COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
COMPANY
QUALITY MANAGEMENT PLAN
(RK-QMS-0001)
1
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
TABLE OF CONTENTS
1. POLICY STATEMENT ………….………….……………..………………………………………………….. 4
1.1 INTRODUCTION ………………………………………………………………………………………… 6
1.2 SCOPE ………………………………………………………………………………………… 6
1.3 PURPOSE ………………………………………………………………………………………… 6
1.4 DEFINITION OF TERMS …………………………………………………………………………….. 7
1.5 ABBREVIATIONS ………….……………..……………………………………………………………… 7
1.6 QUALITY PLAN’S PURPOSE, RESPONSIBILITIES AND AUTHORITY ………. 8
1.6.1. PURPOSE …………..……………...……………………………………………….. 8
1.6.2. RESPONSIBILITIES ....……………………………………………………………… 8
1.6.3. CONTROL OF PROJECT QUALITY PLAN …….……………………………………. 9
2. PROJECT ORGANIZATION ……………..……………………………………………………………… 10
2.1. MAIN PROJECT OBJECTIVES FOR THE SCOPE OF WORKS .………………….
2.2. ORGANIZATIONAL CHART ………………………………………………………………….
3. DESCRIPTION OF ACTIVITIES ………………………………………………………………….
3.1. CONTRACT REVIEW ……………..………………………………………………………………
3.2. PERSONNEL COMPETENCE / HR MANAGEMENT ……………………………….
3.2.1. COMPETENCE OF QUALITY PERSONNEL ……………………………….
3.3. DATA AND DOCUMENT CONTROL …….…………………………………………….….
3.4. MATERIAL CONTROL, IDENTIFICATION AND TRACEABILITY …………………..
3.4.1. CONTROL OF SUPPLIER MATERIAL/PRODUCT .………………….
3.4.2. PRODUCT IDENTIFICATION AND TRACEABILITY .………………….
3.5. INSPECTION AND TESTING ………………………………………………………………….
3.6. CONTROL OF SUBCONTRACTORS ACTIVITIES …….…………………………………….
4. PROJECT QUALITY ACTIVITIES PROGRAMME ..…………………………………………
4.1. GENERAL ……………..………………………………………………………………………….
2
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
3
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
1. POLICY STATEMENT
The policy and objectives for the PROJECT shall be as follows:
Policy:
To establish, implement and maintain an efficient and effective quality system for
application to the project works including the control verifications to be put in place
to assure quality during each stage of the work.
To ensure that products are supplied and constructed in accordance with Client
COMPANY’s requirements as stated in the CONTRACT, and to ensure that the
requirements are determined, fulfilled and where practical exceeded to enhance
customer satisfaction.
To implement the quality system on all activities and operations that affect the
quality of the products and services provided under the CONTRACT.
To review and monitor the quality system at regular intervals throughout the
contract period both to improve the system and detect and correct any adverse
trends by taking the necessary executive action.
Objectives:
To provide products and services for the realization of a successful project that
meets the contract and project’s requirements to the satisfaction of the Client
COMPANY.
To meet all quality requirements and technical performance criteria for the plant.
To meet all commercial performance criteria (namely schedule and cost) by efficient
use of technological, human and material resources.
The core objectives of the Arkay Quality Management Plan are as follows:
The QMP will be subject for periodical reviews to establish that the QMP remains
relevant to project needs
Ensure that the personnel involved in the project are adequately trained and
qualified, and that tasks and responsibilities have been correctly assigned
Demonstrate, by means of documented quality record, that the work has been
carried out and inspected to the required level of quality
To monitor, measure and be focused on the COMPANY satisfaction throughout all
activities and phases of Project execution
Furthermore, all measures shall be taken in order to ensure safety and to safeguard
personnel during the performance of the work
________________
HAYDEE J. DE GUIA
Chief Executive Officer
5
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
1.1. INTRODUCTION
This plan identifies the key interfaces, the allocation of responsibilities and the
methods and controls to be applied. With reference to Standards, Codes of
Practice, Client COMPANY procedures and COMPANY’s processes are made
where appropriate. These planned arrangements will enable the Company to
clarify requirements, minimize risk and ensure that potential errors are identified
and corrected. It is important for the success of the project that all staff working
on it is aware of these arrangements.
1.2. SCOPE
1.3. PURPOSE
6
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
This also to highlight the processes needed for the Quality Management Plan for
continual improvement.
1.5. ABBREVIATIONS
1.6.2. RESPONSIBILITIES
The Project Manager in collaboration with the Project Director and the
Quality Engineer, are responsible for the preparation and review of the
Quality Management Plan in accordance with the standard criteria of
CONTRACTOR and the COMPANY’s specifications.
The Project Manager is responsible for the issue, distribution and up-
dating of the Quality Management Plan for the duration of the Project.
Quality Personnel will assist Project Manager and its Project team to
ensure that all Quality Premises and guidelines as defined into the actual
Quality Management Plan are correctly implemented at any activity stage
or level by means of monitoring and auditing the work performance in
respect of the established quality program and objectives.
All Project Functions will have to be committed to the best result in terms
of information needed to be tracked and relevant records.
The Project Manager will be responsible for all those aspects connected
to surveillance activity and will also have the necessary authority to
8
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
In case the Project Manager will be absent, the Quality Engineer can act
on his behalf.
The Quality Management Plan and all the Work areas Project Quality
Plans are issued for this specific Project as controlled documents and are
subject to COMPANY’s approval prior to their final distribution and
implementation within the Project organization.
The Project Director shall verify and approve the Quality Management
Plan and Work areas Project Quality Plans.
It is understood that any new revision shall replace and superseded all
previous ones.
The original of the Quality Management Plan and Work areas Project
Quality Plans shall be filed within the Project Filing System in Quality
Department under the control of a Document Controller.
9
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
Each holder of the Quality Management Plan and Work areas Project
Quality Plans copy shall take all necessary steps in order to familiarize
with the contents of this document and suggest improvements.
Copies of the Quality Management Plan and Work areas Quality Plans
shall be distributed by the Document Controller (DC) to the involved
Project functions/organizations as indicated in the following "Project
Quality Plan Distribution / involvement Matrix".
2. PROJECT ORGANIZATION
2.1. MAIN PROJECT ACTIVITIES FOR THE SCOPE OF WORK
2.1. Overall Project Management (Work permits; Permitting Support)
2.2. Design Engineering (Detail design)
2.3. Installation Engineering (Installation analysis, Installation Manuals)
2.4. Procurement & Material Handling (Procurement; Company Provided Items;
Material Control; Material Traceability; Handling and Storage)
2.5. Fabrication
2.6. Logistics and Transportation
10
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
2.1. Top management shall provide evidence of its commitment to the development
and implementation of the quality management system and continually
improving its effectiveness by:
communicating to the organization the importance of meeting customer as
well as statutory and regulatory requirements,
establishing the quality policy,
ensuring that quality objectives are established,
conducting management reviews, and
ensuring the availability of resources
11
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
The Quality Management Team will solely participate in the quality assurance function
and will not be involved in any other aspect of the construction effort. This team will,
however, possess all of the credentials, capabilities, and experience of an independent
design/construction oversight team. The duties and responsibilities of each position are
described below. One individual or entity may perform multiple construction quality
assurance responsibilities.
PROJECT DIRECTOR
The Project Director is responsible for overseeing the entire project from start to finish.
He or She must keep in constant communication with project managers on-site as well
as the client. A project director has the overall responsibility for the successful initiation,
planning, design, execution, quality, monitoring, controlling and closure of a project. The
project director responsibilities are:
Planning and defining scope
Resource planning
Time estimating
Cost estimating
Creating charts and schedules
Risk analysis
Controlling quality
PROJECT MANAGER
The Project Manager is solely responsible for the on-site implementation. He or She
must see to it that it was properly carried out and thoroughly implemented. Project
Managers must be persistent and reporting on a daily basis any development or issue
might arise to the Project Director.
12
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
SITE ENGINEER
The Site Engineer must promote the best construction practices. Undergo activities and
practices that comply with the procedures of the company and the specification.
Assured the is completed and delivered without any defect and delay.
SITE SUPERVISOR
The Site Supervisor is the direct response for any problems or injuries that occur on a
job site. He oversees the project on-site and tracks workers and completion of tasks on
schedule.
3. DESCRIPTION OF ACTIVITIES
3.1. CONTRACT REVIEW
The Contract Review activity, performed by the Project Director with the support
of the Project Team Members, is the first step to be taken after Contract award
or for each new revision of an existing CONTRACT document or any issue by
COMPANY of new CONTRACT document.
This review gives the right understanding of the CONTRACT requirements and to
ensure that all pending items have been solved and that all qualifications and
modifications accepted have been incorporated in the CONTRACT documents.
Project Director is in charge to implement with the Project key Managers the
Contract review process, by defining the list of team personnel to be involved in
the review of each specific CONTRACT document/ deliverable, to appoint the
review leader for each document/deliverable, to define and agree with the
Project key Managers the completion dates for an exhaustive and timely review
and to coordinate with COMPANY the possible required clarification meetings.
The Contract review phase is directly managed by the PA, coordinated by the PD
and supported by the Project Team members, with the involvement of all
interested DL of the Project Team.
13
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
Records of the Contract Review activities, must be kept by the PM within the
Project Master file
The Professional Role System identifies and contains the description of all
possible Professional Roles entailing the Job Description (Mission and Tasks),
attributes of Seniority, Job Title(s), Professional Skill set and Personal Skill set.
The Personal Skills are characteristics, traits and capabilities of the resource that
generate a superior performance.
The Professional Skills are the collection of all the Arkay Business specific
characteristic competencies.
The Skill evaluation system has the aim to identify the Skill Profile of the
employee in order to individuate strong and weakness skills and foresee possible
job mobility between different functions or in other job activities; in particular,
the aim of the system is:
identifying technical and professional skills and competencies of people with
reference to those requested and expected for their professional roles;
driving development & management actions of people, supporting their self-
development;
assigning and certifying the professional role of people and their seniority;
giving input for training plans and knowledge management systems;
15
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
The Professional Skill Evaluation is a system to assess and measure the level of
ownership of the:
Professional Skills
Personal Skills of a resource by comparing them with the level of knowledge
needed for the professional role in which he is employed.
The Gap analysis results are the input to plan actions for each employee - to
meet development needs or to improve an outstanding professional profile - or
at the level of the overall professional area.
The standard surveying or updating of the individual skills is carried out at least
every two year; moreover, every time the responsible Manager proposes to
change the role of the employee for Project or business needs, the skill
evaluation has to be applied.
Project Director and Project Manager jointly review and accept the proposed
candidates, based on the specific competence and experience that the Project
requires.
The Corporate Training Department defines and develops the Group training
plans for each professional area.
16
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
Referring to the Quality personnel, each year the Quality Manager evaluates the
training necessities of his personnel, and for each position, plans the necessary
actions to be taken both internally and externally.
Document and data control is the formal control of all documents and data
related to the Quality process within the Scope of Work. Controlled documents
shall be identified for their development, approval, issue, revision, distribution,
maintenance, use, storage, security, obsolescence or disposal.
17
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
Changes to controlled documents and data are subject to the same review and
approval cycle as the original issue. Obsolete and/or superseded documents shall
be removed from circulation to preclude their use.
A centralized document control center will be located in the ARKAY Main Office
at Chino Roces Avenue, Makati City.
This office will have the function of handling all Project documentation (storage
of electronic and hard copies) and manage the interface with COMPANY
document management system.
The Quality methods and procedures outlined in this QMP will be used to verify
and document that the Project is completed in accordance with plans and
specifications and codes, standards and practices referenced therein.
All data and documents garnered will be treated as detailed in the Document
and Data Control Procedure.
CONTRACTOR shall ensure that all materials purchased and free issued by
COMPANY are handled and controlled effectively, and that materials are
protected and preserved during handling, storage, packaging, transportation and
installation.
18
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
19
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
The local laws and international regulations shall be adhered for storing the
classified and hazardous materials. The personnel shall be trained in the
handling and storage of hazardous materials.
Preservation of material at Offshore Facility will be done by other
Contractors.
3.4.1.1. The COMPANY supplied products will be controlled upon receipt from
the COMPANY’s warehouse. Upon receipt, a receiving inspection shall
be carried out including checking of accompanying documentation
shall be checked for correctness and any deficiencies shall be
processed through the system and COMPANY shall be advised.
Quality Control Plans are defined in accordance with the Project Quality Plan and
the contract time schedule.
The plan indicates and organizes all the inspections and tests to be performed on
constructed works (or parts thereof) to verify their compliance with Project and
contract requirements.
Together with the Quality Management Plan and relevant documents indicated
as references, the Work area Project Quality Plan will be distributed to the work
area personnel only for their use and implementation.
The proper distribution of the above will be done by the Document Controller
based on established Documents Distribution Matrixes.
Quality objectives are defined with respect to the following areas and monitored
in accordance with the relevant standard.
22
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
1. Project Management
2. Engineering
3. Procurement
4. Training
5. Installation
6. Quality
7. HSE
The set of Objectives and KPIs will be established during the Project life,
together with all the Department Managers. They will be approved by the
Project Director and monitored during the year for verifying their
accomplishments, forecast and eventual necessary corrective/ preventive
actions to be defined. The monitoring will be done 2 times per year.
Regarding the training for the special processes as well as Welding, specific
Project procedures shall be dedicated to arrange these activities and to qualify
the operators (welders) in compliance with the COMPANY’s Project
specifications/requirements.
During the tool box talks, discussion will be held to identify any potential in-
process problems that may or have occurred, as well as the technical solutions
applicable and / or implemented.
The applicability of this Audit plan is internal for those activities related to Arkay
scope of work and external for the subcontracted activities or major items to be
purchased.
24
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
The planning of the audits shall consider also the contractually requirements.
The planning of quality audits is proposed by the Project Manager, reviewed and
approved by the Project Director.
The audits are carried out by qualified personnel with no direct executive
responsibility for the activities being audited. The selection of auditors and the
conduction of audits must ensure objectivity and impartiality of the process.
The test and inspection records are checked by the competent Quality personnel,
who monitor the inspection status and authorize acceptance after the
verification that inspection requirements have been met.
The Quality personnel ensure the collection and filing of the inspection records,
after checking their completeness and compliance with the Quality Management
Plan.
25
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
In order to ensure proper and effective execution of this activity, the Project
Quality Management Review Meetings shall be organized 2 times per year.
During the review meeting the following topics shall be analyzed /discussed:
Follow-Up on findings identified during previous meetings
Project Quality Program documentation status
Auditing activities status : performed Audits vs planned Audits, forthcoming
Audits, unscheduled
Audits deemed necessary, brief presentation of Audits results highlights
Preventive / Corrective Action Requests Status (Raised, Closed, Outstanding)
Customer Complaints status
Training / Induction activities status
Non-conformances status (Internal, to SUBCONTRACTORs / VENDORs, Non
Conformities from
Customer)
Observations / Recommendations
QA/QC resources status and needs
Plan with Initiatives and Actions to be implemented, with responsibilities and
timeframe.
The measure of Customer Satisfaction is one of the basic points and fundamental
elements for implementing the improvement of the Quality Management System
processes.
For this reason all the COMPANY functions are involved at the operational level
in order to meet this objective.
The results of these analyses will represent one of the input for the
CONTRACTOR’s Management Review meetings.
5. COORDINATION PROCEDURE
5.1. Internal coordination of management decisions, information, documents, etc.,
within the organization on site and Site Office and COMPANY project teams is
covered by the various sections of this QMP and associated documents.
27
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
5.3. Coordination with subcontractors shall be agreed before award of subcontract and
shall cover details such as: addresses for documents, standard form of transmittal,
format and number and addressees of copies of documents / data, authority for
approval, etc.
5.4. Coordination with local and national authorities shall be detailed at the
mobilization stage in full consultation with COMPANY and the applicable section of
CONTRACT.
6. PROCUREMENT
6.1. PROCUREMENT PLAN
6.1.1. Contractor shall prepare a procurement plan for materials and
consumables required for the hook-up and pre-commissioning scope of
the project.
6.1.2. Vendor list of prospective Suppliers shall be prepared after taking into
consideration their Quality Systems, product standards, documented
experiences or by carrying out Supplier evaluations.
6.1.4. Purchasing of all permanent works materials will be carried out and all
subcontracts will be issued.
28
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
7.1.4 The Quality Manager shall carry out the trend analysis of the NCRs and
adverse trends noticed shall be subjected to corrective and preventive
actions.
7.1.5 After reviewing the records, the Quality Manager shall initiate corrective
and preventive actions, as necessary to prevent recurrence of serious
non conformities.
7.2.3 “Minor” non-conformities are also reported, however they require less
remedial actions, and are monitored to aid continuous quality
improvement.
7.3.1 The Quality Manager, on the basis of trend analysis, root cause of
analysis and other appropriate sources of information such as processes
and work operations that affect quality, audit results or customer
complaints, will initiate preventive actions in order to eliminate potential
causes of non-conformities and make recommendations for
improvement.
7.3.2 Additionally the Quality Manager shall make careful assessments of the
documents and information listed below to determine trends in
processes that give an opportunity for preventive action or process re-
design. A significant element of this activity is historical performance
information and lessons learned.
Input documents for analysis shall include but not be limited to:
Management review reports
Audit reports
Supplier non-conformance and concession requests
Work completion reports
Feedback, Compliments and complaints from COMPANY
Lessons learnt database
8. REPORTING
8.1. A Monthly Quality Report shall be prepared to demonstrate the effective
implementation of the quality management system. As a minimum, the
following shall be included:
Listing of Non-Conformance Reports Issued, Closed and Pending.
Listing of Quality System Audits
Listing of all defective or rejected material received on site.
Welding rejection rate together with a chart showing the history of the
welding rate
Site Engineer will prepare and submit to Client a Monthly Progress Report. These
reports will present summaries of the important information relating to the monthly
construction activities gathered from the various records described below. The Monthly
Progress Report will include, if necessary, any proposed or field approved modifications
and justifications to the Work, the Drawings, the Special Provisions, Technical
Specifications, or Site-Specific Health and Safety Plans or other submittals. The Monthly
Progress Report will include Contractor collected information as well as a summary of
the laboratory analytical results if so required.
30
DOCUMENT TITLE: DOCUMENT NO.
RK-QMS-0001
COMPANY QUALITY MANAGEMENT PLAN SHEET NO. REVISION NO.
01
9. ATTACHMENTS
Attachment – 1 : Matrix of Responsibilities for the contractor
Attachment – 2 : List of Quality Management Procedures
Attachment – 3 : Project Organization Chart
31