Professional Documents
Culture Documents
Co-Presenters:
Dr Titus Mathe
Mr Anton Hart
1. Introduction
15/10/2014 2
1. Introduction
15/10/2014 3
1. Introduction
15/10/2014 4
2. Compliance to SO2 Emissions Legislation
15/10/2014 5
2. Compliance to SO2 Emissions Legislation
• WFGD (Limestone, Forced Oxidation- LSFO) Retrofit: 6 Absorbers and one common plant
for limestone preparation, gypsum dewatering and wastewater treatment
15/10/2014 7
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
15/10/2014 8
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
3.2. WFGD “Ready” Concept
Increased
margin on ID
Fans Medupi PS May 2013
Lining of
Raw Water chimney
Storage and flues with
Pumping corrosion
System resistant
Spatial
provisions
Concept Rotation of
chimneys to
for Absorber 180° to
Island and ensure
Common clean gas
Plants duct tie-in
Lining of ash
dump
85-96% CaCO3
Limestone
range
Sulphur in coal Attemperation
range: 1.2-1.8% Air upstream of
a.d the FFP
Figure 7: Location of limestone deposits in relation to
Medupi Power Station
Varying Raw
Required SO2
Process Water Source:
clean gas
Design Mokolo Dam
concentration:
Basis and Crocodile
400mg/Nm3
West Scheme
15/10/2014 10
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
3.4. Key Design Features & Considerations
Table 4: Medupi FGD Absorber Characteristics.
a. Absorber Design
ABSORBER CHARCTERISTICS (per unit)
Materials of Construction Carbon Steel with Rubber Lining
Flue Gas Volume 2800000 Nm3/hr,
SO2 Removal Efficiency (%) up to 95%
Absorber Height 35.5 m
Absorber Diameter 17.5 m
Reaction Tank Diameter 21.5 m
No. of Spray Banks 4 and 1 spare
Recirculation Pumps (m3/hr) 9600 (4 and 1 spare)
Mist Eliminator 2 stage with flushing system
No. of Reaction Tank Agitators 4 with oxidation air lances
Absorber Gas Velocity 4 m/s
15/10/2014 11
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
b. Low quality limestone
a. Effects on plant design
• Increases in equipment sizing, auxiliary power requirements and investment cost
Table 5: Design changes as a result of low quality limestone evaluated.
15/10/2014 12
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
c. Water Consumption Optimisation
Absorber Make-up
Evaporation
Mist Eliminator Flushing
WFGD Wastewater
Limestone Slurry Prep PLANT
Gypsum
Gypsum Washing
15/10/2014 13
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
c. Water Consumption Optimisation
Figure 9: Medupi FGD Absorber Inlet Duct with Figure 10: Medupi FGD Unit 4-6 Process Area
Gas Cooler Arrangement with Gas Cooler
15/10/2014 14
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
3.5. Challenges associated with Construction and Commissioning Sequence
a. Construction
Unit 1 Unit 3
Unit 2 Unit 4 Unit 5 Unit 6
Unit 4
Figure 13: Render of Medupi WFGD 3D Model Unit 4-6 (Absorber Cluster 2)
15/10/2014 17
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
15/10/2014 18
3. Eskom Large Scale FGD Retrofit- Medupi WFGD
Retrofit Project
b. Operational Challenges
Limestone Limestone
Slurry Slurry
Feed Tank Feed Tank
1 2
15/10/2014 20
4. Conclusions and Current Work
• Current Work:
• Kusile WFGD Plant under construction
• Fleet Technology Evaluation taking into account:
• Evaluation of a suite of FGD Technologies (Wet & Semi-Dry)
• Site Layout
• Capacity of and impacts on existing plant facilities (draught systems, electrical, control & instrumentation,
raw water, compressed air, materials handling systems and chimneys) to support FGD retrofit
• Waste management
• Lessons learned from Kusile and Medupi WFGD.
15/10/2014 21
Acknowledgements
• Medupi WFGD Retrofit Project Multi-disciplinary Team (Eskom, Steinmuller Engineering, Black & Veatch)
• Environmental
15/10/2014 22
Thank you