Professional Documents
Culture Documents
Items are "Done" when they are entirely based on the definition of "Done." In that case, they
would have the potential to create a releasable/shippable Increment that the end-user uses.
Tests are also part of the work, and items are not "Done" before the tests are complete,
even the user acceptance tests. Quality requirements are part of the work but not all of it
(e.g. non- functional features and development processes are also part of the work). We
cannot trust the identified tasks because we might have missed some tasks, and the sum of
them does not conform to the definition of "Done."
2. A Sprint Goal is created during the Sprint Planning. The Sprint Goal should .....
Choose ALL answers that apply.
A be tangible
B be short
C be measurable
D be concise
E explain the when topic of the Sprint Planning
F explain the why topic of the Sprint Planning
A discussion about the potential Sprint Goal happens during Sprint Planning Topic One: Why
is this Sprint valuable? The Scrum Team must finalize the Sprint Goal before the end of Sprint
Planning. It should be tangible, measurable, and concise, but most importantly, it should
explain the why. The Sprint Goal resides in the Sprint Backlog alongside the selected Product
Backlog Items and the plan to deliver the Sprint Goal. Sprint Goals should help the Scrum
Team to navigate toward the Product Goal.
When the values of commitment, courage, focus, openness and respect are embodied and
lived by the Scrum Team, the Scrum pillars of transparency inspection and adaptation come
to life and build trust for everyone.
Planning poker, also called Scrum poker, is a consensus-based gamified technique for
estimating mainly used to estimate the effort or relative size of development goals in
software development. In planning poker, members of the group make estimates by placing
numbered cards face-down on the table instead of saying them aloud. The cards are
revealed, and the estimates are then discussed. By hiding the figures in this way, the group
can avoid the cognitive bias of anchoring, where the first number spoken aloud sets a
precedent for subsequent estimates. Planning Poker is not a prioritisation technique
5.
6.This (these) member(s) of the Scrum Team determines when it's time to update the Sprint
Backlog during the Sprint.
Choose only ONE best answer.
A The Product Owner
B Developers
C The team leader
D The senior member of the Developers
E The entire Scrum Team
The Sprint Backlog includes the items selected from the Product Backlog and the tasks
created by decomposing the items. Only the tasks are updated during the Sprint, and it's the
Developers' responsibility to do so.
7. From the following answers choose activities that are accountable to Developers
Choose ALL answers that apply.
A Make technical decisions
B Create releasable Increments
C Provide estimates
D Breakdown epic stories into smaller ones
E Create user stories and use cases
F Choose the team leader for Developers.
8. The Scrum Master has the authority to allow Developers to start developing without
having the tasks identified and assigned.
Choose only ONE best answer.
A True
B False
"There are two problems with this statement: 1. The Scrum Master doesn't manage people
and cannot forbid team members from doing something and cannot order them to do
certain things. By training and coaching, S/he should always "convince” them to do the right
thing. 2. Developers identify the tasks and assign them gradually throughout the Sprint. We
don't do it upfront at the beginning of the Sprint."
9. The purpose of the Sprint Retrospective is to plan ways to increase .... (select
all correct answers)
The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness.
10 . According to the Scrum Guide, Scrum is founded on empiricism and lean thinking. What
else is true about Scrum? Select all correct answers
Choose ALL answers that apply.
A Scrum is a methodology for managing complex projects.
B Scrum is a traditional process but with Sprints and related artefacts
C Scrum is a framework for developing and maintaining complex products.
D Scrum employs an iterative, incremental approach to optimize predictability and control
risk.
11. The Scrum Team has just finished the Sprint Planning. According to this, choose all
correct statements from the following answers.
Choose ALL answers that apply.
A After the Sprint Planning, a Sprint cannot proceed without complete requirement
specification.
B After the Sprint Planning, a Sprint cannot proceed without a Sprint Goal.
C After the Sprint Planning, a Sprint can proceed without a complete Sprint Backlog.
D After the Sprint Planning, a Sprint cannot proceed without complete design and BRD or
FSD
12. A Definition of Done drives the quality of work and assesses when a task has been
completed. But what are the benefits of having tests in the definition of "Done"? Select all
correct answers
Choose ALL answers that apply.
A Increments would be closer to being potentially shippable.
B Increased transparency and the quality of the Increments
C Increments would be more complete.
D Reporting would be easier for the project manager.
15. The Scrum Team is planning to start the first Sprint. The Product Backlog item is ready
for selection in a Sprint Planning meeting when ......
Choose only ONE best answer.
A It meets the criteria in the definition of Ready.
B It can be Done within one Sprint
C All tasks required for completing it are identified.
17. The number of developers has increased from 8 to 15. Now the duration of the Daily
Scrum event is not 15 minutes but more. What's the best response to this problem?
Choose only ONE best answer.
A Divide the developers into two Scrum teams with minimum dependency
B Increase the timebox of Daily Scrums to 20 minutes
C Help the team self-organize and finish the Daily Scrums in 15 minutes.
D Finish the Daily Scrums in 15 minutes and let as many developers talk as possible
19. The Product Owner can transfer some of his/her accountability to developers.
Choose only ONE best answer.
A True
B False
The Product Owner can delegate his/her responsibilities to Developers, but s/he stays
accountable.
20. The Scrum Team is ready to release a product. From the following answers, choose 2
best of how the product's success may be evaluated.
Choose ALL answers that apply.
A By improving KPIs through frequent releases
B By increasing velocity
C By delivering an Increment every Sprint
D By passing all Sprint Backlog items
E By completing the Product Backlog at the end of the project
F By increasing the satisfaction of the customer
21. From the following answers, what are the responsibilities of Developers in Scrum?
Choose ALL answers that apply.
A Prioritize the Product Backlog
B Provide Estimates
C Design Software
D Create User Stories
E Make technical decisions
F Order the Product Backlog
The correct answer is 'B', 'C', & 'E' .
Designing the software is part of the development and should be done by the developers.
They are self-managed and make technical decisions. Estimation is the responsibility of the
developers because they are the people who will develop the item. The Product Owner does
the rest.
22. Developers realized that the Sprint Goal became obsolete and tried to convince the
Product Owner that the Sprint should be cancelled. What's the proper response from the
Scrum Master?
Choose only ONE best answer.
A It is OK
B The Scrum Master should stop this because Developers do not have the authority to
influence Sprint cancellation
C The Scrum Master should be involved in making this decision.
D The Product must cancel the Sprint as it is the decision of the Developers.
23. At which event must the Product Owner update the Product backlog? Choose only ONE
best answer.
A The PB may be updated anytime.
B The PB is updated after the Sprint Review
C The PB is updated before the Sprint Planning
D There is a special time to update the PB - Product Backlog Refinement
24. In 1 hour, there will be the Sprint Review. The Scrum Team realized they hadn't
completed the Sprint Backlog. What happens to the incomplete Product Backlog items?
Choose only ONE best answer.
A They won't be re-estimated, and they would be moved back to the Product Backlog.
B They would be re-estimated and moved back to the Product Backlog.
C They won't be re-estimated and would be moved to the next Sprint Backlog.
A To help people perform inspections & adaptations upon the transparency of the work
being undertaken and results being produced.
B To help discover a way of working that is continuously adaptable to everybody's actual
context and current circumstances.
C To adjust, adapt, change and gain flexibility.
26. …is the most valuable metric for a Product Owner to measure the progress of the
product. Choose only ONE best answer.
27. Sprint Backlog emerges during the Sprint. Choose only ONE best answer.
A False
B True
This answer is incorrect. The correct answer is 'B'.
While the Product Backlog items selected for the Sprint Backlog stay the same, the tasks
created by decomposing them always change and emerge during the Sprint.
28. From the following answers, choose the best. Which of the following best describes
transparency? Choose only ONE best answer.
A The process should be visible to key stakeholders or senior management.
B The whole process should be visible to everyone.
C Significant aspects of the process must be visible to those responsible for the outcome.
D The whole process should be visible to stakeholders.
29. From the following list of answers, choose one which less likely to be used by a Scrum
Team. Choose only ONE best answer.
A Big screen planning poker cards
B WBS Gantt Chart
C Scrum board
D Velocity
30. Which of the following is true about the Sprint Review according to the Scrum Guide?
(select all correct answers) Choose ALL answers that apply.
A It is a maximum of 4 hours in one month Sprint
B The Scrum Master organises this event
C The Scrum Master demonstrates the presentation
D Stakeholders should attend
E The Product Owner doesn't need to attend
31. As we know from the Scrum Guide Scrum Teams are self-managing and cross-functional.
Self-managing Scrum teams are characterised by their ability to ...
Choose only ONE best answer.
A Make project-based decisions
B Make local decisions
C Sit where they like
32. Developers decided to add mandatory testing for DoD. What are the benefits of it?
(Select all correct answers) Choose ALL answers that apply.
A Increments would be closer to being potentially shippable
B Increased transparency of the Increments
C Increments would be more complete
D Reporting would be more comfortable for the project manager
33. During the Sprint...... (select all answers that apply) Choose ALL answers that apply.
A The scope may be clarified as more is learned.
B Some Sprint Backlog items will be replaced with items from the Product Backlog if the
Sprint goal has been changed.
C The scope may be re-negotiated as more is learned.
D Some Sprint Backlog items would be removed from the Sprint Backlog to the Product
Backlog after the Product Owner confirmation.
34. One of the internal stakeholders wants to interact with Developers. What are the best
ways to make it? Select all that apply
Choose ALL answers that apply.
A At the Sprint Planning
B Via the Product Owner
C At the Sprint Review
D At the Daily Scrums
E At the Sprint Retrospective
35. Ordering the Product Backlog item is part of the Product Backlog refinement. Choose
only ONE best answer.
A True
B False
36. The Sprint Retrospective is one of the events in Scrum. Which of the following two items
are not topics of discussion within a Sprint Retrospective?
Choose ALL answers that apply.
A Sprint Backlog for the next Sprint
B Team relations
C Process improvements
D The functionality implemented as a result of the Sprint
E Definition of done
37. When should the Product Backlog items be refined? (Select all correct answers)
Choose ALL answers that apply.
A In the Sprint 0
B During the current Sprint, if they have not been refined in the previous Sprints.
C In one or two preceding Sprints
D In the time between the two Sprints
38. From the following answers, select all that apply. The responsibilities of Developers are
Choose ALL answers that apply.
A Pull Product Backlog items for the upcoming Sprint.
B Create new Product Backlog items
C Sizing the items from Product Backlog items
D Create tasks for Sprint Backlog items
E Reorder the Product Backlog
This answer is incorrect. The correct answer is 'A', 'C', & 'D'.
Developers' responsibility is to estimate the amount of work of Product Backlog items and
select an appropriate number of them for each Sprint. They also break down the items into
tasks during the Sprint. Measuring the project performance is the Product Owner's
responsibility, while measuring the Sprint performance is done by the Developers. Creating
new Product Backlog items ordering them (prioritization), and making sure that everyone
has a clear understanding of them is the Product Owner's responsibility.
39. Spikes may be used to learn more about a Product Backlog item before development
commences on that PBI.
a. True
b. False
A spike is learning activity before development begins and sometimes it may be helpful to
learn more about the work to aid refinement.
The “cone of uncertainty” shows the uncertainty is highest at the beginning of developing, a
product and reduces as we progress and more work is Done. This uncertainty can take many
dimensions, including duration, work, risks, etc.
50. There are many accountabilities for Developers in Scrum. Some of them are in the
following answers. Choose activities the Developers are always accountable for.
a. Sprint Retrospective
b. Sprint Review
c. Daily Scrum
d. Sprint Planning
During each Sprint Retrospective, The Scrum Team plans ways to increase product
quality by improving work processes or adapting the definition of Done if appropriate
and not in conflict with a product or organization standards.
52. The maximum duration of Sprint may be more than one month.
a. False
b. True
53. According to the Scrum Guide, to help with inspection, Scrum provides cadence in the
form of its five events. But what should be the frequency of Inspection in Scrum. Select all
that apply:
Other than the Sprint itself, which is container for all other events, each event in Scrum is a
formal opportunity to inspect and adapt something. To detect undesirable variances, Scrum
users must frequently inspect Scrum artifacts and progress toward a Sprint Goal. Their
inspection should not be so frequent that inspection gets in the way of the work. Inspections
are most beneficial when diligently performed by skilled inspectors at work.
54. According to the Scrum Guide, empiricism asserts that knowledge comes from
experience and making decisions based on what is observed. Also in Scrum empiricism
provides:
54.Stakeholders provide feedback in the Sprint Review, and this feedback impacts the next
Sprint Planning event.
a. False
b. True
55. From the following answers, choose the correct one. Which of the following helps PO
avoid waste in the project?
56. The Product Owner may choose to delegate the responsibility of estimating to
Developers or even to the Scrum Master. It is up to the PO.
a. True
b. False
Estimating is the responsibility of Developers by default. The PO doesn’t have such authority
in the first place to delegate it.
57. As the Sprint Planning meeting progresses , Developers realized there were too many
items in the print Backlog. What are the valid actions? Select all correct answers.
58. An organization is building different products by using the Scrum Framework. How can
they measure the success of using Scrum?
a. By reducing costs.
b. By increasing customer satisfaction
c. By delivering an increment every sprint
d. Throughout frequent releases and meeting value metrics or KPIs.
e. By improving the velocity.
Customer and end user satisfaction is essential. It s not an abstract measure, as in the case of
lines of code or velocity. There can be some KPIs for measuring the value of the releases, and
when improved will show our success. Increased velocity is desired but it s not directly
connected to value and can be misleading. This is the same as the production cost.
59. From the following answers choose correct about the DoD and Increment. Having a solid
DoD, and creating an Increment that meets it, has the following benefits:
Choose ALL answers that apply.
A Transparency of the Increment.
B Transparency of process
C Transparency about where we are and where we are going.
D Transparency about planning a Sprint.
E All answers are incorrect
60.
As we know, the Daily Scrum is a 15-minute event for the Developers of the Scrum Team. To
reduce complexity, it is held at the same time and place every working day of the Sprint. If
the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they
participate as Developers. What are the characteristics of effective Daily Scrum?
Choose ALL answers that apply.
A Promotes self-organization and collaboration
B Ensures the Scrum Team consensus on the Sprint Goal
C Promotes transparency and a shared understanding of the progress of valuable outcomes.
D Creates focus and reduces waste
E All answers are correct
61. What are the characteristics of a good Sprint Goal?
Choose ALL answers that apply.
A Size
B Focus
C Difficulty
D Flexibility
E Purpose
62. During the Sprint Planning, The PO asked the Scrum Team to postpone the Sprint
Planning as they (the Scrum Team) didn't process all the feedback from the Sprint Review
into the Product Backlog yet. They argue it makes no sense to plan the Sprint if the Product
Backlog isn't in a good state. How should the Scrum Master respond to this case?
We rarely have complete and perfect information in complex environments. Practice the art
of the possible and keep using Scrum and an empirical approach. Adapt and improve as you
go. All work, including refinement, happens inside Sprints. There may be times when high-
value work is not ready/refined enough, and so development work must wait until this is
complete. We should work on other highly ordered work instead or focus on refinement as
the priority.
63. What factors should be considered by the Product Owner in the release decision (select
four)? Choose ALL answers that apply.
A The amount of work remaining toward the Sprint Goal
B The customers that will be constrained by the new release
C Approval of the Key Stakeholders
D The costs and benefits of the upgrade
E Can customers actually absorb the new release?
F Does the Increment meet the Definition of "Done"?
G The risk that the product's value can get out of line with the marketplace
64. As a Product Owner, your focus must always be on getting the product to its next
shippable state-a Minimum Viable Product (MVP). Minimum Viable Product is about the
validation of the hypotheses. You need to validate this (these) kind(s) of hypothesis(es)
Choose ALL answers that apply.
A Incremental
B Market
C Productive
D Technical
65. How does the Product Owner transfer his or her marketplace knowledge to the Scrum
Team (select all answers that apply)? Choose ALL answers that apply.
A Through Product Backlog Refinement
B Through Daily Scrums
C Through Sprint Reviews
D Through Daily ad hoc interactions
E Through Sprint Retrospectives
66. How can the Product Owner count PCR (Product Cost Ratio)? Choose only ONE best
answer.
A By comparing the total expenses and total costs for the product, except operational costs
compared to revenue.
B By comparing the total expenses and total costs for the product, incl. operational costs
compared to revenue.
C By summarizing all expenses for the product, but not costs
67. Scrum Master is against it and asked the PO not to invite stakeholders to this meeting,
as this event is only for the Scrum Team. Choose only ONE best answer.
A It is the correct decision of the Scrum Master
B it is not correct decision from the Scrum Master
68.The Scrum Master serves the organization in several ways, including: Choose ALL answers
that apply.
A Leading, training, and coaching the organization in its Scrum adoption
B Planning and advising Scrum implementations within the organization
C Helping employees and stakeholders understand and enact an empirical approach for
complex work
D Removing barriers between stakeholders and Scrum Teams
E All answers are incorrect
69. What does Scrum employ to optimize predictability and control risk? From the following
answers, choose correct Choose ALL answers that apply.
A Contingency plans
B Incremental approach
C Roadmap
D Iterative approach
E Risk planning
70. A developer in the Scrum Team added a new requirement in the Sprint Backlog, and this
item is not from the Product Backlog. This was discovered on the last day of the Sprint
before the Sprint Review by other Developers. What should the Developers do? Select two
correct answers from the following.
Choose ALL answers that apply.
A Developers have to continue their job and include this item in the Increment.
B Developers should remove this item from the Increment before the Sprint Review.
C Developers have to ask the Product Owner to get approval from the stakeholders to add
this item
D The Scrum Team should discuss this issue at the Sprint Retrospective event.
71. Scrum Teams use the information in the Scrum artifacts to make decisions. The
effectiveness of these decisions depends on Choose only ONE best answer.
A The artifacts adaptability
B The artifacts agility
C The artifacts transparency
D The artifacts format
72. At the Sprint Review, the Scrum Team realise that a Product Backlog item does not meet
their Definition of Done. What should the team do with the unDone item? Select all correct
answers Choose ALL answers that apply.
A Show it at the Sprint Review anyway.
B Do not include the item in the Increment for this Sprint.
C Return it to the Product Backlog.
D If the stakeholders agree, the Product Owner can accept it and release it to the users.
73. Using Scrum ensures that all resources on a project will be utilised in the most efficient
way. Choose only ONE best answer.
A False
B True
This answer is incorrect. The correct answer is 'A'.
Scrum is more about value delivery (not only money). Sometimes it is necessary to de-
optimize efficiency in order to optimise value.
NEXT
74. Which of the following statements is accurate about the Developers deciding to allocate
an amount of their capacity to unplanned work?Choose only ONE best answer.
A The importance of the Sprint Goal increases. It can help the Developers maintain their
focus.
B Reserving capacity for unplanned work should not be allowed as it introduces risks of
failing to achieve the Sprint Goal.
C Reserving capacity for unplanned work must not be allowed as it increases the risk of
failing to deliver an Increment.
certification! 🎉