You are on page 1of 2

1.

Those BSC’s where PCM links are having full guaranteed redundancy, we
shall correctly dimension C7 links. (this is applicable for future plan –
combination of SDH on fibre/MW)

2. For other BSC’s, we should have additional C7’s and PCM’s for
redundancy. (applicable to current plan & future plan for BSCs on MW
PDH+DXX)

3. Heavily loaded BSCs like Mehta Mahal, Bombay Hospital, Buena Vista etc
should have a more robust Transmission Redundancy Plan. While
planning redundancy, BSC loads should be taken into consideration.

4. Transmission to inform concerned departments about the redundancy


capability (100% or not) of each BSC, so that they can be appropriately
over-dimensioned for C7 and PCM links.

5. Work to shift MTL’s on to Microwave to start immediately from all BSC’s,


starting from RF II team. This configuration will have 1 MTL on fibre and
rest of the MTL’s of each BSC on microwave and shall operate on 50%
redundancy plan for PCMs, C7s shall be over-dimensioned to avoid
disasters.

6. Timeline for Tata FIBRE in Ring Connection:

a) MSC 1, MSC 2 – To night (30th April)


b) Parimal, Oscar to be done.
c) Balance network – estimated time 1 month

7. In the Interim Plan, Transmission will have 50% redundancy. Hence all
BSC’s will be overdimensioned. Number of C7s shall be equal to number
of PCMs in a BSC. This may lead to odd number of C7s for certain BSCs.

8. It has been found that the current distribution of SDCCH configuration for
LA border cells is :

- 70% of LA cells are 16 SD, 20% are 8 SD’s, balance 10% cells are either
having 24, 32 or 48 SDs.

9. No.of C7 links at MSC end is a constraint (as stated by Rajesh B.) after all
BSC’s are equipped with 8 MTL’s.

MSC 1 - 11 C7 Port (will remain)


MSC 2 - 18 C7 Port (will remain)

10. CPU loading to be constantly checked after 2 MTL’s / GPROC have been
equipped by OMCR.

11. We shall stick to existing LAI plan along with enhanced C7 TS equipage.
12. On a GPROC, having 2 MTL’s, the 2 MTL’s should be on separate
physical paths.

13. For Tata fibre, after ring is implemented, Transmission team will do
random checks by pulling out fibre and checking their loop redundancy.

14. The future transmission plan will be a combination of SDH on MW or Tata


fibre and PDH on MW which will use DXX for redundancy.

You might also like