Professional Documents
Culture Documents
12-286 Revision Final
12-286 Revision Final
net/publication/277304961
CITATIONS READS
193 6,235
3 authors:
David Sanders
University of Nevada, Reno
92 PUBLICATIONS 1,603 CITATIONS
SEE PROFILE
All content following this page was uploaded by Zachary B. Haber on 27 May 2015.
Precast columns
Four precast column models were tested with different
column-footing connection details. Two models were
connected directly to the footing (denoted NP for no
pedestal), and two models were connected atop a precast
pedestal (denoted PP for precast pedestal), one-half column
diameter in height, to reduce the moment demand on the
spliced region. Each precast column was first cast as a hollow
Fig. 2—HC connection: (a) HCNP connection details; (b)
shell that incorporated the main longitudinal and transverse
transition bar; and (c) connection region before closure
reinforcing steel. After connection to the footing, the core
grouting.
was filled with self-consolidating concrete (SCC), which is a
highly flowable concrete able to spread into place and encap- by the manufacturer of the couplers, to complete the instal-
sulate reinforcement without mechanical vibration. lation. It was found that even though transition bars were
Figure 2 shows the details of the HC connection without customized to each location around the column, small steel
a pedestal (HCNP). The precast shell for the HC models shims were required to fill gaps between heads. After instal-
had a reduced section at the base, which allowed for the lation of transition bars, the spiral was raised and tied around
threaded collars to protrude from the shell and for working the longitudinal bars (Fig. 2(c)), and the connection region
room such that the reinforcing bars in the footing and those was formed and filled by pumping a cementitious grout. The
in the column could be connected. A template was used to construction time for this connection could vary greatly,
align longitudinal bars in the footing and column shell to depending on the alignment of longitudinal bars.
meet the tight tolerances required to join the two bar sets The grouted coupler (GC) connection details and
with a transition bar measuring approximately 12 bar diam- construction photos are shown with the pedestal (GCPP) in
eters (Fig. 2(b)). Each transition bar was manufactured to Fig. 3(a). The grout sleeve couplers were cast into the base
fit in an assigned location around the cross section, which of the column shell with PVC ducts protruding to allow for
is a process that could require extra construction time in the pumping grout into the sleeves (Fig. 3(b)). A corresponding
field. Before installing these bars, a spiral was placed around pattern of longitudinal reinforcing bar dowels were cast in the
the bars protruding from the footing, and the column shell footing/pedestal that protruded seven bar-diameters from the
was lowered onto a layer of bedding mortar on the footing. surface of concrete (Fig. 3(c)). The field end of the GC has
Once the shell was plumb, transition bars were inserted, and length and location tolerances for reinforcing bar dowels of
each HC was torqued to 150 ft-lb (203 N-m), as specified approximately 0.5 and 0.9 in. (13 and 23 mm), respectively,