You are on page 1of 3

No.

Surat : 0398/Kitchen/Jakarta Surabaya, 25 Agustus 2020


Kepada : Kitchen
U/p : Bp.
Telp./Fax :
Email :

PROYEK : Pipa Gas LPG Kitchen


LOKASI : Jakarta

Dengan hormat,
Bersama ini kami mengajukan penawaran harga instalasi pipa gas LPG 50KG dengan rincian :

HARGA JUMLAH
AREA URAIAN VOL SATUAN
SATUAN HARGA
R.GAS HIDDER MANIFOLD
ballvalve gas kitz bronze 1/4" 5 pcs 243,000 1,215,000
Regulator medium 50kg/jam USA 1 unit 2,610,000 2,610,000
elbow las 1½" 2 pcs 27,000 54,000
doubel napel 3000psi 3/4" 3 pcs 36,000 108,000
presure gauge 10bar Germany 1 pcs 261,000 261,000
incian valve 1/4" 5 pcs 27,000 135,000
selang gas 50kg Germany 1/4" 4 pcs 261,000 1,044,000
dop las sch 40 2" 2 pcs 45,000 90,000
union gas 3000psi 3/4" 2 set 108,000 216,000
reduser las sch 40 1½" x 3/4"" 1 pcs 54,000 54,000
pipa gas SMLS sch 40 2" 1 batang 819,000 819,000

SUB TOTAL 1 6,606,000

PIPA MAIN LINE


ballvalve gas kitz bronze 3/4" 1 pcs 351,000 351,000
ballvalve gas kitz bronze 1/4" 1 pcs 243,000 243,000
incian valve 1/4" 1 pcs 27,000 27,000
preseur gauge 2.5kg 2½" Germany 1 pcs 252,000 252,000
elbow las sch 40 1" 6 pcs 18,000 108,000
pipa gas SMLS sch 40 1" 4 batang 414,000 1,656,000

SUB TOTAL 2 2,637,000

DAPUR TITIK API/KITCHEN


ballvalve gas kitz bronze 1/4" 1 pcs 243,000 243000
ballvalve gas kitz bronze 1" 1 pcs 414,000 414,000
ballvalve gas kitz bronze 1/2" 8 pcs 261,000 2,088,000
incian valve 1/4" 1 pcs 27,000 27,000
preseur gauge 2,5kg 2½" Germany 1 pcs 252,000 252,000
napel selang 1/2" x 3/8" 8 pcs 18,000 144,000
elbow las sch 40 1" 2 pcs 18,000 36,000
regulator lowpres 5kg/jam Italy 8 pcs 423,000 3,384,000
reduser las sch 40 1½" x 1" 2 pcs 27,000 54,000
elbow drat 3000psi 1/4" 1 pcs 36,000 36,000
pipa gas SMLS sch 40 1" 1 batang 414,000 414,000

SUB TOTAL 3 7,092,000

MATRIAL SUPORTING
besi unp 50 x 6000 1 batang 306,000 306,000
kawat las RB26 2,6MM 1 pack 189,000 189,000
cat kuning Ftalite/emco 1 liter 72,000 72,000
cat zyncromet kansai/nipon 1 liter 63,000 63,000
tiner A special * 1 liter 36,000 36,000
kuas 2" 2 pcs 12,000 24,000
dinabolt M10 x 60 24 pcs 3,000 72,000
ubolt 1½" 4 pcs 14,000 56,000
ubolt 1" 16 pcs 9,000 144,000
batu grinda cutting 4" 8 pcs 8,000 64,000
senai/ngedrat 27 titik 27,000 729,000
N²(alat test tekan kebocoran) 1 lis 900,000 900,000
seltape onda 27 rol 6,000 162,000
biaya kirim material onsite + akomodasi 1 lis 2,700,000 2,700,000

SUB TOTAL 4 5,517,000

R.GAS BYPASS SOLENOID SYSTEM


ballvalve gas kitz bronze 3/4" 3 pcs 351,000 1,053,000
union 3000psi 3/4" 3 set 108,000 324,000
doubel napel 3000psi 3/4" 4 pcs 36,000 144,000
solenoid gas koil kotak 3/4" Germany/Italy 1 unit 2,610,000 2,610,000
gas detector Harpabek 3 unit 594,000 1,782,000
panel alarm gas 3 zone Harpabek 1 unit 2,520,000 2,520,000
kabel NYA 1,5MM X 50M 2 rol 135,000 270,000
kabel LAN UTP cat5e belden 36 M' 9,000 324,000
flexibel 5 m' 9,000 45,000
te dos clipsal 5 pcs 18,000 90,000
pipa clipsal 10 batang 27,000 270,000
elbow clipsal 8 pcs 12,000 96,000
klem pipa clipsal 24 pcs 4,500 108,000
isolasi hitam nachi 1 rol 27,000 27,000
pisher 50 set 1,000 50,000
kabel power 1 phas NYM 1,5mm x 50m 1 rol 630,000 630,000
SUB TOTAL 5 10,343,000

BIAYA TEKNISI CENTRAL LINE PIPA GAS LPG 3,600,000


BIAYA TEKNISI SAFETY BYPASS SOLENOID PANEL ALARM SYSTEM 1,800,000
SUB TOTAL 6 5,400,000
TOTAL 1,2,3,4,5,6 : 37,595,000

System & cara pembayaran :


[a] Uang muka (DP) ...... 50% Total Proyek
[a] Pekerjaan selesai ... 50% Total Proyek
[a] Pembayaran pekerjaan 100% paling lambat 1 hari setelah pekerjaan selesai
[a] Pek. Perubahan & tambahan di progress sesuai on site
[a] Pembayaran DP dan pelunasan melalui rekening Bank BCA AN: Muhammad Nidhom 6750-459-453

Catatan :
(1) Listrik kerja,lokasi gudang,scafolding/tangga disediakan pemberi tugas
(2) Volume tersebut masih berupa estimasi/volume,real akan disesuaikan dilapangan
(3) Pekerjaan dapat diproses setelah penawaran di ACC & uang muka [DP] dibayarkan
(4) Harga dapat berubah tanpa pembeitahuan, penawaran berlaku 30 hari setelah terbit
(5) Harga tersebut diatas sudah termasuk biaya kirim material onsite dan akomodasi 2 teknisi

Demikian penawaran ini kami sampaikan. Apabila ada hal yang kurang jelas silahkan hubungi -
saudara Muhammad Nidhom di nomer HP (082113854445).

Menyetujui Hormat kami

.................... M.NIDHOM

You might also like