 ] / W1 = [ M2×D2 ] / W2
Page 23 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams
Expected DI & Caselet Questions Based on Time and Work for Upcoming Mains Exam

We using this form, we will get the following

(150 × 152)/3/5 = (?× 100)/2/5

We solving this, we get the, 2/5 of the work completed by 152 men.

So we need 2 more men to complete work on time. I.e., 152-150 =2 men

50. Answer B:

= (770+924+420+462+385)/ 5

392.5

THE COMPLETE Static GK Capsule for Upcoming Exams

Check Here for Last 6 Months Current Affairs PDF

Click Here for More Expected Monthly Current Affairs Questions

Monthly Current Affairs PDF 2020- Click Here to Download

Monthly One Liner Current Affairs PDF - Download Now

Click Here to Join Our What’s App Group & Get Instant Notification on
Study Materials & PDFs
Click Here to Join Our Official Telegram Channel

Page 24 of 24
Subscribe Our Yearly Mock Test Pack to Get 1000+ Mock Test for Bank+SSC+Railway Exams

You might also like