Professional Documents
Culture Documents
I
I General Notes:
I •
SPT
Penetration, N-
Value(blows/ Density of
I foot)
<4
Sand
Very loose
4> (degrees)
<29
4 - 10 Loose 29 - 30
I 10 - 30
30 - 50
Medium
Dense
-- 30- 36
36-41
---
>50 Very dense >41
I • Planning is done in the scheduling process
I
• Work Breakdown Structure (WBS) is the first thing to be done after project definition havf> been
I •
completed
WBS organizes and defines the total scope of the project
I • the lowest level of WBS is work packages or activities that can then be scheduled, cost
estimated, monitored and controlled
• WBS does not show activity sequences
I
• Schedule provides full map of activities to complete a project
• Schedule determines the time frame and responsibilities of the activity
• Schedule is a vision of how the project will be performed; monitoring measuring and managed
progress.
•
...~Pl.........
h•oh!Oollll
'"'°"•'~ D
,_,.. .........., D
-Ill~
lha.. rt~
°"""'''..... __
Sldo ,.,...,tJ -
I •
•
Activity Duration= Work Quantity/Production Rate
An alogous Estimation is using actual durations of previous similar projects to estimate durations
• PERT (Program Evaluation and Review Technique) is used to estimate activity durations
I i
Pessnistc
I
(I>)
I
I
I •
• Expected time: (a+ 4m + b)/6
I
• Critical Path Method (CPM) is the longest path through a project which will determine the
r earliest time for completion of the proj ect (longest total duration of a· path and 0 float)
• Forward Pass Computations is made to determine the earliest start and finish times
• Backward Pass Computations is made to de~ermine the latest start and finish times
• Float is the latest point in time an activity can be delayed from its earliest start without delaying
the project ~
• Gantt Charts are a combination between Bar chart and Milestone chart
I •
)i> (ACWP) Actual Cost of Work Performed
Estimate To Complete (ETC) is the expected cost needed to complete all the re maining work for
a schedul e activity
I .,
•
Budget Al Completion {BAC) is the sum of the budget for each phase of the project
Estimate At Completion (EAC) is the expected total cost of a schedule activity
I • Variance At Completion {VAC) is the difference between the total baseline cost (BAC) and the
estimated total cost (EAC)
• Cost Variance (CV)= Earned Value (EV} - Actual Cost (AC)
I •
)> [-ve CV==== the project is over budget]
Schedule Variance {SV) =Earned Value (EV) - Planned Value (PV)
I •
)i> [-ve SV === the project is behind schedule]
Cost Performa~ce Index {CPJ) = EVI AC
}> [CPI less than 1, cost overrun of the estimate (loss)]
~
)i> [CPI more than 1, cost under run of the estimate (gain)]
• Schedule Performance Index (SPI} EV/PV =
)i> [SPI less than 1, less work was completed than was planned (loss)]
I •
);:> [SPI more than 1, more work was completed than was planned (gain)]
EAC =AC+ (BAC - EV) [Assuming that balanced work will have EV= AC]
• EAC =[AC + (BAC - EV)]/CPI [Assuming that balanced work will have EV01d - AC01d =EVnew - ACnew]
• The re<:1sons for unnecessary costs that can be solved by Value Engineering (VE) are:
)i> Lack of information
)i> Lack of ideas
)i> Temporary circumstances
)i> Honest wrong beliefs
)i> Habits and attitudes
)i> Changes in owner requirements
)i> Lack of communication and coordination
)i> Outdated standards and specifications
• American Concrete Institute (ACI) is used to design the mix of concrete
•I
• The lower the water - cement ratio, W /C, the higher the concrete strength
• Aim is to get concrete mixtures of optimum strength at minimum cement content and
acceptable workability
• The compressive strength of concrete is the highest and measured on the 28th day
• (Air entrainment) The primary purpose of air entrainment is to increase the durability of the
hardened concrete, especially in climates subject to freeze-thaw; the secondary purpose is to
I o
increase w orkability of the concrete while in a plastic state.
Air entrainrnenl abo relieve internal pressure on the concrete by providing tiny ch2mbers for
the expansion of water when it freezes
• Workability: A good mix de~ign must be capable of being placed and compacted, with minimal
bleeding and segregation, and be fin_ish able
• W orkability should be improved by redesigning the mortar faction rather than simply adding
more water
• Slump is the measure of the degree of workability
• ASTM (American Society for Testing and Materials) explains how the slump test should be done
• Mix Design Procedur:e:
1. Required material information - sieve analysis of both fine and coarse aggregate, unit
weight, specific gravities and absorption capacities of the aggregates
2. Choice of Slump - In general, the lowest slump that will permit adequate placement
should be selected
Slump. mm (In.)
3. Maximum aggregate size - t he largest maximum aggregate size (not larger than) t hat will
conform the following limitations:
1/5 the minimum dimension
.
of the structural member
. .
1/ 3 the thickness of a slab
3/4 the clearance cover.
./ These restrictions limit maximum aggregate size to 1.5 inches
./ Reduced maximum aggregate size for a given w/c ratio can achieve
higher strengths
4. Water/Cement ratio:
o Strength can be determined after 28 days (compressive strength)
o ~ -...
I
I Notes to be known:
./ The Strength of Materials: is the ability of the material to resist external forces or resist
I the deformation due to external forces
./ Stress: the internal forces developed in a material to overcome external forces
I ./ The summation of internal angles at any polygon= 180 • (n-2) "n =number of faces"
./ Compaction of backfilling ts used to reduce the air content in the backfilled material
I ---------
./ In Slump test, 3 layers of concrete is required __..
,/ Fast Track Projects is that activ_ities work in parallel (design and build)
./ Crashing a project mean increase resources in order to reduce total durat!on of the
-- ·· ~ .
I project
I Ji
..
I ,•
Pick up the correct statement from the following:
A. The theory of formation of concrete is based on the phenomena of formation of voids
B.The bulking of sand is taken into· account while volumetric proponioning of the aggregates
I C.The dry sand and the sand completely flooded with water, have practically the same volume
D.The expansion and contraction joints are provided if concrete structures exceed 12 min length
E. All the above
I Answer: Option E
1· Initial setting time of cement for asbestos cement products should be not less than
A.30 minutes ' ~ _..__..-r--......_ · ·
R <;() m.inure.;
I C. 75 n:iinutes
D.90 minutes
I Answer: Option D
Pick up the correct statement regarding__~ heat cement from the following:
I A.It possesses less compressive strengtli
B.Its initial setting time is about one hour
Answer: Option E
/
I Name the type of cement from the following for canal linings :
A.sulphate resisting cement
B. rap1d hardening cement
C.quick setting cement
D .pozzuolana cement.
Answer: Option A
If water required for 1 bag of cement is 30 litres, the water cement ratio is :if
A.0.40
B. 0.50
j fo ~w !, 4$~o "'"
,,,_ •
C.0.60
D.None of these.
JolJt' =~· ,~-;, 111
Apswer: Option C
Answer: Option B
Answer: Option D
Answer: Option B
Answer: Option C
Answer: Option E
Answer: Option C
••
-- ~ . '
T he loose pockelS in soil mass can be bridged safely by providing a raft foundation provided the
soft area is smaller than
A .the column spacing
B.ooe-thinl the column spacing
C.halfthe column spacing
D.three-fourth the column spacing
E. none of these.
Answer: Option B
Answer: Option C
The entrained co:Jete is used in lining walls and roofs for making
A.heat insulated
B. sound insulate
C.neither (a) nor (b) · ·
D.both (a) and (b).
Answer: Option D
Answer: Option C .
Raft foundation are generally preferred to when the area required for individual footing, is more
I than
A.25% to total area
B.30% of total area
I C.40% to total area
D.50% of total area.
I Answer: Option D
J Answer: Option E
I The process of keeping concrete moist for a certain period after its finishing, is known as
A.finishing of concrete
B.curing of concrete ~
I C. placing of concrete
D.compaction of concrete
E. none of these.
Answer: Option B
Answer: Option D /
The foundation which consists of a thick reinforced cement slab covering whole area to support
heavy concentrated structural loads, is known as
A.combined footing
B.strap footing
(' rnft fnnting
D.none of these
Answer: Option C
For a wall carrying heavy load on low bearing capacity soil,
A.lean concrete bed is provided
B. thick concrete bed is provided
~.reinforced concrete bed is provided
D .(a) and (c) of the above
E. (b) and (c) of the above.
Answer: Option D
Answer: Option C
Answer: Option E
The formWork including the props can be removed from beams, only after
A.3 day
8.7 days
C.14 days -
0.21 days.
Answer: Option C
Answer: Option C
I
1. The construction joints in buildings are provided after
A.IO m
B.15 m
I C.20m
D.40 m .
E.60 m.
I Answer: Option D
I Answer: Option D
Answer: Option D
Answer: Option E
If h is the difference in level between end points separated by l, then the slope correction is
h2 h4
I -+-
2/ 813 . The second term may be neglected if the value of h in a 20 m distance is less than
1
A.-2 m
-
B. l m
C.2m
D.3 m
Answer: Option D
I
I The accw-acy of measurement in chain surveying, does no t depend upon
A.length of the offset
B. scale of the plotting
I C. importance of the features
D.general layout of the chain lines.
I Answer: Option D
Offsets are measured with an accuracy of 1. in 40. If the point on the paper from both sources of
I error (due to angular and measurement errors) is not to exceed 0.05 cm on a scale of 1 cm== 20
m, the maximum length of offset should be limited to
A 14 14
I B.28.28 m
C.200m
D .none of these.
I Answer: Option B
I E. none of these
Answer: Option B
I 1.
2.
rough orientation of the plane table
the three lines form a triangle of error
3. drawing lines back through the three control points
I 4. select a point in the triangle of error such that each ray is equally rotated either clockwise
or anti clockwise
5. the points obtained by three rays is the correct location.
A.1, 3, 2, 4, 5
I B.1,2,3, 4,5
C.1,4,3,2,5
D.1 , 3, 2, 4, 5
Answer: Option A
!f th~ !1?ngth nf ~ tr::imition curve to be introduced between a straight and a circular curve of
radius 500 m is 90 m. the maximum perpend icular offset for the transi tion curve, is
A.0.70 m
B.1.70 m
C.2.70m
D.3.70m
E.4.70 m
Answer: Option C
Answer: Option E
If 1500 g of water is requ ired to have a cement paste 1875 g of nonnal consistency, the
percentage of water is,
A.20% B.25%
C.30% D.35%
E.40%
Answer: Option B
Answer: Option D
Curing
A.reduces the shrinkage of concrete
B. preserves the properties of concrete
C. prevents the loss of water by evaporation
D.all of the above.
Answer: Option D
Answer: Option E
rl
Answer: Option E
Answer: Option B
Answer: Option E
Answer: Option D
Answer: Option D
Answer: Option C
-..............__________________________ ........
l Permissible compressive strength of M 1~O concrete 0orade is
A.100 kg/ cm
2
2
B.150 kg/cm
I C.200 kg/cm
D.250 kg/cm
2
2
2
E. 300 kg/cm
Answer: Option C X
Slump test of concrete is a measure ofits
A .consistency ,_--
B.c0mpre<\sive st 1·ength
C. tensile strength
D.impact value.
Answer: Option A
Answer: Option E
Answer: Option A
Answer: Option D
High temperature
~increases the strength of concrete ~
B.decreases the strength of concrete v
C.has no effect on the strength of concrete Y
D.none of these.
Answer: Option B
I
I Allowable shear strength of concrete, depends upon
A.she.a r strength '
8. tensile strength
I C.compressive strength
D.none of these.
I Answer: Option A
I Answer: Option C
I Answer: Option E
Answer: Option C
Answer: Option E
Answer: Option E
If the slump of a concrete mix is 60 mm, its workability is
A. v~ylow · ·
B.low
C.medium
D.h.igh ~4lmj. f' 8 J j 1 f
{!
0
)
~ ]j., •O
E. none of these.
Answer: Option C t
.
j
' "
•
l
Answer: Option E •
•
The shortest distance between two places measured along the surface of the earth, is
A.le~gth of the equator between their longitudes
B.length of the parallel between their longitudes
C.length of the arc of the great circle passing through them
D.none of these.
Answer: Option C
&--'-..."""•, ,
·1
----·~
In the cantilever truss as shown in below figure, the horizontal c.pmponent of the reaction at A, is
Answer: Option A
For a simply supported beam with a central load, the bending moment is
A.least at the centre
B.least at the supports
Answer: Option D
A simply supported beam carrying a uniformly distributed load over its whole span, is p ropped at
the centre of the span so that the beam is held to the level of the end supports. The reaction of the
prop will be
A.half the distrihuted load
'
l
B.3/8th the distributed load
C.5/8th the distributed load
D.distributed load.
E. none of these.
Answer: Option C
The range within whic.h a lnad can he applied on a rectangular column. to avoid any tensile
stress, is
A.one-half of the base
B. one-fifth of the base
C.one-fourth of the base
D.one-fifth of the base
E. one sixth of the base on either side of centroid.
Answer: Option B
Answer: Option C
The region of the cross-section of a column in which compressive load may be applied without
prod}lcing any tensile stress, is known as the core of the cross-section. In circular columns the
radius of the core, is
A.one-half of the radius
B.one-third of the radius
C.one-quarter of the radius
D.one-fifth of the radius
E. one-sixth of the radius.
Answer: Option C
The maximwn bending moment due to a moving load on a simply supported beam, occurs
A.at the mid span
B. at the supports
c._11ncier the load
D.anywhere on the beam
E. none of these.
Answer: Option C
A simply supported beam of spar1 L canies a uniformly dis cributed load W. The maximum
bending moment M is
AWL
- 2
--
B. WL
- 4 z,,.
C. WL 2
- 8
WL
D.12
WL
E. -
f
- 16
Answer: Option C
.
A cantilever beam rectangular in cross-section is subjec1ed to an isolated load at its free end. If
the width of the beam is doubled, the deflection of the free end will be changed in the ratio o f
A .8 B.l~ .
C.1/2 D.2
E.3
Answer: Option C
When equal and opposite forces applied to a body, tend to elongate it, the stress so produced, is
called
A.shear stress
B.compressive stress
C.tensile stress ,,.-----
D.transverse stress
Answer: Option C
.
Stress in a beam due to simple bendihg, is
A.directly proportional ••
B.inversely proportional
C.curvilinearly related
D .none of these.
Answer: Option A
Answer:. Option D
0
A simply supponed beam of span L carries a uniformly d istributed load W. The maximum
bending moment Mis
A. WL
- 2
B. WL
-
C
~
4
WL
8
v
-- 2
D.12
E WL
WL
f
-' 16
Answer: Option C
A cantilever beam rectangular in cross-section is subjected to an isolated load at its free end. If
the width of the beam is doubled, the deflection of the free end will be changed in the ratio of
A.8 B.l~
C.1/2 D.2
E.3
Answer: Option C
When equal and opposite forces applied to a body, tend to elongate it, the stress so produced, is
called
A.shear stress
B. compressive stress
C.tensile stress ,,----
D. transverse stress
Answer: Option C
Answer: Option A
Answer:. Option D
A district road with a bituminous pavement has a horizontal curve of l 000 m for a design speed
of 75 km ph. The super-elevation is
A.I in 40
B.1 in 50
C. l in 60
D.l in 70
E. none of these.
Answer: Option A
The total length of a valley fonned by two gradients - 3% and + 2% curve between2
the two
tangent points to provide a rate of change of centrifugal acceleration 0.6 m/sec • for a design
speed 100 km ph, is
A.16.0 m
B.42.3 m
rr· ·r ··--·r·"·~· ·
f..P.."
..,
C.84.6 m
D.none of these 1 1
Answer: Option A -" sl
•
The advantage of providing sup~elevation on roads, is
A.higher speed of vehicles V
B.increased volwne of traffic/ v · · .J
C. reduced maintenance cost of the roads
D.draining off rain water quickly
E. all the above. /
Answer: Option E
~or a vehicle moving with a speed of 80 km per hour, the brake r~a:io~4.~ ordjnary cases,J
~ ~·
-
i
Ole
JS
o...... ~ ·()
£
• J~ ~
BEAM DEFLE~TION FORMULAE
BEAM TYPE I SLOPE AT FREE END I DEFLECTION AT ANY SECTION IN TERMS OF x MAXIMUM DEFLECTION
l . Cantilever Beam - Concentrated load P at the free end
I I
:I ==c=1:j-r
y
u -----!..\~"
I
~ x 9= Pa
2El
2
Px1
y= -
6E/
Pa
(3a-x) for O<x<a
2
y=-(3x-a) for a<x<l
o...,. -_ Pa
2
( 1-a)
6El 3
6El
3.~C~an--:-:-
til~e-ve-r~B~e~am---~U~ru~.~fo-nnl--,-y-r7-·=str~i~
u bu~~~d~l~o-
adTro
~~(N
~/~m~)----------------l....-------------__J
~ x
ijY ~~
' 0=-
(J)/j
6El
y
(J)XJ
=14EI (x 2
+ 6/2 - 4lx) om... = SE/
(J)['
4~C~an--:til~e-v-er~B
;::-
eam
..____ ~U~nifi~.~o-rm--:-ly_v_ary--:m-g--:-
lo-a~d:~M
:-:-
ax.un~.:---um-m~·_7
te-n-si~ty-.-ro-.~(N~/~m~)---~-----~'--~-------~~~------1
<»='7'" (1- ~
·) X
9=~
1
~t.x.J:.&.i!:!:!:i!:~.~=- y =-·-
ro x· ( IO!J -10/'·x+5Lx-' -x'. ) ro0 / 4
0.,,., 24El 1201£/ o.,,.. = 30£/
-- - ----
- ·- 1
5 Cantilever Beam - Couple moment M at the free end
~· ~-i ~~ @ Mxl
y= 2EI
~
Y ~MT ~
T . I
----------- - - - - -·- - -
BEAM DEFLECTION FORMULAS
BEAMTYPJ·: SLOPE AT ENDS DEFLECTION AT ANY SECTION IN TERMS OF x MAXIMUM AND CENTER
DEFLECTION
~------"""6'"""'
. Beam Simply ~upported at Ends - Concenvated load Pat the center
a, t Pt 1a, i ; Pl 1 (31
Px ---x1 ) for 0<x<-I
2
Pl
3
=Pb (.'ib1)"2
2
y = Pbx (1 x' - b 1 ) for 0 < x < a
~
2 2
Pb(l -b -
~:Lt-~
a -h e1 = -'-----'-
6ZEI
)
6/El S at x= fi(1 2 -iF)/3
mox 9 3 lE! '1 1
[!..(x-a)3 +(12 -b2)x-xJ]
/ Jt
8 e Pab(2l-b) Y = Pb
iy """' 2
6lEI
6/EI b
B = -.!!l._(311 -4b 2 ) at the center, if a> b
48EI
for a<x<l
8. Beam Simply Supported at Ends - Unifonruv distributed load oo <Nim)
-
~co~*.~
~~ ti~ 8,..,·
p I J' 0
I
=0,=~
• 24E/
9. Beam Simolv Suooorted at Ends - Couple moment Mat the riaht end
~ y=~(> 2
24E/ l -2lx +x')
r 0
5CJ>/4 j
- = 384E/ 1
\
Ml' l
M o=>< =--atx=-
a,\ 1e. ~ x Ml.x( x2) 9Jj EI f3
~--:rj y=ru i- y ~ Ml'
o=- - at the center
\ 16EI
360EI
I -
(l)X 2 4 EI
y = 36dlEI ( 71• - I Ofx + 3.x )
(J) z•
e. = CJ>.t> o= 0.00651- 0
- at the center
· 45El EI
,. ., . " I I '
l
,.
I I·
I
<_27. The error in measuring tape due to shortage of tape is called:
Systematic error
I , y{ Initial setting t ime of cement for asbestos cement products should be not less than :
I 30 minutes
31. If water required for 1 bag of cement is 30 liters, the water cement ratio is:
L- 0.6
3
[ ·. 32. The weight of 1 m of brick earth, is about:
1800 kg
,~
33. Mastic asphalt is normally used for :
Water proofing
Le-chatelier apparatus
Workability
l!l lht t,<,)f.l(:r.t'.I.!~. r.lump recommended for beams and slabs is:
Px' . I pf
I' ; - ( 31 - X,
. 6£/. . 'j[i
rnf • w!'
S= - 0 =-
6£/ = 8£1
··r~~~:·
r-
,Y I
.
1· = - N·-.x' {IOI·• -I OI.·.r-x1·
1201£1
•. . - .1- 'J 5 = w.J"
""' 30£/
:..-·-..- ---·----·-.... J
t
I
I - 'I I.
'' 9: .\{/ .\.!/ _ Ml:
,,.. =
.:> -
1'=-
El . 1£1 2£/
BE..\'.\! TYrE SLOPE AT £\'DS DEFl.ECTIO'.'\ ,\ T ANY SECTIO\ I\' TER.\IS OF x ~IA..'\l'.\IDI A'iD CE:'\TER
DEFLE.mO:"\
6. Beam Si111 \1· Su oncd ar Ends - Conccnuattd load Pat th~ centtr
~1 .r
. '. •' 1i ~1 ... - -I'
r =t:lX I -~L1 ·•-..x')
l r jl . 2~£1 . . 3R4£/
'~ !
= :.ii "' ---.=-- n1 x = --,..
6£1 l/f.\ 9.J 3 fl "·'
9. = ~
fi - .\/:'
Mf'
0, 0 , =Cl.IJOc52-·- m x =fl.'.\IQ /
1· = w.x i 71' - IOl'x: ~ 3.\' I £1
. 3601£/ .
1. T_l:1e st rength of material is defined as:
[]
a) Abil'.ty of mater'.al to resist external for~~- --~
b) Ab ility of mate.i:_i~I t~-~-i:~~! d~_fo_~m~ti.on . \
0
c} A~ of rrui.!_e_rla.l.~2. wi_th st~_nd.~~~~LJ.g~q..s. J D
@-·
d) Nooe-of-t~~e. ALL /))~1,,c.
2. Stress means:
a) ,1sth-;
internal forces developed in material due to externa l forces . .c:..-----'
c:r-·
b) Ab"ility fo resist external forces D
c) Deformation in.materi.al caused of ext ernal forces. 0
d) Forces applied perp.endi_c ular to the longitudina l axis of a member. ~ 0
3. The Sf.T~!:-1 V?~ue_~ of Dense sa_!:l-9. is equal .to~ \/~Y'/ Lc:iS'iC ._(2b
I t0}')
a) 0 - 20
20 -40 '
l
1·
I
l
~ - <:.-
~';;.:;. 2..b
01
-'2 I
D
0
c) Largerth an SO vied . 1
"2..."° -'"Sb 0
I d} (~00
b·
't>:viS::!-
Ve
~b ~ ~
l->~·fi -· / '"'f O
0
·~Lft
E = 250
I E, = 350
I 25KN
I 4m
4m
2·
c~ - ·~· L.,,,,,.--.. . . . . .
D
4
28days.. . '·. '-!_,,) D
d) 35 days.
~- D
9. For simply supported beam the shear and flexural stresses will equal to Zero at:
. . -=-- D
a) End supports. ·
b) Middle of the span and above neut.ral axis. ~ D
c) M iddle of th~
span and on t)1e n_eutr.al a x i s / _ --::-;::-:-: ::·· D
d) End Supports and below neutral axis. -··~ ;
D
10. he summati~n of internal an les o 6 ides polygon: ~
v q) 360. A)-7- Y-' : 30 c:> \ {
D
~ D
~/
b) 540.
C) 720~
,
J(µev "\_,_.----
s-1 d ~ I~· D
\ ~ d) None of the above.
D
11. Ministry of urban planning need to construct an exhibition center the location pf this
center should be next to:
-- -
a) Airport
~ -.
D
b) Buses stations.
D
c) y a high_population are.a.
D
.s4'" ln a remote area.
D
..r:zi
12. i8SHG& responsible for:
Responsible of public hous!ng.
c:zb) Responsible of electrical and water services
D
n
L-J
I 4) Curing.,
The correct sequence of work for concrete work is given by:
a) 4-1-2-3 D
D
I b) 3-1-4-2
c) 3-4-1-2 D
D
d) 2-1-3-4
~
17. Slump test is used for: ~
· a) f estingof ,_.;,,orkability of concrete. ~ D
b} Monitoring heat of dehydrated concrete D
D
~
c) Used to calculate strength of concrete.
d) None of t he above. 0
-I 8
'
c) Maximum steel area,Maximum section dimension.
d ) Maximum steel area, Minimum section dimension.
28. UPVC Pipe with station 0.00 and box culvert with station 163...6.t?.9_ ft. calculate t he back
p..-•· o -
30. A sample ofl2:9_@1 ~a-~tewater is given in a cont_a iner (~-~_!_~Qn!ainer ~g) and
was inserted in oven, after water evaporated the weight of sample was given as =74.SOJ_g
- --
'
·-·· - was. inser:t~.9
then the sample .
'•
. ·-
in a burning
,..,•-
-
oven and the weight changed to= 2;S.606 g , t he
volatile solids content for this sam le is enual to:
• --::,..r~
I \
rJ\ s c:rO
7.
I
QCS2010 Section1 Part8 Page 38
I Quafrty Assurance
Material /Section I
I 4.00 Earthworks,
Subgrade, Base.
Subbase, Backfill,
Refer to
footnote
Sub-ballast etc11• 12 ~·
~
rift (le, per
com~laYet>
4.03 Gradation (Sieve) AASHTO M145. T27, • Eaeh source Refer to
Analysls14 T88. ASTM C136, • Visible change in footnote
I 0422. 02487. 03282.
BS EN933-1
gradation
• 1 test every 1000 m3
4.04 Atterberg Umits AASHTO T89, T90, • Each source
(Index limits) • (Liquid ASTM 04318, BS • (Visible) Change in
Umit & Plasticity 1377·2 material
Index)
• 1 test every 1000 m~
n Footnote 11: Earthworks, SUbgrade (tncluding porous, prepared etc), Base, Subbase,
BaeldiU (including soikement, structural, pipe bed'dfng, trenching, piping, pervious, porous,
reclamation backfill etc), Sub-bal!ast. Common fil~ Select fiD, Technical fill, Embankment till,
Rock fill, Sabkha rock fill, Gravel, Granutar Base (for pavers of all kinds}, Setting Bed (for
paver.> of all kinds) etc and/or products and materials confom1ing to ASTM 02940 or
equivalent shall be tested as per this section reQUlrement where applicable.
12
Footnote 12: Concrete specifications, testing prooedures and frequencies shall be adopted
for concrete and concrete related baddilt
!~ ::-vcfn.):: 13. Th: ::::r~ ~ t-:·:!!~:; :Ts-: ..:=~1:'~ ;~ :-:· :. ? t~··r··:/::.ri -=~- "='~-~"! "~,.~.. fi i.'.:."\-Jt ~ ' ""'""
as n:an;;cles, ciia:n:.iers m;..:s: t;!;;:,·s s~:i;· s<;:~ &~:.
1~Footnote 14: Aggregate gradation standards are ~nc[uded to cater ior pervious. porous ·eic
backfill.
I
I
I Some Guidelines for Constructing Shear Force and Bending Moment Diagrams
SIGN CONVENTIONS
+V -V
BOUNDARY CONDITIONS
A B
B
A
P.iJloed LEFT Eod: PiJloed Right End:
Rcactioo force, A, is unknown. R.cactioo fon:c; B, is wil<Down.
Rcacrioo force, A., is uoknown. ReactioD force, B, is uoknown.
V (sbear force) - A., (reaction force) V (shear force) -8 1 (reaction fon:e)
2
A B
A
Clamped Ead: Free End:
Rcactioa force, A, is unknown. V (shear force)= 0 (unless there is an applied point
Reaction force, A7 is unknown. force at this end)
Reaction moment, M,. is unknown M = 0 (unless there is an applied moroeol at this point)
v (internal shear force)= A7 (reaction force) Deflection, y is unlcnowa
M (internal bending moment) = M,. Slope, 6 is unknown
Ocfleclion. y = 0
Slope, 0 • 0
REVIEW ( 5-Jun- 13 )
'I _ 0
1. What is the SPT for dense ? 'So:\ \~ ·_
Options: 0-20 I 2 -
JUM: 20-40.
Recfan~fufarsection.
JUrV!-:l§~~d ~e~
C:i>.-L--·l·-·
.J.- ·
,• '
-
- -J-··
_________
4. For how cross sections are used ? JUM : for cut and fill .....quantities.
_...-· -
5. What is the perc_!ption an~ reaction time for calculating the si~ht distance?
1 second
~;
3.5 s
None of the above .
JUM : 1 second. rf
\
6. If a work, if the.property decides to make a change in scope, what is the procedure to
do?
Change or~
Modification
...
~.,-~-------------------------
•·
Cracks on the surface due to excessive water content c...---·
All others are true.
JUM : all others are true.
10. On relation to the use of air-entraining ag~nts in concrete, which of the following
statements are true:
Improve the workability ~
Improving long-term durability_;_....--"
Makes a less dense mixture :..... -··
---· -~- · ·. .
JUM : all the above are true .c....---·-
12. What of the following statements are f~se for a Work package:
Allocating resources must I
It should de~ignatea ·work ma.nager. /
It should set deadlines
. . "definitive "
'
\'
None of the above is false . -
JUM : You should set a timetable definitive .
18. Probl em: " If in a plane I measure 7 % " " (inches) and is 1/62.500 scale, what is the
distance between the two points in miles ? "JUM : 7, 25 miles.
20. In a beam which points of stress due t o the t ime and bearing is equal to 0 ?
In the neutral light center .
In the top center fiber light.
At lower fiber support.
In the neutral support .
JUM : the neutral center and the neutral light support .
'J-~.- --t
+- 1- ~ ~
~:
-
.. .
-i- ,_.. ;
....
L
-
~L..
Z- ·.. _
\.t,j l
\
__L t ::_L?- x_ ~
2- 8 2.-
\JJ \.}
32-
v--i
;_
b. 11- - ~
c_
3
(
. u
- - - - - - - ve> c/
v ..----
) \
D eilec1ions - Method of Vinual 'Nork - Verncal Deflection by C anble1er M ethOd
Deflecl•ons - Method QI Vi rtual Work I Index o • :Oxa "T>cfe s I CCE -fQ!:!~DaQe
r The following example utilizes the cantilever irethod to determine -the 'real" and virtual rroment diagrams used in
the calculation of deflections of a beam
Note: The colors of the loads and moments are used to help indicate the -contribution of each force to
' the deflection or rotation being calculated The moment diagrams show the moments induced by a load
using the same color a s the load
problem statement
Determine the vertical displacement at end C ofthe beam shown in the figure below. The imdulus ofelasticity
(E) and the moment ofinertia (I) are constant fur the entire beam
Li I:
- - - · ----~
'
4 - I
. 'I'
YA Ye
Figure I - Beam s tructure to analyze
Solution:
• calculate the support reactions
Calculate the support reactions (caused by the applied "real" loads) using the fullowiog relationships.
L MA= 0 ~ 56ft -k +Y3 x 20ft - 2 kl.ft x 20 ft x10 ft -6 k x 26ft = 0~YB =25k 1'
L MB = 0 ~ 56.ft -k + 2 k/ft x 20 ft x 10 ft - 6 k x 6 ft - y A x 20 ft = 0 ~ yA = 21 k I
Check these reactions by summing the forces in the vertical direction
i"lttp://vwm.publ1cJas1a1e.eduJ-lanouslcemA:rtualv.Q"Wbean:defteclion.htrrl 1/6
2/19/2014
I, Dertections- M ethod of Virrual Work- VeflicaJ DeftE(OOllby Canolel.€f Method
r
Figure 2 - Beam structure with reactions
l • draw shear (V) and moment diagrams (M) for the structure under applied "real"
loads
I
The resultant shear and moment diagrams can be determined using statics (see figures below).
r
r=---==-- -=::::::::lliJw
21
II I I Shear D;agrom
I v -19
(
54.25
I .
Moment Diagram !
M f
I t
I
i
I
-56 .
Figure 3 - Resultant shear and moment diagrams
.
i
In this example we will use the cantilever method find an equivalent rroment diagram in order to carry out the
required integration
To construct the moment diagrams caused by the applied 'real" loads utilizing the cantilever method, a point on
r the structure is selected and a :fixed support is assumed at this location In this example, point B is selected and a
fixed support is inserted (see figure below).
Notice that all reaction forces are applied as loads on the structure with the assumed fixed support at B.
_,._ ·~
._; ·,
2 k/ ft
C ::HJlliiHIJHHHl_p:ii- 1
56 ft-k l 20' 6' --i
'
21 I<
Plot the moment diagram for each applied load separately, i.e., by parts. The final results can then be obtained
by utilizing the method ofsuperposition i e., by summing the contribution ofeach individual load to the
displcicement being calculated. Thi5 method is applicable since the structure is asstnned to be elastic and the
deflections are small
http://ww>N. public.i astate.edul-fanous/ce.332Nrtualvl.ll"l<Jbearrxje6ection.hlm! 216
211!!t'201~ Denecuoos ·Method of Virtual Work· vertical Oefte<:'cn byCantile..er Metnod
Note: The cenrroid of eac~ area is indicated by the numbered arrow and dot
-
OMoment diagram due to the 56 ft-k concentrated moment at A
- '
1~8
-56 ft-k
1 .
-
(
Figure 5- Moment diagram due to 56 ft-k moment
A
c
B [
A
B
~ c
Notice that the resultant roornent diagram (figure 3 above) is the sum ofthese four diagrams.
. : .ids.~ AL"\6\ i /(
~ .~
t\ 8 ' A B ( -"111111111111 + o:..A_ _ _ •._...:( = (/
r:::•= ====-::£::£ -+ - ·- v ~
iv)
ii) iii)
i)
Figure 9- Resultant moment diagram
Note: The cenrroid of eac~ area is indicated by the numbered arrow and dot
-
OMoment diagram due to the 56 ft-k concentrated moment at A
- '
1~8
-56 ft-k
1 .
-
(
Figure 5- Moment diagram due to 56 ft-k moment
A
c
B [
A
B
~ c
Notice that the resultant roornent diagram (figure 3 above) is the sum ofthese four diagrams.
. : .ids.~ AL"\6\ i /(
~ .~
t\ 8 ' A B ( -"111111111111 + o:..A_ _ _ •._...:( = (/
r:::•= ====-::£::£ -+ - ·- v ~
iv)
ii) iii)
i)
Figure 9- Resultant moment diagram
:§};> ! 0 .._
/
,.......~ -
I
J
("J Lt::"/-J •. .. ),. ·- - (,,..
1 - ,.
' • .··-:/! ,- .•' I /,1
--:---:-.---··-·-- - -- 5 - v_,._~!I
~-
G/"1. Temperature {Allowable) of Asphalt during lining. (135 degree centigra~
J.· Plasticity index of soil (Pl)=Ll(liquid limit) - P.l(Plastic limit)
._,,a. Time cost curve is representing the relation between..?Earneq cost and plann_ing C?St. Also it
can be considered as the relation between the cost and time.
The direct cost includes the following, labors and staff cost, project Materials (s:,;pplies). plants,
...-4. transportation (travel) and consultant services.
, '\.."' ..,..-..5. Indirect cost and expense during the project is the overhead, profit and administrative
equipment rental, audit and legal.
6. Elevation of leveling device is 106:23 what is ground level If reading of the stand is 106:52?
_>J. tf T-Shaped beam is passing through many supports, the section above the support should be
designed as? rectangle section Z:, '.>
8. Interdisciplinary n11ture of Engineering project ls defined as the Integrates between different
disciplines within the project like civil, mechanical. ArChitect, electrical department in
information, ~at~, techniques, tools, concept, .etc. to solve problems whose solutions are
beyond the scope of a single djscipline. Also, we can can~ Interdisciplinary engineer as
coordinator engineer. The course of interdisclpllnarv enc;purages you to combine (integrate)
your knowledge and experience with thafof"(;thers. Also, it is the interconnections among
-. . . .
differe!"lt departments within the project organization, work with others from different
backgrounds and sections to pose and evaluate resolutions to complex problems. It is how to
wortc within a team. The collaboration between all d~partments within the construction of the
project.
9. program evaluation review technical
PERt~is
t---'
__..l,0. If the~ magnJtude O!l a tra~~D!'l!il R.~ colµ~n . in~rea5£S continuous_ly, the allowable
-~· moment In one plane is constant.(~!!ro)
;..
Jl. If design speed of road is 60 mile and f (side friction) =8%, e (Super elevation) =l, then the
./ minimum radius is equals to? R =v2 / 127(e + f) where vis the speed in Km/h. "'
12. Slump test of concrete is used for. woricabilf1'& . <;;'•) / °(" c.....
zC t·' n ~xtract good samples of rock we a~ u~ing (sin~le. t4~6arrel - d~~~l_e_~be barrel - barrel
· - Shelby tube- traditional split spoonp dou~~rrer ··-~"".a _
_).4. The la;t composition of cement during ma ~u-rer.is? '¥°4___.Jgvpsum)
15. calculate the peak hour factor for the following roads?= the sum of the total four readings /
/ 4 •the maximum One.
16. What are the parameters affecting on the workability of concrete mix? W/C ratio, aggregate
gradation, the procedure of the pouring of the concrete.
17. What are the parameters put on your,consideration during the design of concrete m~x? '!Jf C
ratio, aggregat~radation, the procedure oJ the pouring of the concrete.
18. What is the maximum allowable temperature of fresh concrete and why?
Concrete shall not be placed if the fresh concrete temperature exceeds 32 degree centigrade .
........................................________ ~~~~~~~~~ ·
I
I
I
I . - -·--- -
Because at this temperature, rapid hydration process inside the poured concrete will takes
. :::::-.--
place inside the concrete which will causes inner thermal stresses and this will make inner hair
cracks inside the concrete. Also, if the ambient temperature Exceed than 40 degree centigrade
I at shade.
I lnterdlsclpllnaf)I field of ~ginee1iog thai focuses ors how to daslgrr c;,nd mansgs compfe.lt 0ngineerln9
projects over their lire cycles. By lntagra~es informa:tion, data, techniquGs, tools, perspectives,
concepts, and/or theories from two or mor& diseipHnes or·bodies o1 speclaU2ed knowledgs to a:dvaruce
I fundamental unde1'Standin91 or io solve f"'Oblems W'Glose soluUons ~re beycnd iha scope of a single
discipline or area of research practice.
_, , 'I , ;.
.::....-~;_,?1
Shelby Tube ~amp~'9rs
\
Shel!>Y tube samplers consist of a one-p,i!Q:. thin-walled, hollow steel tube ~ an open-e.nd that has been
honed to it altttng edge. The maln purpose of the Shelby Tube ~rn_P.ler is to ~q>~r ~atively tJnd!~!~~ .
soil samples suitable for laboratory tl!sts of engineering properties sueh as strength, c;ompressibil!!=Y, ~~~~
permeablfity, and density. They ~re v~ useful fofcolrec:ung sans that a.re earticular1y setis!ttve to sampling s
dlsturt>aote, lnduding fine cohesive sods and ~· provided that the soil has not been disturbed by sinking 0..J.
the borehole and are free from large particles. --
\
\' Advantages Include:
~
• Seamless steel tubing
• Collection or good quarity, virtually undisturbed samples for lithological description and chemical
analysis
• EffectJve in fine, cohesive soils
• 2• samplers are ideal for use through 3 1/2" geotechnical direct push systems (dual tube) and 2
1/4" ID hollowstem augers
\__,. • )" samplers are ideal for use through 4 1/2" IO hollowst augers
• Not recommended for driUing througti(2ravel~ hard clay.
'\s....,uy-:1l
.,....- -
Traditional split spoon: used with SPT for cohesion less m ater ial like sand and gravel
-
S-curve is defined as:
I ,,.
1·
.~
[steeperlin the middle, which is typical of most projects. The b~inning represents a slow,
I'
,.dellberate but-=-
~
·- the work- runs
accelerating start, while the end represents a deceleration as
. -
-----
Types of S-curves
There are a varlety of 5 - cu~ves that are applicable to project management applications,
including: -
PERT:- It's the abbreviation olProgram Evaluation and Review Techniqi0' Critical Path Method.
the critical path method (CPM) is a project modeling technique
~s a method ~zt the involved tasks in completing a given pnijcct~.J!LIY the time needed to
co1111>lete each t.iSkJ 8nd to identify the minimum time ~ to complete die total project.
- ..
PERT was develoPcd ~y to simplify the plailning and sc&edUliilg of large and complex projec\'S.
- -
.-
In order to use PERT, you must first identify three simple estimates:
=
Te To+4Tm+Tp 16
1·- ,.
I
The float for each activity on Path t is 19 days. The Purchase Plot, Select Design, and Assemble Shed activities also lie on
another path (the critical path). for which we've already calculated the floal Therefore. though these activities tie on Path 1,
the float you will take will be that of the longer path. In other wcrds, lhe float for Purchase Plot, Select Design, and Assemble
Shed Is not 19, but 0. This is the reason why you must calculate float from the longest path to the shortest
Now, let's cala.dale the float for the next longest path - Path 2.
rntrod uction:
If you have been into project management. I'm sure you have already heard the term 'critical path method'.
If you are new to the subject. it is best to start with understanding !he 'critical path' and then move on lo the 'critical path
method'.
'Critical path is !he sequential activities fran start to the end of a pmject. Although many projects have only&critical palh.)
some projedS~have m~n one Ciffical path depending on ih8 flow logic used in the project.
If there is~In any of the activitles under the criticaJ path, there will be a~ the project deliverables.
Most of the timeS, if such delay is occuned. project acceleration or re-sequencing is done in -order to achieve the deadlines.
The initial critical path method was used for managing l!flm majntenaoce projects. Although the original method was
developed for construction work, this method can be used for any r:iroject where there are interdependent activities.
---'Z> In the critical path malhod, the critical activities of a program or a project are identified. These are the activities that have a
direct impact on the completion d8te of the pl'Ofect. - - -
,..--...,
l:._,1..._
Task' / ···-.••
/-( " ·..
TM~lO
lS 19
~ A~vity specification
You can use~oric Breakdov.TI Structure~iden~'}ie activities involved in the project This is the main input fOf
the aitlcal pa ethod. - -=-
-
In activity s~on, only the higher-level activities are selected for critlcal path method.
.
When detailed activities are used, the critical path method may become t'lQ_ complex lo manage and maintain.
•
•
Step 3: Network diagram
Once the actiVily sequence 1Fci0identified.~...
...... ... ........ ----
th-e_n_e_two_rk-d-ia-g-ram-;p-an be drawn (refer to the sample diagram above).
Although the early diagrams were drawn on paper, there is a number of computer software, such as Primavera. for this
:i.r;>ose nowadays
• Earliest start lime (ES) - The earlies! time an activity can start once the previous dependenl activil1es are over
• Latest finish time (LF) - The latest time an activity can finish without delaying lhe project.
..-- the time betweenEiest (~ and the lat~ (LS) start o;i,:;)o~between~
During the ftoal time, an activity can be dela~elaying the project.finish date.
(The critical ~is '!1e iooQest oi!t! of the networtc di~ The activities in lhe critical path have an effect on the deadline
of the project. If anactivfy of this path i.s dela;ea", the project Will be deiiyed.
In case if the project management needs to acceJerate the project,
• Presents the time to complete the tasks and the overall project.
A critical path diagram should be constantly updated with actual information when the proiect progresses rn order to refine
trie activity length I project duration predictions. -----
M*f
•
finished
0
Tiwt the ~o oJ bui(9i(l9 tWo · entlcal f the same hoi:se using the same material. Let's_.sav. building the first wall
is tasl(A)lnd building the second one B englnier wants to delay task BTortWO
days. This is due to the tact that
lhe marerial used for bOttl A and B are a new . so the engineer wants to learn m>m
A and then apply if there is anything
to 8. Therefore, the two taslCS A ana
B have a SS relationship. ~
The ti=tween lhe start~ o~ two~ a.'n be defined a & days in this case)
- -
Task B started prior to Task A with a 'lead'.
For 1 project manager. the concepts of.!!,2.at. ~· and f!a make a lot of me~ning and ~ These aspects of tasks are
~ant in order to calculate project timeline variations and eventually the proJed completion lime.
. ' lr~nh
.'@j~t t11ppl les
J~~llu1 tlon!. ·
lliivt-1
-
few terms and conceptstl1ar are "must-Knows." These terms fonn the foundation of
PM methodology and mentality.
~::I\ ~ .. - - .. ..
·
--It Qmstramts: E.t;_strictions set on ~r(jlliish d~of a task. .You can specify that
~ /;ltask must start on or · h no later than a parucular date. Constraints' can be flexible
" - · n~ed to a specific d@.te) or inflexible tied ro a specific date~ ··
• )fF1exib/e constraints such as oon As Po · (ASAP) and Late As PossibW
~) do not have specific dates associated with them. Setting these constraints allows
.JOU to stMtJasti:as early as possible or as late as possible with the task endiDg before ffie
2!2iect finish, ~vcn other co · . · · e sc e.
•/tlnflexible constraintsd as Must Start On 0 Must Fiili On (MFO require
an associated d8ie, which controls e start or finish date of the . ese constraints are
bS'clUi when you need to make your schedule take into account external 18ctors, such as
the availability~r resources, deadlines, contract milestones, and start and
"finish dates.
r-r _ _
__.. - .
;/r;, Critical Path: !_he longest time path through the task network. The series of tasks (or
even a single t~) that dictates the calculated finish date of ille project (That is, when
the Jast task in the critical path is completed, the project is completed) The "lo~t"
path (in_terms of~ to_!!e completion of a P!Oject. Ifsho~ed. it would shorten
the tiriie it take_!.!o.complete the pmject. Activities offthe critical path would not
affecftompletion time even if they were done more quickly.
o Discretionary, optional task sequence preferences that, though not required, may reflect
organizational preferences
~ Duration: The time it takes for an activity to be completed, given the planned amount
of material, labor and equipment.
>f Effort: The amount (not duration) of work required to complete a task. Duration may
da:rease by adding resources but the effort required will remain the same.
1;. Gantt chart: A bar chart. Whlle visually appealing on a task/duration basis, it is
limited because it does not show task or resomce relationships welL ItS 1cey Strength is
that it is easy to maintain and read.
;·; :o l....._
r·
~~~~A~1f..i!J:~
. -·--··- -..-
i_!_·~
~~
.= :·-,.;
;..
···:· •. i
}:·-~· i
==---
.. .--~- -
..... ~6M'i.
..,_,,...osn,~
Or.,....,caq.•.:"-~
.
!
l
!! ·=-~-
ESEiil .......
D.....,..,_.
1111 ~..,.
. !
•· 1
! .,
:J.:~i
°"ll!'Mll~•-O..C
~....-ti- :
i
!
E!i!l!ii§!I ~~Allll
B..._....,
·:·-·! i
Sample Gantt chart
..
Sample Network Diagram
-Jt Relaxation: The method that is the opposite of crashing a project. Relaxation is used
to lower costs while extending 1he duration ofthe project. A typical use of this method
is when a project may be relaxed if its resources are need on higher priority projects.
This method involves deh"berately lengthening the duration of the project with the
specific aiin of lowering costs as much as possible.
-:/:... Resources: Time, money, people, equipment and other supplies are generally
accepted as resources for planning and executing a project.
Scope: A specific definition of what the project does and does not entail. A well
researched and coordinated scope of work is critical to managing expectations of
customers and workers alike.
Sample Network Diagram
-Jt Relaxation: The method that is the opposite of crashing a project. Relaxation is used
to lower costs while extending 1he duration ofthe project. A typical use of this method
is when a project may be relaxed if its resources are need on higher priority projects.
This method involves deh"berately lengthening the duration of the project with the
specific aiin of lowering costs as much as possible.
-:/:... Resources: Time, money, people, equipment and other supplies are generally
accepted as resources for planning and executing a project.
Scope: A specific definition of what the project does and does not entail. A well
researched and coordinated scope of work is critical to managing expectations of
customers and workers alike.
f Slack Time: The amount of time a task can be delayed before the project finish date is
delayed. TQtaJ slack can be positive or negative. If total slack is a positive it indicates
the amount of time that the task can be delayed without delaying the project finish
date. If negative, it indicates the amount of time that must be saved so th~t the project
finish date is not delayed. (Slack time is aJso known as float time)
.. Total Slack = Latest Start· Earliest Start.
o By default and by definition, a task with Oslack is considered a critical task. If a critical
task is delayed, the project finish date is also delayed.
---~
54eye
;lwS
...... '°"'
.....
14~,
10CM
I ,, ,.WIS·uc - J~!~ •I __
~
1.1.S
I .>,1 .1 ' 31$51
'
:
.........
--~R<+*WC 1 .1 .1 .:I w-. 19*
·-
• •• 1.1
1 .U~
...
t.11,IJSSJ, •1~1
--- t.uim·
1 .1.:1 21ft U.3
_.,__~o-- 1.t~· :nn
...... 1. . 1.1.2
·- ""'
1 ,1A
..,;... 1 .1 s tOM t ~t .I t .15
T. . . . . . . .. lllatOCl 0 . - 1.16 :un us· 1.:1
1.2 ;w.
=~=·
PftUe 2 - l!;reeution t.1.G
-Oatii·c...,._• .
·- ·-'°"'
1.1-t 13'!i. 1.2..2
..;..o.;....;.·-ew-r 1 :z:1.1 12.12
Sd.__........... _
~·~.._._,, 1.2.1 .:!
..••
U11n 1..2.U 1.:?....1.3
,.j,1 3
~-
1.2.12; 1~1 A
'"'
-·~--~---
1 .a.1 A
a11r> ~ 1 .2.1 ,; 1.:12.1.1 .:.1 .$ ;.....
.._....,·~----Or'-
--
1 .2 .1 :; 1.:u.•'.
2-
........
iiieac-c-.·. ~ c..;p;.;~
~~..__ .....
i .2~; ir.
1 ~-· ; ·
a.t.n
""" , .:I.• "ISSI
· ~.,3.,2.22
Sample WBS
• Mn = Fs.As(d - a)
• Mn = 0.85fc.ab(d-a/ 2)
• Mn = 0.85fc.ab(d -a/2) + Fs.As(d - a/2)
7. Something about flow in pipes, 2 pipes A and B joined together into pipe C
Flow A given
Flow B given
Area C given
Calculate velocity of water in C.
8· Calculate the length of arc, radius 250m, first tangent 25°30', second tangent 30°25'
g. car going on a speed of 60 mi/H on a curve highway. After passing midpoint the driver saw
an accident in front of him. The distance that will be passed from t he moment the driver saw
•
13· What is the factor effecting the hardness of water ?
14· How to calculate T-beam ... (flanged section)
is- Who make testing of product in the factory
• Testing engineer
• Product engineer
•
16-
1- What is the first thing you do after you take a project:
Arrange for meeting
Assign staff
Prepare WBS-~ .,.•._--·
-------
MMUP Most Common Questions (CIVIL_}
Ability of Material to Resist External Forces (Ability of M aterial to Resist the Deformation s \jµe_Jp_external -
-·- - · --------..._
forces)
0 Stress Means:
Indication of the relative density of granular deposits (for dense sand =20-40)
o Critical Path:
28 days
ual to zero at:
orted beam the shear ahd flexural stresses will e
7?7???
~~~----
I
.~
, - • /.!~ A'Y
• • · •·• P> .··• '~ 1
o The summation of internal angles at anh&tvgo~~~ :
180 * (n-2} , where "n" is the number of faces
{It is used to inspect the depth and w idth of concrete, and detection of steel bars location in concrete}
0
Slump test is used for :
3 iayers
Fire resistance
Moist ure content ran e for timber that is used in construction is e ual to:
e
14-18%
Plvwood is preferred as construction material because :
---
The strength of the panel consistent across all directions
Minor limit desi n method for rectan ular section will rovide:
Mn::Fs As (d-a/ 2)
Hardy Cross
Systematic error
30 minutes
e If water required for 1 bag of cement is 30 liters , the water cement ratio is :
0.6
1800 kg
Water proofing
Water-Cement ratio
Le-chatelier apparatus
Workability
)tablltcy or suudur e
rovidin a raft foundation rovided the soft area is
The loose ockets in soil mass can be brid
smaller than:
30to125 mm
" The entrained concrete is used in lining walls and roofs for making:
0.25
???????
o What to take in consideration to safe design for long pile in a drilled rock soil:
Strength of concrete
Calcium &Magnesium
Diversion activity
Budget cost
300mm
o Amount of time that an activity may be delayed from early start w ithout delaying the pro ject is:
-otal fl oat
o Amount of time a task can be delayed wit hout delaying the early sta rt of its successor is:
Free float
It is the sum t otal of all its product and their requirements or features
The ability of a metal to tolerate gradual p rogressive force w ithout permanent deformat ion
Double Sleeve
o What is the perception and reaction time for calculating the sight distance?
2.5 seconds
Drainage
• Who makes the tests to ensure the reliability and suitability of the product?
???????
Problems
o A sample of 200 ml w astewater is given in a cont ainer (W eight of container = 22.00 g) and
was inserted !!'"! o'!e:!, 2fte~ ~·.i2ter e•.i2por3ted the weight o f sa mple was given as = 24 502 E
then the sample was inserted in a burning oven and t he weight changed to= 22.606 g, the Volatile solids
content for this sample is equal to :
==24.502-22.606=1.896 g
0 A car going on a speed of 60 mile/Hr on a curve highway. After passing midpoint the driver
saw an accident in front of him. The distance that will be passed from the moment the
driver saw the accident until he hit the brakes equal to:
- The perception and reaction time f or calculating the sight distance=2.5 seconds
- The dist ance that will be passed from the moment the driver saw the accident until he hit the brakes = 88 ft/sec
-- h -=- ·
-
f) -- } r (
D/ 1<>s1-1-{