DOCUMENT LOG
DOCUMENT NUMBER
SAPL‐MEWA‐R‐2021‐XXXX
1. INTRODUCTION .......................................................................................................................... 5
SCHEDULING OVERVIEW .................................................................................................................... 5
SCHEDULING IMPORTANCE AND BENEFITS.............................................................................................. 5
SCHEDULING KEY CONCEPTS AND BASIC REQUIREMENTS .......................................................................... 6
SCHEDULE TYPES AND PROJECT SCHEDULE HIERARCHY/LEVELS .................................................................. 7
SCHEDULE PLANNING AND DEVELOPMENT PROCESSES ........................................................................... 12
2. SCHEDULE MANAGEMENT ........................................................................................................ 14
SCHEDULE SPECIFICATION ................................................................................................................ 14
SCHEDULING TOOL ......................................................................................................................... 19
CALENDARS AND WORK PERIOD ........................................................................................................ 20
SCHEDULE LOGIC............................................................................................................................ 20
3. SCHEDULE DEVELOPMENT / STRUCTURE .................................................................................. 21
SCHEDULE ID AND NAME ................................................................................................................. 21
WORK BREAKDOWN STRUCTURE (WBS) ............................................................................................ 22
3.2.1. WBS STRUCTURE AND CODE ............................................................................................................ 23
RESOURCES STRUCTURE, CODE AND DICTIONARY .................................................................................. 25
ACTIVITY CODE .............................................................................................................................. 26
CONTROL LEVEL SCHEDULE............................................................................................................... 27
3.5.1. CONTROL SCHEDULE LAYOUT ............................................................................................................ 28
3.5.2. CONTROL SCHEDULE NARRATIVE REPORT ............................................................................................ 28
LOOK AHEAD SCHEDULE ................................................................................................................... 29
3.6.1. LOOK‐AHEAD SCHEDULE LAYOUT ....................................................................................................... 29
CONTRACTORS RECOVERY SCHEDULE .................................................................................................. 29
3.7.1. RECOVERY SCHEDULE LAYOUT ........................................................................................................... 29
3.7.2. RECOVERY SCHEDULE NARRATIVE REPORT ........................................................................................... 29
CONTRACTORS AS BUILT SCHEDULE ................................................................................................... 30
3.8.1. AS BUILT SCHEDULE LAYOUT ............................................................................................................ 30
4. SCHEDULE HEALTH CHECK PROCEDURE .................................................................................... 31
BASELINE SCHEDULE REVIEW ............................................................................................................ 31
4.1.1. COMPLIANCE WITH SCHEDULE SPECIFICATION ...................................................................................... 31
4.1.2. UNDERSTANDING THE PROJECT ......................................................................................................... 31
4.1.3. SCHEDULE SUBMITTAL..................................................................................................................... 31
4.1.4. COMMON ERRORS ASSOCIATED WITH THE PROGRAM SUBMITTED BY THE CONTRACTOR .................................. 32
4.1.5. REVIEW SCHEDULE QUALITY ............................................................................................................. 32
4.1.6. REVIEW SCHEDULE NARRATIVE ......................................................................................................... 35
CONTROL SCHEDULE REVIEW ............................................................................................................ 35
List of Figures
FIGURE 1 CONTROL SCHEDULE LEVELS / HIERARCHY ................................................................................................ 8
FIGURE 2 PROCESS MAP FOR SCHEDULE PLANNING AND DEVELOPMENT.................................................................... 12
FIGURE 3 WORK BREAKDOWN STRUCTURE (WBS) SAMPLE.................................................................................... 24
FIGURE 4 RESOURCE BREAKDOWN STRUCTURE (RBS) SAMPLE ................................................................................ 25
List of Tables
Scheduling Overview
Scheduling provides a way of contributing input during project execution concerning means, methods,
techniques, sequences, or other conditions affecting the plan’s outcomes. It uses the baseline established
in planning and aligns the update of the schedule as a methodology of updating and analysis to allow for
periodic progress and forecast reporting. Additionally, it establishes a basis for change management and
project execution control to achieve successful outcomes.
Project scheduling ensures the development of effective schedule models through the application of skills,
tools,
techniques, and intuition acquired through knowledge, formal and informal training, and experience. A
schedule model rationally organizes and integrates various project components (e.g., activities, resources,
and logical relationships) to
optimize the information available to the project management team and facilitate the likelihood of a
successful project completion within the approved schedule baseline.
Scheduling provides a basis for management of the work, improves communications, and facilitates
coordination. Using a schedule improves the effective use of resources. The project schedule gives the
user a baseline to monitor and control the work.
Scheduling provides a means for obtaining feedback since the development and use is a team effort
incorporating the ideas and objectives of those responsible for the work.
Scheduling is one of the basic requirements of project planning and analysis. The schedule model, once
completed, becomes an effective planning tool for
(a) engaging communications that focus on optimizing future actions,
(b) assisting proactive collaboration, and
(c) creating a project performance management system.
All schedules shall apply the Critical Path Method (CPM), be submitted on time as per approved
governance and policies (Schedule shall be submi ed within 15 days from the date of site handover) and
Level1 ‐
Management
Schedule (MS)
Level2 ‐
Summary
Schedule
Level3 ‐ Control
Schedule (CS)
Level4 ‐ SUbject
Matter Schedule
Level5 ‐ Detalied
Trackers
Planning should be done top‐down, as the initial plans are conceptual and very high level, but with the
expectation that the objectives are to be met. Status, on the other hand, is bottom‐up, as the lower‐level
trackers and schedules are used to update the higher‐level schedule activities.
Schedule levels are an indication of degree of detail of the schedule. Schedule levels are not an indication
of schedule maturity.
Baseline schedule
The baseline schedule derives from a schedule model to meet the project execution plan and achieve
management approval for use as a baseline. It is the approved version of a schedule model ,identifies the
initial critical path and is used as a basis for measuring progress , identify trends ,comparison to actual
status to determine if a change, corrective action, or preventive action is necessary, show impact of any
milestone or completion date variance and reporting progress. It will be the foundation for cash flow
planning, resource managing, trending, forecasting for cost and schedule reporting.
Schedule baseline is one of the elements of project management documents that should be updated
regularly.
However, it should be agreed upon by (Consultant/Engineer) prior to commencing significant work and is
not progressed.
The baseline should not be modified or revised as part of the normal progress update process. Rather, if
significant changes, particularly contract modifications, occur during the project then a new baseline
should be developed and submitted for approval.
The baseline schedule documentation is recorded from the assumptions, constraints, and parameters‐‐as
well as from the contract and supplementary documentation‐‐that goes into the development of the
baseline schedule.
The baseline schedule documentation includes a narrative that describes baseline schedule development,
the critical path, and key characteristics of the schedule model. Each stakeholder’s input and assumptions
are clearly identified.
The baseline schedule provides the documentation and foundation for schedule change or delay and
To develop and use a target schedule effectively, it is necessary to have a performance management
strategy in place. This includes measuring the variances between the target start/finish dates and how
quickly the project work is advancing. The targets can be adjusted to take early and late start or finish
dates into account based on how interrelated schedule activities are progressing. This is helpful in
determining best‐ and worst‐case scenarios and the impact they have on the overall schedule.
Schedule forecasts are the estimates or predictions of conditions and events in the project’s future based
on information and knowledge available at the time the schedule is calculated. In the project
management, forecasts are updated and reissued based on work performance information provided as
the project is executed. The information is based on the project management’s past performance and
expected future performance and includes earned value performance indicators that could impact the
project in the future.
The schedule forecasts are derived from progress against the schedule baseline and computed time
estimate to complete (ETC). This is typically expressed in terms of schedule variance (SV) and schedule
performance index (SPI). For projects not using earned value management, variances against the planned
finish dates and forecasted finish dates are provided. In project management, forecast may be used to
The outputs of schedule planning and schedule development are used as inputs for asset planning and
project cost and
Schedule Specification
NWC refers to CSI – Sec on 013200 and the Contractor shall comply with the following general
requirements in preparing Construction Schedules.
Engineer shall require that the work be managed using the criteria outlined in this document.
Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting,
with capability of producing CPM reports and diagrams within 24 hours of request.
All correspondence and submittals shall be in both Arabic and / or English.
Developed Procedure shall be used for schedule development, updating, monitoring, controlling,
revising, and reporting.
Prescheduling Conference: Conduct conference at Project site to comply with NWC scheduling
requirements and review methods and procedures related to the Contractor's construction
schedule, including, but not limited to, the following:
o Review Scope of Work, Contract Documents, Project Execution Plan, and format for
reports.
Scheduling Tool
The approved tool for planning, scheduling, managing, and executing projects, programs, and portfolios
is Oracle Primavera P6 Professional Project Management So ware. that has been developed specifically
to manage CPM construction programming, scheduling, and reporting indicated for Project. All project
data shall be loaded into P6, and results shall be extracted from P6. The approved P6 version to be used
by all Consultants and Contractors shall be compatible with the latest version used at NWC.
Schedule Logic
Relationships: Schedule activity relationships shall adhere to strict CPM network techniques with
proper predecessor/successor usage based on hard logic (technical or contractual) and justifiable
so logic. Although P6 recognizes and handles four rela onship types, start‐to‐finish (SF)
relationships are not allowed. The schedulers shall use finish‐to‐start (FS), finish‐to‐finish (FF), and
start‐to‐start (SS) as required to close a logic loop. All activities shall have at least one predecessor
and at least one successor. The only exceptions to this rule are Start of Project (which has no
predecessor) and End of Project (which has no successor).
Leads and Lags: The use of negative lags (Lead) is prohibited. lags shall be used only when the
justification is compelling and agreed upon with the NWC Scheduling Dept. In most cases, an
additional activity is more logical than a lag.
Activity Code
Activity codes are used to classify, categorize, and organize activities based on reporting needs. Activity
codes are usually created and assigned at the beginning of the project.
Moreover, it enables the project controls team to filter, group, sort, and report activity information
according to unique requirements.
The NWC activity codes have been defined and may include but not limited to the following:
Scheduler may increase more activity codes or values more than mentioned above if needed and shall
be defined in schedule narrative.
4.1.4. Common errors associated with the program submitted by the Contractor
During reviewing, assessment, or approving the program, the Engineer should notice certain errors
that might be done by the Contractor scheduler. These errors may include but not limited to the
following:
Check Schedule Structure (Level of Details, Activities Duration, Approved Layout.)
Check Schedule Data (Resources, costs, etc..).
Run Schedule, ensure no changes
Check NTP and Completion dates
Check all interim Milestone dates
Check Organizational Codes
Review WBS structure and Code
Review Activity Code Dictionaries
Review Resource Code Dictionaries
Review Calendars
Review Resources loading by Manpower, Equipment and Bill of Quantities
5. Appendices
Appendix No.1: WBS Code and Structure
Appendix No.2: RBS Code and Structure
Appendix No.3: Narrative Report Template
Appendix No.4: Schedules Health Check List
Appendix No.5: Compliance Sheet
Appendix No.6: Cash Flow
6. References
1. Practice standard for scheduling / Project Management Institute. Third edition 2019. Revised
edi on of Prac ce standard for scheduling, c2011. ISBN: 978‐1‐62825‐561‐4
2. Planning and Scheduling Professional (PSP), First Edition, Revised Copyright © 2014, By AACE
Interna onal. ISBN: 978‐1469968919
3. Practice standard for work breakdown structures ‐ Third edi on 2019. ISBN: 978‐1‐62825‐619‐2
4. DCMA 14‐Point Schedule Assessment, by Ron Winter, PSP, Copyright © January 7, 2011
5. Skills & Knowledge of Cost Engineering, 6th Edi on
6. Total Cost Management (TCM) Framework, 2nd Edi on, Copyright© AACE® Interna onal, 2015
7. AACE® Interna onal Recommended Prac ce No. 27R‐03 – Rev. November 12, 2010
8. AACE® Interna onal Recommended Prac ce No. 37R‐06 – Rev. March 20, 2010
9. White Book Document No. EPM‐KPP‐PR‐000001 Rev 001
10. Project Scheduling Rules,2nd edi on © 2013 Nader Khorrami Rad, PMP. ISBN 978‐87‐403‐0333‐9
Activity ID
NWC.CL.RU.WTR.221100
Project Documents
Submittals NWC.CL.RU.WTR.221100 NWC.CL.RU.WTR.221100 NWC.CL.RU.WTR.221100 NWC.CL.RU.WTR.221100 NWC.CL.RU.WTR.221100
Enterprise Zone 1 Zone 1 Zone 1 Zone 1 Zone 1
Enterprise
WBS Code
WBS Name Page 1 of 1 © Oracle Corporation
ResponsibleManager
Appendix No.02
Table of Contents
1. Project Brief and General Information ............................................................................................. 2
2. Project Scope of Work ....................................................................................................................... 2
3. Project Location / Masterplan / Layout ............................................................................................ 2
4. Key Dates / Milestones / Level-1 ...................................................................................................... 2
5. Work Breakdown Structure ............................................................................................................... 3
5.1 Project Decomposition ................................................................................................................... 3
5.2 Engineering WBS............................................................................................................................ 3
5.3 Procurement WBS .......................................................................................................................... 3
5.4 Construction WBS (Main Decomposition)................................................................................... 3
6. Calendars ............................................................................................................................................. 3
7. Activity Codes & ID ............................................................................................................................. 3
8. Construction Sequence...................................................................................................................... 4
9. Critical Path.......................................................................................................................................... 4
10. Schedule Basis of Estimation ....................................................................................................... 4
11. Resources Breakdown Structure .................................................................................................. 4
12. BOQ Main Items.............................................................................................................................. 4
13. Production Rates ............................................................................................................................ 4
14. Manpower Histogram ..................................................................................................................... 5
15. Equipment Histogram ..................................................................................................................... 5
16. Schedule Risks................................................................................................................................ 5
17. Appendices ...................................................................................................................................... 5
I. Schedule Health Check List .......................................................................................................... 5
II. Compliance Sheet .......................................................................................................................... 5
III. BOQ .............................................................................................................................................. 5
IV. Project Baseline. ......................................................................................................................... 5
V. Critical Paths. .................................................................................................................................. 5
VI. Histograms. .................................................................................................................................. 5
VII. CD. ................................................................................................................................................ 5
Item Description
Contractor Name
Consultant Name
Project PO No.
Project Name
Project Cost
Project Start Date
Project Finish Date
Project Duration
Project Site Hand Over
Project location
6. Calendars
8. Construction Sequence
9. Critical Path
- Critical path activities only
- List of Required Permits from Authorities (If Any).
17. Appendices
V. Critical Paths.
VI. Histograms.
VII. CD.
Project Name (Enjaz) : :(اﺳﻢ اﳌﺸﺮوع )ﺑﻨﻈﺎم إﻧﺠﺎز Enjaz Project No. / ERP No. : (رﻗﻢ اﻟﻌﻘﺪ اﻟ ﺸﻐﻴ )ﺑﻨﻈﺎم إﻧﺠﺎز
Submission Date ﺗﺎر ﺦ اﻟﺘﻘﺪﻳﻢ Revised ﻣﻌﺪﻟﺔ Baseline ﺧﻂ أﺳﺎس Schedule Type ﺗﺼ ﻴﻒ ا ﺪول اﻟﺰﻣ
ﻣﺴﻠﺴﻞ اﻟﻮﺻﻒ Acceptable ﻣﻘﺒﻮل ﻻﻳﻮﺟﺪ ﻣﻼﺣﻈﺎت
No Description Yes ﻌﻢ No ﻻ N/A Remarks
General Items اﻟﺒﻨﻮد اﻟﻌﺎﻣﺔ
(ﺗﻮﺣﻴﺪ ﻟﻐﺔ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ )ﻋﺮ ﻴﺔ أو إﻧﺠﻠ ﻳﺔ
1
Unified Schedule Language (Arabic, English)
ﻳﻮم ﻣﻦ ﺗﺎرﺦ ﺴﻠﻴﻢ اﳌﻮﻗﻊ١٥ ﺗﻘﺪﻳﻢ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﺧﻂ اﻷﺳﺎس )اﻹﺻﺪاراﻷول( ﻣﻦ اﳌﻘﺎول ﺧﻼل
2
Baseline Schedule (1st Revision) Submission within 15 days from Site Handover
(٣٫١ ﻗﺴﻢ- إﺳﻢ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﻣﻄﺎﺑﻖ ﻹﺳﻢ اﳌﺸﺮوع اﻟﺘﻌﺎﻗﺪي ﺑﻨﻈﺎم إﻧﺠﺎز ﻣﻊ إﺿﺎﻓﺔ رﻗﻢ اﻹﺻﺪاروﺗﺎر ﺨﮫ )دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ
3 Schedule Name Schedule same as contractual name in addition to Revision No. and date of submission
(Refer to Scheduling Management Manual - Section3.1)
(٣٫١ ﻛﻮد اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﻣﺘﻮاﻓﻖ ﻣﻊ دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ )ﻗﺴﻢ
4
Schedule ID Schedule Comply with Scheduling Management Manual (Refer to Scheduling Management Manual - Section3.1)
ﻣﻊ اﻹﻟ ام ﺑﺎﻹﺻﺪاراﳌﻌﺘﻤﺪ ﻟﺪى ﺷﺮﻛﺔ اﳌﻴﺎﻩ اﻟﻮﻃﻨﻴﺔ، Pdf و ﺔXER ﺗﻘﺪﻳﻢ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﺑﺼﻴﻐﺔ
5
Submit Electronic copy (XER file) along with the hard copy of project schedule provided and compatible with the latest version used at NWC
(٣ ﻣﺮﻓﻖ رﻗﻢ،٤٫١٫٦ ارﻓﺎق ﺗﻘﺮﺮﺗﻔﺼﻴ ﻋﻦ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ واﳌﻄﺎﺑﻖ ﻟﻠﻨﻤﻮذج اﳌﺮﻓﻖ ﺑﺪﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ )ﻗﺴﻢ
6
Attach Schedule Narrative Report (Refer to Scheduling Management Manual - Section4.1.6 , Appendix No.3)
(٦ ﻣﺮﻓﻖ رﻗﻢ- ارﻓﺎق ﻣﻨﺤ اﻟﺘ ﻠﻔﺔ اﳌﻌﺘﻤﺪ ﻣﻊ ﻣﺮاﻋﺎة أن ﺗﻜﻮن ﺴﺐ اﻹﻧﺠﺎزا ﻄﻄﺔ اﳌﺪرﺟﺔ ﺑﻨﻈﺎم إﻧﺠﺎز ﻣﻤﺎﺛﻠﺔ ﻟ ﺴﺐ اﻹﻧﺠﺎزا ﻄﻄﺔ ﺑﺎﻟ ﻧﺎﻣﺞ اﻟﺰﻣ )دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ
7
Attach Signed S-Curve (Refer to Scheduling Management Manual - Appendix No.6)
(ارﻓﺎق ﻣﻨﺤﻨﻴﺎت اﻟﻌﻤﺎﻟﺔ و اﳌﻌﺪات )ﻣﻠﻔﺎت اﻛﺴﻞ
8
Attach Manpower & Equipment histograms in trades (Excel Sheet )
(ارﻓﺎق ﻣﻌﺪﻻت اﻻداء ﻟﻠﻌﻤﺎﻟﺔ و اﳌﻌﺪات )ﻣﻠﻔﺎت اﻛﺴﻞ
9
Attach Productivity Rate (Excel Sheet)
(ارﻓﺎق ﺗﻔﺼﻴﻞ اﻟﺘ ﻠﻔﺔ ﻟﻸ ﺸﻄﺔ )ﻣﻠﻔﺎت اﻛﺴﻞ
10
Attach Cost Break down (Excel Sheet)
ارﻓﺎق ﺟﺪاول اﻟﻜﻤﻴﺎت اﳌﻌﺘﻤﺪة اﻟﺘﻌﺎﻗﺪﻳﺔ
11
Attach Contractual signed BOQ
ﺣﺎل ﺗﻜﺮارﺗﻘﺪﻳﻢ اﻟ ﻧﺎج اﻟﺰﻣ ارﻓﺎق ﻗﺎﺋﻤﺔ اﻹﻣﺘﺜﺎل ﻟﻠﻤﻼﺣﻈﺎت ﻋ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ
12
Attach the list of compliance sheet to the schedule, in case of schedule resubmission
ارﻓﺎق ﺧﻄﺎب إﻋﺘﻤﺎد ﺻﺎﺣﺐ اﻟﺼﻼﺣﻴﺔ ﺣﺎﻟﺔ اﻟﺘﻤﺪﻳﺪ اﻟﺮﺳ
13
Attach the letter of approval of the authorized person in the case of an official extension of time
Main Technical Items اﻟﺒﻨﻮد اﻟﻔﻨﻴﺔ اﻷﺳﺎﺳﻴﺔ
ﺗﺎرﺦ ﺎﻳﺔ اﳌﺸﺮوع ﻣﻤﺎﺛﻞ ﻟﺘﺎرﺦ اﻟ ﺎﻳﺔ اﻟﺘﻌﺎﻗﺪﻳﺔ أو اﳌﻌﺪﻟﺔ اﳌﻌﺘﻤﺪة، ﺗﺎرﺦ ﺑﺪاﻳﺔ اﳌﺸﺮوع ﻣﻤﺎﺛﻞ ﻟﺘﺎرﺦ إﺳﺘﻼم اﳌﻮﻗﻊ
1
Project Start Date like Site Hand Over date & Project Finish Date Like Contractual or Revised approved Completion Date
ﻗﻴﻤﺔ اﳌﺸﺮوع اﻹﺟﻤﺎﻟﻴﺔ ﺑﺎﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﻣﻤﺎﺛﻠﺔ ﻟﻘﻴﻤﺔ اﻟﻌﻘﺪ ﺑﺪون ﻗﻴﻤﺔ أﻋﻤﺎل اﻟ ﺸﻐﻴﻞ واﻟﺼﻴﺎﻧﺔ
2
The total project value in the Schedule is like the contract value without operation and maintenance works Value
إدراج ﺗﺎرﺦ ﺎﻳﺔ اﳌﺸﺮوع اﻹﻟﺰاﻣﻲ ﻋ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ
3
Finish Date shall be mentioned (Must Finish By)
ﻴ ﻠﺔ أﻋﻤﺎل اﳌﺸﺮوع ) ﺸﻤﻞ ﻞ ﻧﻄﺎق وﻣﺨﺮﺟﺎت اﳌﺸﺮوع ( و ﻣﻨﻈﻤﺔ ﺎﻟﺘﺎ
((1) اﳌﺮﻓﻖ رﻗﻢ، ٣٫١ ﻗﺴﻢ- اﻹﻏﻼق )دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ، اﻹﺧﺘﺒﺎرات، اﻟﺘﻨﻔﻴﺬ، اﻟﺘﻮرﺪات، اﻟﺘﻘﺪﻳﻤﺎت اﻟ ﻨﺪﺳﻴﺔ، اﳌﻘﺪﻣﺎت، اﳌﻌﺎﻟﻢ
4
Project WBS Structure (Shall consider all SOW ,Deliverables) and arranged like: Milestones, Preliminaries, Engineering, Procurement, Construction, Testing & Commissioning, Closeout & As-Built (Refer to
Scheduling Management Manual - Section3.2-Appendix No.1)
((1) اﳌﺮﻓﻖ رﻗﻢ، ٣٫٢٫١ ﻛﻮد ﻴ ﻞ أﻋﻤﺎل اﳌﺸﺮوع ﻣﺘﻮاﻓﻖ ﻣﻊ دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ ) ﻗﺴﻢ
5
Project WBS Code Comply with Scheduling Management Manual (Refer to Scheduling Management Manual - Section3.2.1-Appendix No.1)
( اﻻﺟﺎزات اﻟﺮﺳﻤﻴﺔ ﺑﺎﳌﻤﻠﻜﺔ- اﻟﺘﻘﻮ ﻢ ا ﺎص ﺑﺎﳌﺸﺮوع واﻷ ﺸﻄﺔ واﳌﻮارد )أﻳﺎم و ﺳﺎﻋﺎت اﻟﻌﻤﻞ اﻟﺘﻌﺎﻗﺪﻳﺔ
6
Project , Activities & Resources Calendar (Contractual working days & Hrs., KSA Official holidays)
(٣٫٤ إﺳﺘﺨﺪام ﻛﻮد اﻷ ﺸﻄﺔ اﳌﺘﻮاﻓﻖ ﻣﻊ دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ )ﻗﺴﻢ
7
Project Activity Codes Comply with Scheduling Management Manual (Refer to Scheduling Management Manual - Section3.4)
ﻣﺴ اﻟ ﺸﺎط ﻓﺮﺪ وﻏ ﻣﻜﺮر
8
Project Activity Name shall be unique and not repeated
اﻟﺘﻮاﻓﻖ ﻣﻊ اﳌﻌﺎﻟﻢ اﻷﺳﺎﺳﻴﺔ ﻟﻠﻤﺸﺮوع
9
Compliance with Major Contract Milestones
FF ور ﻂ ﻣﻌﺎﻟﻢ اﻟ ﺎﻳﺔ ﺑﺎﻟ ﺸﺎط اﻟﺴﺎﺑﻖ ﻌﻼﻗﺔSS ر ﻂ ﻣﻌﺎﻟﻢ اﻟﺒﺪاﻳﺔ ﺑﺎﻟ ﺸﺎط اﻟﻼﺣﻖ ﻌﻼﻗﺔ
10
Start Milestones shall be linked by SS relationship with Successors and Finish Milestones shall be linked by FF relationship with predecessors
اﻹﻋﺘﻤﺎدات- ﺗﻘﺪﻳﻤﺎت اﳌﻮاد- اﻟﺮﺳﻮﻣﺎت اﻟ ﻨﺪﺳﻴﺔ: ﺗﻘﺴﻴﻢ أ ﺸﻄﺔ اﻟﺘﻘﺪﻳﻤﺎت اﻟ ﻨﺪﺳﻴﺔ واﻟ ﺗﺘﻀﻤﻦ وﻻ ﺗﻘﺘﺼﺮﻋ
11
Engineering Activities includes but not limited to the following: Shop drawings, Material submittals and Method statements in respect to each discipline
اﻟﺘﻮﺻﻴﻞ ﻟﻠﻤﻮﻗﻊ( ﻟ ﻞ ﻗﺴﻢ- اﻟ ﻦ- اﻟﺘﺠﻤﻴﻊ/ اﻟﺘﺼ ﻴﻊ- )أﻣﺮاﻟﺘﻮرﺪ: ﻗﺼ ة اﻷﺟﻞ( واﻟ ﺗﺘﻀﻤﻦ وﻻ ﺗﻘﺘﺼﺮﻋ، ﺗﻘﺴﻴﻢ أ ﺸﻄﺔ اﳌﺸ ﻳﺎت )ﻣﻮاد ﻃﻮ ﻠﺔ اﻷﺟﻞ
12 Procurement Activities includes but not limited to detailed dates for procuring long lead items & short lead items that illustrate issuance of Purchasing Order, fabrication / assembly, shipping, and delivery to
site in respect to each discipline
( ﻳﻮم )أو ﻛﻤﺎ ﻳﺘﻢ اﻹﺗﻔﺎق ﻋﻠﻴﮫ ﻣﻊ اﻹﺳ ﺸﺎري٩٠ ﺗﻔﺼﻴﻞ أ ﺸﻄﺔ اﳌﺸ ﻳﺎت ﻟﻠﻤﻮاد ﻃﻮ ﻠﺔ اﻷﺟﻞ و اﳌﻮاد اﻟ ﺗﺤﺘﺎج دورة ﺗﻮرﺪ ﺎ ﻷﻛ ﻣﻦ
13
Breakdown of the LLI procurement activities which are the materials that need a supply cycle of more than 90 days (or as agreed upon with the consultant)
ً
ﻳﻮﻣﺎ١٤ إﻋﺘﻤﺎد اﻟﺘﻘﺪﻳﻤﺎت اﻟ ﻨﺪﺳﻴﺔ ﻳﺠﺐ أﻻ ﺗﺘﺠﺎوز/ ﻣﺪة أ ﺸﻄﺔ ﻣﺮاﺟﻌﺔ
14
Engineering Activities of Review/Approval Duration shall not exceed 14 days
ﻳﺠﺐ ﺑﺪء أﻋﻤﺎل اﻟﺘﻨﻔﻴﺬ ﻌﺪ إﻧﻘﻀﺎء ﺬﻩ اﳌﺪة، ﺷ ﺮ١٢ ﺣﺎل ﻣﺪة اﳌﺸﺮوع أﻗﻞ ﻣﻦ أو ﺴﺎوي ﺑﺤﺪ أﻗ%١٠ = ﻣﺪة أﻋﻤﺎل اﻟﺘﺠ ات ﺑﺎﳌﺸﺮوع
ﻳﺠﺐ ﺑﺪء أﻋﻤﺎل اﻟﺘﻨﻔﻴﺬ ﻌﺪ إﻧﻘﻀﺎء ﺬﻩ اﳌﺪة، ﺷ ﺮ١٢ ﺣﺎل ﻣﺪة اﳌﺸﺮوع أﻛ ﻣﻦ ﺑﺤﺪ أﻗ% ٨ = ﻣﺪة أﻋﻤﺎل اﻟﺘﺠ ات ﺑﺎﳌﺸﺮوع
15
project Mobilization Activities = 10% as a maximum, in case the project period is less than or equal to 12 months, the implementation work must start after the expiration of this period
project Mobilization Activities = 8% maximum in case the project period is greater than 12 months, the implementation work must start after the expiration of this period
( اﻟﺘﻘﺮﺮ/ ﻳﻮم )ﻣﺪة اﻟﺘﺤﺪﻳﺚ٣٠ = ا ﺪ اﻷﻗ ﳌﺪة اﻟ ﺸﺎط اﻟﻮاﺣﺪ ﺑﺄ ﺸﻄﺔ اﻟﺘﻨﻔﻴﺬ
16
Construction Activity Duration shall not Exceed more than 30 days (Reporting/Updating Duration)
(ﺗﻔﺎﺻﻴﻞ أ ﺸﻄﺔ اﻟﺘﻨﻔﻴﺬ )ﻣﺮاﻋﺎة ﺗﻔﺼﻴﻞ اﻷ ﺸﻄﺔ ﻟﻠﻮﺻﻮل ﻟ ﺪ اﳌﻘﺒﻮل ﻟﻠﺘﺤﻜﻢ ﺑﺎﳌﺸﺮوع
17
Activity Level (Breakdown Sufficient for Proper Control)
ﻣﻦ إﺟﻤﺎ ﻗﻴﻤﺔ اﻟﻌﻘﺪ أو ﺣﺴﺐ ﺟﺪاول اﻟﻜﻤﻴﺎت اﳌﻌﺘﻤﺪة%١٠ ﺗﻔﺼﻴﻞ أ ﺸﻄﺔ اﻹﺧﺘﺒﺎرات واﻟﻔﺤﺺ وﺗﺤﻤﻴﻠ ﺎ ﺑﺘ ﻠﻔﺔ ﺑﻤﺎ ﻻﻳﺘﻌﺪى
18
Detailed testing and commissioning activities and its cost shall not exceed 10% of the total contract value or according to the BOQ
ﻣﻨﻄﻘﻴﺔ اﳌﺴﺎرا ﺮج ﻟﻠﻤﺸﺮوع، ﻣﻨﻄﻘﻴﺔ ﺴﻠﺴﻞ اﻷ ﺸﻄﺔ ﺣﺴﺐ ﻣﺮاﺣﻞ اﻟﻌﻤﻞ، ﺗﻮاﻓﻖ ﺴﻠﺴﻞ اﻷﻋﻤﺎل ﻣﻊ ﻃﺮق اﻟﺘﻨﻔﻴﺬ
19
Logic/Sequence of Work Shall Comply with Approved MOS and Critical Path shall be Meaningful links & Sound logic
(Fixed Duration & Units) ﻧﻮع اﳌﺪة اﳌﺴﺘﺨﺪﻣﺔ ﻟ ﻞ اﻻ ﺸﻄﺔ
20
Duration Type ( Fixed Duration & Units ) For All Activities
إﻻ ﺑﻮﺟﻮد ﻣﺎ ﻳﺜ ﺖ ذﻟﻚ ﻌﺎﻗﺪﻳﺎ٠= ﺴﺒﺔ اﻟﻘﻴﻮد ﻋ أ ﺸﻄﺔ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ
21
Activity Constraints =0 unless stated in contract
٠= أ ﺸﻄﺔ ذات ﺎﻳﺎت ﻣﻔﺘﻮﺣﺔ( ﻣﺎ ﻋﺪا ﺸﺎط ﺑﺪاﻳﺔ و ﺎﻳﺔ اﳌﺸﺮوع/ ﺴﺒﺔ اﻷ ﺸﻄﺔ ا ُ ﺮة )ﺑﺪون أ ﺸﻄﺔ ﺳﺎﺑﻘﺔ او ﻻﺣﻘﺔ
22
Activities Without Predecessors or Successors (Open ended activities) except Project start and finish activities =0
ﻣﻦ إﺟﻤﺎ ﻋﺪد أ ﺸﻄﺔ اﳌﺸﺮوع وﻻ ﻳﺘﻢ وﺿﻌ ﺎ اﻻ ﻟﻀﺮورة ﻣﻨﻄﻘﻴﺔ%٥ ( ﻻ ﺗﺰﺪ ﻋﻦLag) ﻋﺪد اﻷ ﺸﻄﺔ اﳌﺸﺘﻤﻠﺔ ﻋ ﻓﻮاﺻﻞ زﻣﻨﻴﺔ
23
Number of activities with LAGs shall not exceed 5% from total number of project activities and can't be added unless there is logical reason
ﻣﻦ إﺟﻤﺎ ﻣﺪة اﳌﺸﺮوع%١٠ اﻟﺴﻤﺎﺣﻴﺔ اﻟ ﻠﻴﺔ ﻻ ﺗﺰﺪ ﻋﻦ
24
Total Float not exceed 10% from Project Duration
٠=ﺳﻤﺎﺣﻴﺔ أ ﺸﻄﺔ اﳌﺴﺎرا ﺮج أو اﳌﺴﺎراﻷﻃﻮل
25
Critical Path or Longest path Float (TF=0)
%٠= ﺎﻳﺔ( ﺑ ن اﻷ ﺸﻄﺔ-ﺴﺒﺔ اﻷ ﺸﻄﺔ ﻌﻼﻗﺔ )ﺑﺪاﻳﺔ
26
(SF) Relationships =0
ﻣﻦ اﺟﻤﺎ ﻋﺪد اﻟﻌﻼﻗﺎت%٩٠ ﺑﺪاﻳﺔ( ﺑ ن اﻷ ﺸﻄﺔ ﻳﺠﺐ أن ﻻ ﺗﻘﻞ ﻋﻦ-ﺴﺒﺔ اﻟﻌﻼﻗﺔ ) ﺎﻳﺔ
27
(FS) relationship between schedule activities not less than 90% of total relationships
٠ = ﺴﺒﺔ اﻷ ﺸﻄﺔ اﳌﻌﻠﻘﺔ ﻣﻦ إﺟﻤﺎ ﻋﺪد اﻟﻌﻼﻗﺎت
28
Dangling Activities = 0
٠ = اﻟﻔﻮاﺻﻞ اﻟﺰﻣﻨﻴﺔ اﻟ ﻠﻴﺔ اﻟﺴﺎﻟﺒﺔ ﻟﻸ ﺸﻄﺔ/ اﻟﺴﻤﺎﺣﻴﺔ اﻟ ﻠﻴﺔ
29
Activities with -ve (Lag/ float) = 0
ﻣﻦ اﺟﻤﺎ ﻋﺪد اﻷ ﺸﻄﺔ%٢٠-١٠ ﺴﺒﺔ ﻋﺪد اﻷ ﺸﻄﺔ ا ﺮﺟﺔ
30
Critical Activities Account Within Range (10-20%) of Number of Total Activities
ﻟ ﻔﺎظ ﻋ ﺴﻠﺴﻞ اﻟﻌﻼﻗﺎت ﺑ ن اﻷ ﺸﻄﺔRetained Logic ﻋﻤﻞ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﺑﻄﺮ ﻘﺔ
31
Scheduling Progressed Activities Use Retained
Auto Complete Actual & Calculate Cost From Units ﺣﺴﺎب اﳌﻮارد اﳌﺴﺘﺨﺪﻣﺔ ﻟ ﻞ اﻻ ﺸﻄﺔ ﺑﻄﺮ ﻘﺔ
32
Resource Calculation with Auto Complete Actual & Calculate Cost From Units
ﻴ ﻠﺔ وﻛﻮد اﳌﻮاد ﻣﺘﻮاﻓﻘﺔ ﻣﻊ ﺟﺪاول اﻟﻜﻤﻴﺎت- ( (2) ﻣﺮﻓﻖ رﻗﻢ، ٣٫٣ ﻛﻮد اﳌﻮارد )ﻋﻤﺎﻟﺔ وﻣﻌﺪات( ﻣﺘﻮاﻓﻖ ﻣﻊ دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ )ﻗﺴﻢ- ﻴ ﻠﺔ اﳌﻮارد إ ﻋﻤﺎﻟﺔ وﻣﻌﺪات وﻣﻮاد
33 Resource Breakdown Structure into labor, equipment and materials - Resource code (labor and equipment) is in line with the Scheduling Management Manual (Refer to Scheduling Management Manual -
Section3.3-Appendix No.02) - The material structure and code is in line with the BoQ
((2) ﻣﺮﻓﻖ رﻗﻢ، ٣٫٣ )ﻗﺴﻢ: ( ﻋ ﺟﻤﻴﻊ اﳌﺴﺘﻮ ﺎت و ﺗﻨﻈﻴﻢ اﻟ ﻴ ﻞ ﻋ اﻟﻨﺤﻮ اﻟﺘﺎRBS) ( ﺴﺒﻖ رﻗﻢ اﳌﻮرد ﻴ ﻞ ﺗﻔﺼﻴﻞ اﳌﻮاردERP) رﻗﻢ ﺗﺨﻄﻴﻂ ﻣﻮارد اﳌﺆﺳﺴﺔ
BOQ اﻟﻘﻮى اﻟﻌﺎﻣﻠﺔ واﳌﻌﺪات و:اﳌﺴﺘﻮى اﻷول
. (وﺣﺪة اﻟﻘﻴﺎس، ﺳﻌﺮاﻟﻮﺣﺪة، اﻟﻜﻤﻴﺔ، ﺗﻘﺴﻴﻢ اﳌﻮاد ﻣﻤﺎﺛﻞ ﺪاول اﻟﻜﻤﻴﺎت اﻟﺘﻌﺎﻗﺪﻳﺔ ﻣﻊ ﻣﺮاﻋﺎة ﺗﺤﻤﻴﻞ )رﻗﻢ اﻟﺒﻨﺪ:اﳌﺴﺘﻮى اﻟﺜﺎ ﻲ
((2) ﻣﺮﻓﻖ رﻗﻢ، ٣٫٣ اﳌﻌﺪات اﳌﺸﺎرإﻟ ﺎ دﻟﻴﻞ إدارة اﻟ اﻣﺞ اﻟﺰﻣﻨﻴﺔ )ﻗﺴﻢ، أﻛﻮاد اﻟﻘﻮى اﻟﻌﺎﻣﻠﺔ:اﳌﺴﺘﻮى اﻟﺜﺎ ﻲ
إﺟﻤﺎ اﻟﺘ ﻠﻔﺔ ﻋ اﻟ ﺸﺎط ﺣﺎﺻﻞ ﺿﺮب اﻟﻜﻤﻴﺔ ﺳﻌﺮاﻟﻮﺣﺪة
34
Enterprise Resource Planning No. (ERP) shall precede Resource Breakdown Structure (RBS) at all levels and shall be structured as follows: (Refer to Scheduling Management Manual - Section3.3-Appendix
No.02)
Level-1: Manpower, Equipment and BOQ
Level-2: BOQ Structure shall be similar to Contractual Bill of Quantities ( Item No., Qty,Unit Price,Unit of Measure).
Level-2: Manpower, Equipment Codes s in line with the Scheduling Management Manual (Refer to Scheduling Management Manual - Section3.3-Appendix No.02)
Total Activity Cost = QTY * Unit Rate
ﺗﻢ ﺗﺤﻤﻴﻞ اﻷ ﺸﻄﺔ ﺑﺎﳌﻮارد اﳌﺒﺎﺷﺮة اﻟﺘﻔﺼﻴﻠﻴﺔ ﻣﻄﺎﺑﻘﺔ ﳌﻌﺪﻻت اﻷداء اﻟﻮاﻗﻌﻴﺔ ﻟﻠﺘﻨﻔﻴﺬ اﳌﻮﻗﻊ
35
Direct Resources loading in details and comply with site productivity
ﻟﻢ ﻳﺘﻢ ﺗﺤﻤﻴﻞ ﻣﻌﻈﻢ ﺗ ﻠﻔﺔ اﳌﺸﺮوع ﻣﻨﺤ اﻟﺘ ﻠﻔﺔ ﺎﻳﺔ ﻣﺪة اﳌﺸﺮوع
36
S-curve is not Back loaded
ٌ ً
اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ اﳌﻌﺪل ﺗﻢ إﻋﺪادﻩ ﺑﻨﺎءا ﻋ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ ﺧﻂ اﻷﺳﺎس اﳌﻌﺘﻤﺪ وا َﺪث ﺣ ﺗﺎرﺦ ﺑﺪاﻳﺔ اﻟﺘﻤﺪﻳﺪ و ﺴﺒﺔ اﻹﻧﺠﺎزاﻟﻔﻌﻠﻴﺔ ﻣﺘﻮاﻓﻘﺔ ﻣﻊ ﺴﺒﺔ اﻹﻧﺠﺎزاﻟﻔﻌﻠﻴﺔ ﺑﻨﻈﺎم إﻧﺠﺎز
37
Revised schedule was prepared based on the approved and updated baseline schedule until the start date of the extension, and the actual percentage is consistent with the actual percentage in the Enjaz system
(Out of Sequence Activities) ﺗﻢ ﺗﻼ اﻟﻌﻼﻗﺎت اﻟﻐ ﻣﻨﻄﻘﻴﺔ ﺑﺎﻟ ﻧﺎﻣﺞ اﻟﺰﻣ اﳌﻌﺪل
38
Avoidance of Out of Sequence Activities
ﺗﻢ ﺗﻼ إدراج ﺗﻮار ﺦ ﻓﻌﻠﻴﺔ ﻟﻸ ﺸﻄﺔ ﺗﺘﻌﺪى ﺗﺎر ﺦ ﺗﺤﺪﻳﺚ اﻟ ﻧﺎﻣﺞ اﻟﺰﻣ
39
Avoidance of Activities Actual Dates after Data date
Comments: :ﻣﻼﺣﻈﺎت
Comments: :اﳌﻼﺣﻈﺎت
Month
Month
500,000
0
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
4,000,000
4,500,000
BL Monthly
Act. Cum. %
Period No.
Period No.
(SAR)
(SAR)
Planned (SR)
Planned (SR)
Planned (SR)
Planned (SR)
REV. Monthly
BL Planned %
BL Cumulative
Act. Monthly %
REV. Planned %
Act. Cumulative
REV. Cumulative
Contract Price
1
1
0 0 500,000 500,000
Original Price
٢٠‐ﻳﻨﺎﻳﺮ ٢٠‐ﻳﻨﺎﻳﺮ
Total Invoiced
0.0%
0.0%
1.1%
1.1%
[Insert Consultant and Contractor logos]
2
2
٢٠‐ﻓ اﻳﺮ 500,000 500,000 1,500,000 1,000,000 ٢٠‐ﻓ اﻳﺮ
Act. Monthly (SR)
1.1%
1.1%
3.4%
2.3%
Act. Cumulative (SR)
X%
Total Paid
3
3
٢٠‐ﻣﺎرس 1,500,000 1,000,000 2,500,000 1,000,000 ٢٠‐ﻣﺎرس
3.4%
2.3%
5.7%
2.3%
BL Cumulative Planned (SR)
REV. Monthly Planned (SR) (Rev.n)
4
4
٢٠‐أﺑ ﻞ 2,500,000 1,000,000 3,500,000 1,000,000 ٢٠‐أﺑ ﻞ
5.7%
2.3%
8.0%
2.3%
REV. Cumulative Planned (SR) (Rev.n)
0
5
5
٢٠‐ﻣﺎﻳﻮ 3,500,000 1,000,000 4,500,000 1,000,000 ٢٠‐ﻣﺎﻳﻮ
8.0%
2.3%
2.3%
10.2%
Pending
#VALUE!
Advance Payment
6
6
٢٠‐ﻳﻮﻧﻴﻮ 4,500,000 1,000,000 6,500,000 2,000,000 ٢٠‐ﻳﻮﻧﻴﻮ
2.3%
4.5%
10.2%
14.8%
7
7
٢٠‐ﻳﻮﻟﻴﻮ 6,500,000 2,000,000 8,500,000 2,000,000 ٢٠‐ﻳﻮﻟﻴﻮ
4.5%
4.5%
14.8%
19.3%
8
8
٢٠‐أﻏﺴﻄﺲ 8,500,000 2,000,000 10,500,000 2,000,000 ٢٠‐أﻏﺴﻄﺲ
4.5%
4.5%
19.3%
23.9%
9
9
٢٠‐ ﺳ ﺘﻤ 10,500,000 2,000,000 12,500,000 2,000,000 ٢٠‐ ﺳ ﺘﻤ
4.5%
4.5%
23.9%
28.4%
Change Value 4
Change Value 1
10
10
٢٠‐أ ﺘ ﺮ ٢٠‐أ ﺘ ﺮ
4.5%
4.5%
28.4%
33.0%
14,500,000 2,000,000 16,500,000 2,000,000
11
11
4.5%
4.5%
33.0%
37.5%
16,500,000 2,000,000 18,500,000 2,000,000
12
12
4.5%
4.5%
37.5%
42.0%
18,500,000 2,000,000 20,500,000 2,000,000
13
13
٢١‐ﻳﻨﺎﻳﺮ ٢١‐ﻳﻨﺎﻳﺮ
4.5%
4.5%
42.0%
46.6%
20,500,000 2,000,000 22,500,000 2,000,000
14
14
4.5%
4.5%
46.6%
51.1%
22,500,000 2,000,000 25,500,000 3,000,000
15
15
٢١‐ﻣﺎرس ٢١‐ﻣﺎرس
Contract Modified Price 4
Contract Modified Price 1
4.5%
6.8%
51.1%
58.0%
24,500,000 2,000,000 29,500,000 4,000,000
16
16
٢١‐أﺑ ﻞ ٢١‐أﺑ ﻞ
4.5%
9.1%
55.7%
67.0%
26,500,000 2,000,000 33,500,000 4,000,000
17
17
٢١‐ﻣﺎﻳﻮ ٢١‐ﻣﺎﻳﻮ
4.5%
9.1%
60.2%
76.1%
28,500,000 2,000,000 37,500,000 4,000,000
18
18
٢١‐ﻳﻮﻧﻴﻮ ٢١‐ﻳﻮﻧﻴﻮ
4.5%
9.1%
64.8%
85.2%
[Insert Project Name]
Cash Flow S‐Curve
٢١‐ﻳﻮﻟﻴﻮ ٢١‐ﻳﻮﻟﻴﻮ
4.5%
4.5%
69.3%
89.8%
Change Value 5
Change Value 2
٢١‐أﻏﺴﻄﺲ ٢١‐أﻏﺴﻄﺲ
4.5%
2.3%
73.9%
92.0%
33,500,000 1,000,000 33,500,000 41,500,000 1,000,000
21
21
2.3%
2.3%
76.1%
76.1%
94.3%
34,250,000 750,000 42,500,000 1,000,000
22
22
٢١‐أ ﺘ ﺮ ٢١‐أ ﺘ ﺮ
1.7%
2.3%
77.8%
96.6%
79.5%
98.9%
81.2%
100.0%
36,500,000 750,000
25
25
٢٢‐ﻳﻨﺎﻳﺮ ٢٢‐ﻳﻨﺎﻳﺮ
Contract Modified Price 5
Contract Modified Price 2
1.7%
83.0%
37,250,000 750,000
26
26
84.7%
38,000,000 750,000
27
27
٢٢‐ﻣﺎرس ٢٢‐ﻣﺎرس
1.7%
86.4%
38,750,000 750,000
28
28
٢٢‐أﺑ ﻞ ٢٢‐أﺑ ﻞ
1.7%
88.1%
39,500,000 750,000
29
29
٢٢‐ﻣﺎﻳﻮ ٢٢‐ﻣﺎﻳﻮ
1.7%
89.8%
Change Value 6
Change Value 3
40,250,000 750,000
30
30
٢٢‐ﻳﻮﻧﻴﻮ ٢٢‐ﻳﻮﻧﻴﻮ
1.7%
91.5%
41,000,000 750,000
31
31
٢٢‐ﻳﻮﻟﻴﻮ ٢٢‐ﻳﻮﻟﻴﻮ
1.7%
93.2%
41,750,000 750,000
32
32
٢٢‐أﻏﺴﻄﺲ ٢٢‐أﻏﺴﻄﺲ
1.7%
94.9%
42,500,000 750,000
33
33
96.6%
43,150,000 650,000
34
34
٢٢‐أ ﺘ ﺮ ٢٢‐أ ﺘ ﺮ
1.5%
98.1%
43,700,000 550,000
35
35
1.2%
99.3%
0
44,020,000 320,000
36
36
100.0%
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
35,000,000
40,000,000
45,000,000
50,000,000