INDIA
EPC CONTRACTOR: -
M/S. G.R. INFRAPROJECTS LIMITED
Guidelines for a Quality Assurance Plan for Construction Works
TABLE OF CONTENT
TOP SHEET...................................ORGNIZATION CHART
1. INTRODUCTION…………………………………………………………………………5
2. IMPLEMENTATION METHODS………………………………………………………5
2.1 Process Management............................................................................................5
2.2 Process Qualification.............................................................................................6
2.3 QA/QC Process Qualification.............................................................................7
3. INSPECTION AND TESTING………………………………………………………...10
3.1 AIM.......................................................................................................................................10
3.2 SCOPE..................................................................................................................................10
3.3 RESPONSIBILITY..............................................................................................................10
4. CONTROL OF INSPECTION, MEASURING AND TEST EQUIPMENT………10
4.1 AIM.......................................................................................................................................10
4.2 SCOPE..................................................................................................................................11
4.3 RESPONSIBILITY..............................................................................................................11
4.4 IMPLEMENTATION METHODS...................................................................................11
4.4.1 Equipment Selection...........................................................................................11
4.4.2 Identification........................................................................................................11
4.4.3 Calibration............................................................................................................12
4.4.4 Documentation....................................................................................................13
4.4.5 Handling and Preservation................................................................................13
4.4.6 Measures in case Equipment is out of Calibration..........................................13
4.4.7 Master Templates and Comparative Reference...............................................13
4.4.8 Management of Standard Devices and Reference Equipment......................13
4.4.9 List of Plant & Equipment...........................................................................14
5. INSPECTION AND TEST STATUS………………………………………………….15
5.1 AIM.......................................................................................................................................15
5.2 SCOPE..................................................................................................................................15
5.3 RESPONSIBILITY..............................................................................................................15
5.4 IMPLEMENTATION METHODS...................................................................................15
5.4.1 Identification of the Inspection and Test Status...............................................15
5.4.2 Approval of Quarries and Borrow Areas................................................................16
5.4.3 Selection of Borrow Area.....................................................................................17
5.4.4 Transport of Materials.........................................................................................17
5.4.5 Development/ Redevelopment of Borrow Pits and Quarries............................18
5.4.6 Approval of Materials............................................................................................18
5.4.7 Approval of Natural Materials................................................................................19
Page 2
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
8. TRAINING OF PERSONNEL.........................................................................................27
8.1 AIM.......................................................................................................................................27
Page 3
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
8.2 SCOPE..................................................................................................................................28
8.3 RESPONSIBILITY..............................................................................................................28
8.4 IMPLEMENTATION METHODS...................................................................................28
8.4.1 Identification of Training Needs.......................................................................28
8.4.2 Planning of Training...........................................................................................29
8.4.3 Personnel assigned to Special Activities...........................................................29
8.4.4 Documentation....................................................................................................30
9. SERVICING………………………………………………………………………………30
9.1 AIM.......................................................................................................................................30
9.2 SCOPE..................................................................................................................................30
9.3 RESPONSIBILITY..............................................................................................................30
9.4 IMPLEMENTATION METHODS...................................................................................30
9.4.1 General Information............................................................................................30
9.4.2 Technical and Logistical Support......................................................................31
9.4.3 Technical Servicing of the Works......................................................................31
9.4.4 Resolving Complaints.........................................................................................31
10. STATISTICAL TECHNIQUES………………………………………………………...32
10.1 AIM.......................................................................................................................................32
10.2 SCOPE..................................................................................................................................32
10.3 RESPONSIBILITY..............................................................................................................32
10.4 IMPLEMENTATION METHODS...................................................................................32
11.0 INSPECTION & TEST PLAN....................................................................................36-51
12.0 NCR FORMATE............................................................................................................52
13.0 CHECK LIST..................................................................................................................53-62
14.0 QUALITY CONTROL TEST FORMATE.................................................................63-85
LIST OF FIGURES
Figure 2-1-1: General Procedure for the Construction of a Structure and the Control of its
Quality..........................................................................................................................................09
Page 4
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
1. INTRODUCTION
M/s Gr. Infraprojects Ltd Construction Company of India has undertaken the job of
ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN
SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER NHDP
PHASE -III IN THE STATE OF HIMACHAL PRADESH”. This plan provides the
description of Quality Assurance to be implemented to ensure that all the
excavation, concreting works and the overall construction works of Tunnels are in
accordance to the Contract Requirements, Specifications, Drawings and Design.
A Quality Manager/Engineer
Tunnel Engineers
Safety Manager
Store Keepers
QA Supervisors
QA Quality Assurance
QC Quality Control
NC Non-Conformity
Inspections and test requirements including the means and methods to be utilised
2. IMPLEMENTATION METHODS
Personnel are provided with the necessary instructions and documented information
to be able to define execution/utilization methods and work criteria.
The Personnel /processes utilised for the construction are qualified whenever
required.
The suitability of the equipment used in the process is guaranteed by the
maintenance work performed on it, which is documented by the Mechanical
Engineer.
In order to carry out the processes correctly, refer to the following documents:
Work schedule – this identifies the various construction phases, their order
and duration;
Drawings and technical specifications – these contain the technical
references required for the work activities;
Procedures and operational instructions (i.e. Method Statements) – these lay
down the methods according to which the work is to be performed and
are drawn up only when required as a back-up to the usual routine
procedures and the training already given to personnel;
Safety Manual – this contains the rules and regulations governing
behaviour with a view to foreseeing potential risk situations and
safeguarding the health of the workers;
Quality Plans – these establish the inspections and tests required and how
they are to be conducted in order to verify the conformity of the product
constructed.
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
Page 7
The way of how such quality control forms are handled, communicated,
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
Page 8
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
Start
Planning of
Construction
Technical Dept.
Page 9PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
Guidelines for a Quality Assurance Plan for Construction Works
Preparation/C
Preparation of
ollection of
Method Statement
New/Existing
QC
Technical Dept. For
ms
Technical and
QA/QC Dept.
Preparatory Works
N
o
Production Dept.
Pre-
Construct
ion
Chec
k
o.k.?
Yes
Production
Production Dept.
Post-
Constructi
on
Chec
k
o.k.?
No
Corrective Action Yes
No
Production Dept.
F
i
n
a
l
Chec
k
o.k.?
Y
e
s
E
n
d
Page 10
PROJECT: ROAD TUNNELING WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22 (NOW-5) FROM KM 67.000 TO KM 106.000 UNDER
NHDP PHASE -III IN THE STATE OF HIMACHAL PRADESH”,
3. INSPECTION AND TESTING
3.1 AIM
This procedure defines how inspection and testing for the execution and
permanent civil works of the TUNNEL PROJECT shall be carried out and which
additional instructions, method of statements are to be used for the single
activities.
3.2 SCOPE
This procedure covers the inspection and testing of all execution activities and
permanent civil works and the respective permanent materials used for these
works. It also applies to the general activities such as execution, construction
works and surveying activities.
3.3 RESPONSIBILITY
The corresponding person in charge for QC is responsible for: Carrying out the
quality control getting training to be able to carry out the quality control
The QA Supervisor has to:
Carrying out the quality assurance
Making sure that the quality controls are carried out along the
prescribed standards or procedures and that are carried out in an
acceptable manner.
4.1 AIM
The aim of this procedure is to define the methods used by Gr.Infraprojects Ltd
for managing and calibrating inspection, measuring and test equipment used for
the execution and construction of the permanent civil works and associated
structures of Tunnels, with the aim of ensuring that its uncertainty is known and
consistent with required measurement capability.
4.2 SCOPE
This procedure covers all inspection, measuring and test equipment (including
testing software and comparative references) used by Gr.Infraprojects Ltd. to
control conformity of the permanent materials used for the civil works to
the specified requirements of the technical reference documentation.
4.3 RESPONSIBILITY
4.4.2 Identification
All major inspection, measuring and test equipment present on the work site is
recorded on the appropriate Quality Plan for Calibration of Inspection, Measuring
and Test Equipment, prepared and kept up to date by the Technical Site
Department of GR. Infraprojects Ltd.
All inspection, measuring and test devices are identified by means of a company
serial/ asset number attached to them before use.
For each device a “Calibration Form“, prepared by GR. Infraprojects Ltd or from
the agency that device is calibrated is compiled. This contains all the necessary
information for calibration.
The “Calibration Form” shows unique identification number, thus permitting the
corresponding device to be identified.
Operators of inspection, measuring and test equipment ascertain that the devices
are properly identified. If identification is lacking, they have to inform the
Technical Site Department, who verifies the cause of this and sees to it that
identification is made.
4.4.3 Calibration
All major inspection, measuring and test equipment undergoes periodic
calibration against certified standard equipment.
The initial calibration frequency is decided by the Technical Site Department
together with the Quality Engineer and the Operator taking into account the use
of the equipment and the manufacturer’s instructions. The calibration frequency is
recorded on the “Calibration Form” of each device.
The Technical Site Department is responsible for calibrating all the equipment.
The “Calibration Form” indicates the reference documentation for performing the
calibration. Calibration can be carried out externally or on site, each time referring
to the recognised international standards. For on-site calibration in which
recognised methods or manufacturers’ User’s Manuals are not available,
procedures must follow specific instructions issued by the Technical Site
Department.
Calibration outcome and assessment is recorded on the “Calibration Form” of the
respective device.
If the outcome of the calibration is positive, a “Calibration Tag” is attached to the
device. This indicates the calibration status and shows the calibration expiration
date. Inspections, measuring and tests shall be performed exclusively with
calibrated equipment within the validity period.
If inspection, measuring and test equipment gives results which do not seem
reliable, this should be reported to the Quality Engineer, who will instruct that the
device in question undergoes unscheduled calibration. In the case of a negative
outcome, the appropriate measures are taken.
Unscheduled calibration is also recorded on the “Calibration Form”, though in
this case the “Calibration Tag” is not updated.
Calibration operations are carried out under environmental conditions which
ensure the required accuracy.
In the case that a testing device is not used for a period longer than that between
two consecutive calibrations, the phrase “not used” and the relative period must
be written on the “Calibration Form”.
In the case that moving a device from one place to another may have
compromised its calibration, the device must undergo new calibration, which is
recorded on the “Calibration Form” as a note.
4.4.4 Documentation
Calibration data as well as all information which identifies equipment is recorded
on the “Calibration Forms”. The “Calibration Forms” together with the relative.
“Calibration Reports” issued internally to the company or by external agencies are
filed by the Quality Engineer.
Filing of documentation is carried out in accordance with “Control of Quality
Records”.
The no end of type of above equipment may vary as per site requirement during
Construction of Tunnel.
5.1 AIM
The aim of this procedure is to distinguish the inspection and test status of
permanent material, works or parts of works related to Tunnel construction
works, with a view to indicating their "Conformity" or "Non-Conformity" to
contract specifications, as proved by the inspection and tests performed.
5.2 SCOPE
This procedure covers the entire "scope of work" for the ROAD TUNNELING
WORK FOR THE “FOUR LANING OF PARWANOO-SOLAN SECTION OF NH-22
(NOW-5) FROM KM 67.000 TO KM 106.000 UNDER NHDP PHASE -III IN THE STATE
OF HIMACHAL PRADESH”.
5.3 RESPONSIBILITY
The Production/Tunnel Manager is responsible for maintaining the identification
marking on site of the inspection and test status intact.
The Contractor is to obtain approval from the AE for each Quarry and Borrow Area to be
used in the Project prior to commencement of quarrying and/ or borrow area excavation
activities. The primary aspects to be considered by the AE in granting approval are:
The steps to be followed for approval of each Quarry/ Borrow Area are:
1. The Contractor is to complete the “Materials Sources Data” giving details regarding
size, location, orientation and access for the proposed quarry/ borrow area (rough
map to be drawn).
2. The results of laboratory tests conducted on the materials jointly sampled with the QA
Engineer (or his designated representative) are to be summarized on the approval
form, and complete copies of all tests are to be attached to the form.
3. The Contractor shall attach to the completed “Materials Sources Data” form, his
proposed “Environmental Management Plan” for development, use and closing down
of the proposed quarry/ borrow area. Photographs of the sources site, including
access roads, etc., should be included with the proposal so that the base line
conditions of the quarry/ borrow area are clearly established.
4. Based on the Contractor’s proposal, and on the site inspection team’s comments,
the AE will (within 5 days after receipt of the proposal) reply to the Contractor in
accordance with one of the following:
With regard to approval of Quarries and Borrow Areas, the PM shall pay particular attention
to requirements of the Environmental Management Plan particularly with regards to:
It is to be noted that all field activities for the above are not to commence until appropriate
Request for Inspection Forms are completed, submitted and approved.
All materials proposed by the Contractor to be used in the Project Works are to be first
approved. In general, there are four types of materials to be approved.
(1) Natural Materials – materials with little or no processing except for perhaps screening
for oversize and removal of unsuitable particles, etc. An example of this is soil
embankment materials.
(2) Processed Materials – materials that require significant processing, including removal
of unsuitable particles, crushing, screening and perhaps, blending of sizes. These
materials are homogeneous, but with specified gradations.
(3) Manufactured Materials – especially homogeneous construction materials, like
Portland cement and admixture that are used for blending with natural materials to
obtain a concrete mix.
(4) Designed Materials – materials that involve the mixture to specific proportions of two
or more different, natural, processed or manufactured materials to obtain a modified
material giving a set of desired specific properties.
Approval of each of the above material types is required, however the requirements for
obtaining approval of materials for each type differs slightly:
Natural materials are mined (i.e., excavated) and hence the first step, following assurance
that the material is acceptable for its intended purpose, is to obtain approval for the Quarry.
Approval of the material for construction is then obtained by submittal of test results for all
tests required by the Specifications (i.e., to prove that the material meets all minimum
properties required).
Approval of processed materials follows that noted above for “natural” materials, except
that usually the specifications are tighter (e.g. the material may also have to meet stringent
gradation limits), and a greater variety of tests (and production/ storage) conditions are
required to be met.
Approval of “designed” materials for the present Project concerns those mix designs for
Portland Cement Concrete (for culverts, bridges etc). Due to the complexity of these
“mixed” materials, and the plants for producing the range of materials sizes, final approval
is deferred until completion of the following steps:
Following approval of the job mix formula, the PM and all field support staff shall continue
to monitor both the test results of the visual characteristics of the approved mix as placed to
identify at an early stage any significant change in the mix design that may adversely
influence the adherence of the approved mix design to the Specifications. A new mix
design (or adjustment of the plant proportioning of materials to re-establish the approved
job mix formula) will be required when it is observed that significant changes in the mix
design properties are causing the mix to no longer meet all Specification requirements. In
addition, a new mix design will be required when either the approval of a material source or
approval of one of the materials is revoked (i.e., withdrawn). Mix /Material approved shall
be revoked by the PM after due consultation with the Consultant’s Q.A. Engineer.
The Contractor’s Q.A. Engineer shall notify in writing to the PM and the Consultant’s / I C
each time a new source, material and/ or mix design is either approved or the approval is
revoked. This information is to be included in the Monthly Quality Control Report to be
submitted with the Monthly Progress Report.
Records are to be kept by the Consultant’s Q.A. Engineer/ I C giving current approvals of
all Borrow Areas, Quarries (all types) and Mix Designs for all BOQ items. The current
summaries are to be included as part of the Monthly Progress Report.
All construction materials to be used in the permanent works are to be sampled jointly by
the staff of Consultant’s Q.A. Engineer and the Contractor prior to commencement of
the Works. This includes sampling for materials to be tested for proposing approval of the
material source as well as sampling of materials for approval of the individual construction
materials. In both cases, and for each instance, the Contractor must give notification of a
request for such sampling to the AE in advance (minimum 48 hours) by way of the
Request for Inspection Form (RFI). All assistance (e.g. sampling instruments and
equipment, sample bags, and labour etc) that is required for carrying out the sampling
activities are to be provided by the Contractor.
Samples collected are reduced and prepared as per Indian Standards (IS) methods, with
an additional sufficient quantity retained in appropriately sealed bags(s) or container(s) and
separately kept in the sample storage room of the laboratory for additional testing and/ or
future reference as required. Concrete samples in particular are to be carefully cured and
kept in the curing tank of the laboratory. Access to stored samples is under the strict direct
control of the Contractor’s Q.A. Engineer. Details of all samples stored are to be kept in a
Register to be administered by the authorized engineer of the Consultant’s Q.A. Engineer.
6.1 AIM
The aim of this procedure is to determine the management methods of Corrective
and Preventive Actions implemented with a view to eliminating the causes
of already existing and potential Non-Conformities.
6.2 SCOPE
This procedure covers all the Corrective and Preventive Actions implemented
within the TUNNEL PROJECT.
6.3 RESPONSIBILITY
The Technical Site Department is responsible for:
Determining the Corrective and Preventive Actions to be implemented
following internal audits
Implementing the Corrective and Preventive Actions.
6.4.4 Actions following the Periodical Quality Analysis made by the Quality Engineer
Client Complaints
If the Corrective and Preventive Actions have had a negative outcome, they are
replaced. These new Corrective and Preventive Actions are reported by the
Quality Engineer to the Project Manager and Executive Manager.
6.6 FILING
The Quality Engineer files the “Corrective and Preventive Action” forms.
7. INTERNAL AUDITS
7.1 AIM
The aim of this procedure is to define the methods and responsibilities for the
carrying out of the internal audits for this quality assurance manual.
7.2 SCOPE
This procedure covers the reviewing of the quality assurance manual utilised by
SAMMON INFRACORP. with a view to keep it updated and to improve the
procedures.
M/S -SAMMON INFRACORP Will be our Part of Tunnel Construction Work.
7.3 RESPONSIBILITY
The Management Board is responsible for:
Ensuring that the internal audit is carried out periodically
Ensure that improvements to the quality assurance system are
implemented
Deciding on additional internal audits if they feel that such are required
The Executive Officer is responsible for:
Carrying out the internal audit within the involved staff
Implementing the proposed improvements found during the internal audit
The Road Tunnel is part of “Four Laning of Parwanoo-Solan Section of NH-22 (Now-
5) from Km. 67.000 to Km. 106.000 on EPC Mode under NHDP Phase-III in the State
of Himachal Pradesh”. As reported in section B of tender the tunnel portal are at
1+125 and 1+950 respectively on a green field road alignment.
Table 1: Portal Location details as per contract
The total length of tunnel envisaged under this project 825 m as per contract.
Size of Main tunnel – excavation size with Cross section approximate maximum area is
126 Sqm with horse shape.
Availability of tunnel faces is two, one from Parwanoo end, Portal P1 and other from Solan
end, Portal P2
After mobilization of resources, we will take up the excavation work in Portal approaches
& construction of Portal protection works. Portal construction work followed by
commencement of tunnel Canopy & after main tunnel excavation from main tunnel portal.
Tunnel will be excavated using drill and blast method in heading, benching & Invert
sections as per prevailing rock conditions and a per design section accordingly rock class
by using primary lining including shotcrete, wire mesh & rock bolts as per given in design
drawing provided by our tunnel designer M/s Indus Consultrans Pvt Ltd.
Concrete lining of tunnel will be taken up after completing the excavation and primary
lining with rock support. Construction activity will be sequenced in proper logical manner
so that all above structures are completed in time.
8. TRAINING OF PERSONNEL
8.1 AIM
The aim of this procedure is to define methods for identifying the training needs
of all the Personal and for the planning, implementation and recording of the
same.
8.2 SCOPE
This procedure covers all the personnel of GR. Infraprojects Ltd. involved in
activities affecting Quality.
8.3 RESPONSIBILITY
GR. Infraprojects Ltd is responsible for:
Identifying and planning training for its one Personnel.
The selected Quality Engineer is responsible for:
Approving the qualification of the personnel responsible for specific
processing and checking procedures and for filing the related
documentation.
The selected Project Manager is responsible for:
Coordinating the training needs of the various personnel
Personnel training needs are evaluated by the Head of each department involved
on the basis of the following criteria:
Activities performed in the Department
Areas of competence and qualifications necessary for the said activities to be
performed
Knowledge of the Quality System in relation to management and
operational aspects
Project organization
Laws, regulations and standards
Site and management processes
Evaluation of the qualifications and knowledge of the personnel in
comparison with the required skills and mastery required for performing
the activities
8.4.4 Documentation
Participation internal training courses is recorded on a “Training Record” form,
while participation in external courses is recorded by means of the “Certificate of
Attendance” issued at the end of the training course. Such documents are duly
filed by the Head of Department.
Personnel qualification documentation is filed by the Quality Engineer.
9. SERVICING
9.1 AIM
The procedure defines the methods and assigns the responsibilities for providing
servicing assistance to GR. according to the contract conditions and ensuring that
this assistance does, effectively, meet the requirements.
9.2 SCOPE
This procedure covers the servicing assistance for the construction of the
TUNNEL PROJECT.
9.3 RESPONSIBILITY
The Project Manger is responsible for:
Providing technical and logistical assistance on site
Resolving complaints
10.1 AIM
The aim of the present procedure is to define methods and responsibilities relative
to the use of Statistical Techniques.
10.2 SCOPE
This procedure covers all statistical techniques utilised for the construction of the
TUNNEL PROJECT with a view to keeping product processes and characteristics
under control.
10.3 RESPONSIBILITY
The Head of Department is responsible for:
Mean
Standard deviation
Control cards
Diagram and bar graphs
Sampling plans
GR INFRAPROJECTS LTD
QUALITY CONTROL LAB FREQUENCY