CHECK LISTS for use by Building Construction Supervisors
and
ACCEPTANCE CERTIFICATES
INTRODUCTION
This check-list for site supervisors is prepared for use by WVE/ADP site Engineers in order to ensure
a uniform system of supervision of building construction projects and as a result ensure a safe and
durable construction. It is to be of use mainly when construction works are carried out by contractors
and can in some ways be of use for construction carried out by direct labor.
The steps to be followed in checking building construction works are expressed in general terms as
shown in Section 1. Details of construction are specified in the drawings, technical specifications and
in the general and special provisions of the contract. The duty of the site supervisor is to ensure that
the construction works are executed in accordance with the contract requirements. Therefore, in the
application of this check-list, the details specified in the contract document always precede before the
application and use of it. There are also tables and forms in this check-list as presented in Section 3
that help to record the incidences affecting the work and be used as references.
When each permanent part is completed, the supervisor should inspect and approve or reject that
particular work. If approved, the supervisor is expected to issue approval certificate applicable for the
work from the list of certificates presented in Section 2.
Requirements, which are reasonably complied shall be mastered with a “” mark in the
checkbox.
Requirements which are not reasonably complied shall be marked with an “x” mark in the
checkbox.
Where requirements are partly not applicable in the construction, the checkboxes shall be left
open or unmarked.
Comments can be provided only for those requirements not complied and marked with an “x”
mark in the check-box.
3
SECTION 1
CHECK-LISTS
3
Check-Lists
4
Original signed: yes no
5
Original signed: yes no
6
A: not completed B: visual control not possible C: checked
7
A: not completed B: visual control not possible C: checked
8
No Bench/Testing parameter A B C No Bench/Testing parameter A B C
9.9 Stressing is from both ends unless 9.23 The Rout consists only of ordinary
required or agreed by the engineer. Portland cement & water unless
9.10 The tendons are anchored only if the otherwise specified.
pre stressing is applied to the 9.24 Pre stressed members are lifted or
satisfaction of the engineer. supported only at the points specified
9.11 The jack pressure is released in such & handled & placed without impact.
a way as to avoid shock to the 9.25 Beams are prevented from moving
anchorage or tendons. laterally during the placing of the in
9.12 If the pull-in of the tendons at situ concrete.
completion of anchoring is greater 9.26 The engineer informed in advance of
than that agreed by the engineer, the the date of commencement of
load shall be released slowly and manufacture & the dates when
tensioning carried out afresh. tensioning of tendons, casting of
9.13 Sufficient test cubes are taken and members and transfer of stress will
specified transfer strength is attained. be undertaken for the first time for
9.14 The tendons are not cropped or cut each type of beam.
prior to 3 days after grouting. 9.27 All pre stressed concrete
9.15 Full records of all tensioning construction comply the standard
operations including the measured technical specification.
extensions, pressure gauge or load all 10 FORM WORK
readings and the amount of pull-in at 10.1 Form work is so constructed that it
each anchorage, are kept. can be stripped from the hardened
9.16 All ducts are thoroughly cleaned by concrete easily without hammering
compressed air or method specified or without such shock or vibration in
prior to grouting. order to protect the concrete or
9.17 All anchorages are sealed before reduce labour cost.
grouting. The ducts are completely 10.2 The bracing of the form work. The
filled with grout. form work must be strong enough to
9.18 The filled ducts are protected to the carry the load until the concrete is
satisfaction of the engineer that they strong enough to carry itself and
are not subjected to shock or hardened sufficiently.
vibration for one day. 10.3 The inside surface of form works shall,
9.19 A full record of grouting including except for permanent form works, or
the date each duct was grouted is unless otherwise agreed by the engineer,
kept. be coated with a release agent.
9.20 The grout mixer produces a grout of 10.4 Release agents do not come into
colloidal and uniform consistency. contact with the reinforcement and
9.21 The grout is mixed for a minimum of anchorages, and should not be visible
two minutes unless otherwise on the finished works.
specified. 10.5 Wooden form works for unexposed
9.22 No admixtures like chloride or concrete surface, are executed of
nitrates are used. But if other saws boards with sharp edges and of
admixtures may be used a written the same thickness.
permission must be submitted from 10.6 Wooden form works for exposed
the engineer and check it is applied concrete surface are generally of tongued
strictly with the manufacturer's & grooved boards of the same thickness
instructions. & free from knots, holes, cracks & splits.
9
No Bench/Testing parameter A B C 11.2 All reinforcement bars are of the
10.7 Form work lumber shall be kept specified quality & in accordance with
under shed and in varying thickness the standard technical specification.
and width and shall be constantly 11.3 Given in the design in cases where
aerated and under weight to prevent certificates for ultimate tensile strength,
it from decay. yield stress, elongation and cold bend
tests are not issued by the manufacturers.
10.8 Before any concreting starts, the
form work has the right dimensions 11.4 The dimension, length and shape of
and is level and straight. the reinforcement bars is according
10.9 Before any concreting starts, all to the drawings and specifications.
forms are thoroughly cleaned out 11.5 Bending of reinforcement bars is
and free from holes and dirt. done with adequate bending tools.
10.10 The top level of the form work is at But heat is strictly not allowed for
the same level as the top of the bending of reinforcement bars.
finished concrete. 11.6 All bars with cracks or splits at the
10.11 All form work is removed without bend are not used for construction.
any damage to the concrete during 11.7 All mild steels have their ends
the striking. hooked, and the bending radius
10.12 After removal of the form work meets the specification.
remedial treatment to surfaces of 11.8 All reinforcement bars are clean
the hardened concrete is carried out and free from loose rust, grease, oil,
immediately without delay and or tar and other kind of dirt.
period of removal is as follows: 11.9 The reinforcement bars are placed in
position according to the drawings, &
for vertical form work to columns, walls firmly bound together with mild
and beams - 16 hrs. steel wire, diameter 1.6 mm in
for suffix form work to slab - 21 days accordance with the standard
for props to slabs - 14 days technical specification.
for soffit form work to beams - 21 days 11.10 Before any casting of concrete
for props to beams - 14 days starts, that pre cast concrete blocks
in accordance with the standard
or spacers or metal chairs are
technical specification. prepared and all reinforcement bars
10.13 Where intended to re-use form are placed on them.
work it is thoroughly cleaned and 11.11 These blocks or spacers do not turn
made good to the satisfaction of the over when concrete is cast.
engineer.
11.12 The thickness of concrete cover is
10.14 Stripping of form work not to be done
according to the requirements of the
until concrete is set i.e. should ring
drawings and specifications.
under a hammer blow. In no
circumstances shall form work be struck 11.13 And approve the placing of the
until the concrete attains cube strength reinforcement & form work condition
of at least twice the stress to which it before any concrete is cast.
may be subjected at the time of striking. 11.14 The reinforcement in structures are not
welded unless permitted by the
10.15 All form work construction and designer.
quality comply the standard technical
specification.
No Bench/Testing parameter A B C
11 STEEL REINFORCEMENT
11.1 Steel reinforcement is stored in
clean condition. It should be free
from loose rust.
10
A: not completed B: visual control not possible C: checked
11
A: not completed B: visual control not possible C: checked
12
A: not completed B: visual control not possible C: checked
13
A: not completed B: visual control not possible C: checked
14
No Bench/Testing parameter A B C 24.17 Window panels are of the right
24 CARPENTRY AND JOINERY thickness and properly fixed.
24.1 Timber for carpentry and joinery is 24.18 All carpentry and joinery to comply
as specified and of best quality. with the standard technical
24.2 Timber is reasonably straight grained specification.
& obtained from an approved sources 25 CEILING
24.3 And inspect the timber as it arrives, 25.1 Material & dimensions are according
Any timber not approved is removed to the specifications & the drawings.
forthwith. 25.2 Before any mounting, painting of
24.4 Timber is open stacked for as long parts in connection with the ceiling
as possible before use. such as steel guides and walls, is
24.5 Timber and assembled wood work completed.
are protected from rain and sun. 25.3 The ceiling in cleaned and well fixed
24.6 Timber and assembled wood work when the work is completed.
are stored in such away as to prevent 26 PAINTING
attack by termites, insects or 26.1 The kind of paints in according to
decayed fungi. the specifications and designer's
24.7 Timber ready for use in free from instructions.
live borer, beetle or other insect 26.2 The painting is done according to the
attack. manufacturer's instructions.
24.8 All measures to eradicate insect 26.3 The paint is not diluted unless
attack of timber are approved. specified by the manufacturer.
24.9 Timber is seasoned to moisture 26.4 All surface to be painted is clean
content of not more that 20% for from dust and dirt.
Carpentry and 12% for joinery. 26.5 All surface to be painted is
24.10 All timber surface exposed by absolutely dry & free from defects
cutting are treated with three coats of before painting.
approved preservative. 26.6 All brushes and tins used for
24.11 All pressure impregnated timber is painting are clean and free from old
treated with preservative chemicals at paint.
a pressure of not less than 10 26.7 The room is closed until the paint dries.
atmospheres & in accordance with the 26.8 All electrical appliances iron & brass
chemical manufacturer's instruction. works are removed before painting &
24.12 Fixed joinery is completely properly re-fixed after painting.
protected from damage until the 27 GLAZING
completion of the construction. 27.1 Frames are fixed straight & in plumb.
24.13 Profile of sections is not modified 27.2 The type and thickness of glass is
from those shown on drawings according to the specifications and
without approval. drawings.
24.14 Right type of door is fixed in the 27.3 The application & properness of putty.
right place and that the doors open in 28 WATER WELL
accordance to the drawings. 28.1 The water well is dug according to
24.15 Door frames and window frames are the specifications and drawings, if
fixed straight and in plumb. possible dug during the dry season.
24.16 Hinges, locks, latches and handles 28.2 If septic tanks, soak away pits and
are of approved type and properly dry latrines are situated nearby and
fixed. inform the designer to change the
No Bench/Testing parameter A B C position of the well.
15
No Bench/Testing parameter A B C covering soil layer is minimum 50cm.
28.3 The water is tested and approved 31.6 The joining of concrete to pipes is
after the digging is completed. always done with cement mortar, the
28.4 The masonry work is not started joint completely filled all around.
before the test result is known and 31.7 Joining of asbestos cement pipes is
approved. done according to the manufacturer's
29 WATER SUPPLY LINES instruction. Inspection pit is
29.1 The dimensions and types, tubes according to the drawing before back
valves and water tower is filling.
according to the specifications and 31.8 All pipes connected to the inspection
drawings. pit come approximately on the same
29.2 All pipes, unless otherwise level and check channel formed in
specified are buried in the ground concrete at the bottom of the pit.
to a Minimum depth of 30cm. 31.9 Back fill soil is of good quality, free
29.3 All valves are placed according to from stones and it is not top soil.
the drawings. 31.10 Back filling is in layers of minimum
29.4 Inspect and approve the supply line 20cm, if vibrating or roller machine
before any back filling starts. is used the thickness of the layer
30 PLUMBING AND SANITARY can be 40cm unless otherwise
INSTALLATIONS specified.
30.1 Dimensions & types of pipes, tubes, 31.11 Each layer of back fill is well
valves & sanitary ware are according rammed and consolidated with the
to the specification and drawings. addition of water if necessary.
30.2 All pipes and tubes to be installed 31.12 The correct position of the water and
in the floor are placed in position. sewer systems and prepare a sketch
30.3 All joints before mass concrete in last. on the site plan to send to the
30.4 Pipes & tubes are placed in the hard designer for preparing drawings
core with minimum 10cm covering showing their correct positions as
layer of sand or in channels of built on site.
floors as indicated on the drawings. 31.13 Measure the correct lengths of all
30.5 All sanitary ware is properly fixed trenches, of all tubes and pipes.
in its correct position. 32 SEPTIC TANK AND SOAK
30.6 All connection between sanitary AWAY PIT
ware and sewer system is done 32.1 Dimension and type of septic tank
with the prescribed siphon. and soak away pit is according to the
30.7 All exposed pipes and tubes are specifications and drawings.
well cleaned & painted as 32.2 The position of septic tank and soak
specified. away pit if situated nearby water
30.8 All sanitary works comply with the wells, and inform the designer for the
standard technical specification. change of the positions.
31 SEWER SYSTEM 32.3 Level of overflow pipes between
31.1 Dimensions and types of pipes and different chambers & inlet and outlet
inspection pits are according to the pipes are according to the drawings.
specifications and the drawings.
31.2 The excavation measurements of
the sewer lines are according to the
drawings.
31.3 The excavation is done in straight
lines between the manholes.
31.4 All trenches before pipes are laid.
No Bench/Testing parameter A B C
31.5 Unless otherwise specified, the pipes
are laid on a sand bed with a
minimum thickness of 10cm and in
an absolutely straight line with an
even slope of minimum 1:100 and
16
Original signed: yes no
17
Original signed: yes no
18
A: not completed B: visual control not possible C: checked
19
SECTION 2
INSPECTION AND ACCEPTANCE CERTIFICATES
20
Site Hand over/Take over Inspection Certificate
4. Additional Items/Comments:
Following an inspection of the site as per the above listed items the contractor is
here by advised to take over the site and proceed with the subsequent Mobilization and
site preparation works.
21
Project : ________________ Location: _________________
Employer : ________________ Contract No. _______________
Contractor: ________________
Consultant: ________________
3. Additional Items/Comments :
Following an inspection of the layout and levels of all buildings, site works, etc. as per
the above listed items permission to proceed with the subsequent Excavation/Earth
works is hereby Granted/Refused to the contractor.
22
1. Foundation Layout ____________________
2. Width of Excavation ____________________
3. Depth of Excavation ____________________
4. Method of Excavation ____________________
5. Type of Excavation material (s) compared to
soil report ____________________
6. Foundation levels ____________________
7. Type of soil at foundation level ____________________
8. Foundation Pits & Trenches Free from
– Ground water ____________________
– Roots and bushes ____________________
– Backfill or made ground ____________________
9. Sides of Pits & Trenches
– Safe from damage ____________________
– Protected with sheeting, strutting & shoring ____________________
10. Additional Items/Comments.
1. Excavation :-
23
soil, roots, ____________________________
– Thickness of Excavated materials: ____________________________
– Slopes & Levels of Excavated Surfaces ____________________________
– Necessary Temporary drains provided : ____________________________
– No Damage to adjacent areas ____________________________
3. Filling :-
4. Degree of Compaction :-
6. Additional Items/Comments
Following an inspection of the quality of Earthworks as per the above listed items permission to
proceed with the subsequent construction/ _____________________/ work is hereby
Granted/Refused to the Contractor.
24
Certificate No. 005
1. Testing Laboratory
_____________________________
2. Test No.
_____________________________
3. Date of Testing
_____________________________
4. Kind of Material Tested
_____________________________
5. Required Tests
_____________________________
____________________________
25
6. Required/specified qualities
_____________________________
_____________________________
7. Test results
_____________________________
_____________________________
8. Recommendation of supervisor :
Material Accepted / Rejected
9. Additional Items/Comments
26
– Water Cement ____________________
– Workability/Slump ____________________
– Flexural Strength ____________________
Following an inspection of the quality of concrete work as per the above listed items
permission to pout concrete is hereby Granted/Refused to the Contractor.
27
Certificate No. 007
Following an inspection of the quality of Masonry Work as per the above listed items
permission to proceed with the subsequent construction /_________/work is hereby
Granted/Refused to the Contractor.
28
Supervisor : Name __________________ Contractor : Name __________________
Sig. __________________ Sig. __________________
Date __________________ Date __________________
1. Component _______________________________
2. Steel Members – Quality _______________________________
– Shape/Size _______________________________
– Straightness _______________________________
– Free from :-
: Twist _______________________________
: Dust/Dirt/Water _______________________________
: Loose Rust _______________________________
: Other Damages _______________________________
3. Quality/Size of – Plates _______________________________
– Bolts/Nuts _______________________________
– Electrodes _______________________________
4. Shape/Pattern of Steel Work _______________________________
5. Condition/Capacity of welding equipment _______________________________
6. Weld – Type (Fillet, Butt) _______________________________
– Run continuous _______________________________
– Sound _______________________________
– No porosity _______________________________
– Correct Finishing _______________________________
– Slag Chipped _______________________________
– Seal complete _______________________________
7. Anchor Bolts – Correct Location _______________________________
– " Elevation _______________________________
– " Plumbing _______________________________
8. Position, Size of Holes for:
– Electrical Fittings _______________________________
29
– Partition _______________________________
– Others _______________________________
9. Erection – Correctly slung _______________________________
– " Lifted _______________________________
– " Positioned _______________________________
– " Bolted/Welded _______________________________
10. Painting – Rust Removed _______________________________
– Primed _______________________________
– No. of Coats Applied _______________________________
Following an inspection of the quality of steel work as per the above listed items permission to
proceed with the subsequent construction/ ____________________/work is Granted/Refused to
the Contractor.
30
Certificate No. 009
1. Component ________________________
2. Timber Members: – Quality ________________________
– Shape/Size ________________________
– Free from
: Decay ________________________
: Insects attack ________________________
: Other damages ________________________
3. Type Quality of Timber Treatment ________________________
4. Storage protection of Timber ________________________
5. Quality / Size of – Nail ________________________
– Bolts/Nuts ________________________
– Glue ________________________
– Other joinery ________________________
6. Shape/Pattern of Timber work ________________________
7. Quality of Fabrication ________________________
8. Quality/location of Joinery ________________________
9. Quality of Erection ________________________
10. Straightness/Deflection of Timber work ________________________
11. Additional Items/Comments: ________________________
31
Certificate No. 0010
Carpentry & Joinery work Inspection Certificate – For Item Location ___________
1. Ceiling Work
: Hinges ______________________________
: Locks ______________________________
: Latches ______________________________
: Handles ______________________________
3. Additional Items/Comments
Following an inspection of the quality of carpentry, Joinery & Glazing work as per the
above listed items permission to proceed with the subsequent construction
/____________/ work is Granted/refused to the contractor.
32
Certificate No. 0011
Roofing & Cladding Work Inspection Certificate – For Item Location ________
1. Roofing work
3. Additional Items/Comment :
Following an inspection of the quality of Roofing and cladding work as per the above
listed items permission to proceed with the subsequent construction /_______________/ work
is Granted/Refused to the Contractor.
33
Finishing work Inspection Certificate – For Item Location ______________
1. Plastering Work
4. Glazing work
34
– Quality of window panels fixing _________________________
5. Painting work
6. Additional Items/Comments:
Following an inspection of the quality of Finishing work as per the above listed items
permission to proceed with the subsequent construction/_____________________/ work is
Grant/ Refused to the Contractor.
35
Consultant: ______________________
Dimensions and types of pipes, tubes, valves and water tower are according to the specifications and
drawings _________________________
Dimensions and types of pipes, tubes, valves and sanitary ware are according to the specifications
and drawings __________________________
- All exposed pipes and tubes are well cleaned and painted as specified _________
- All sanitary works complies with the standard technical specification _________
3. Sewer System
36
and drawings ______________________
5. Additional Items/Comment:
Following an inspection of the quality of Sanitary (Plumbing) woks as per the above listed
items permission to proceed with the subsequent construction /_______________/ work is
Granted/Refused to the Contractor.
1. Installations:
37
- All electrical installation complies with the standard
Technical Specification
2. Materials
3. Workmanship
- All switches and outlets are properly fixed according to the drawings ________________
- The connections of wires are always done in junction boxes _________________
- All external cables are placed with a minimum 10cm depth in
concrete or asbestos cement pipes and 40cm depth in the ground,
unless otherwise specified _________________
- The excavation, the inspection pits and the pipes works are
done in accordance with the drawings and specifications ___________________
- All underground cable joining are done in special water-tight
junction box approved by EELPA or designated professional ___________________
4. Additional Items/Comments
Following an inspection of the Electrical works as per the above listed items permission to
proceed with the subsequent work is hereby Granted/Refused to the Contractor.
38
– Quality and Size of Hard core stone material ______________________
– Thickness, placing, ramming and blinding of Hard
core layer ______________________
– Quality, thickness and degree of compaction of:
– sub base layer ______________________
– base course layer ______________________
– surface course layer ______________________
– Slopes and Levels or Tope surface layer ______________________
3. Retaining Wall
39
– Quality of Work above ground level _____________________
5. Additional Items/Comments
Following an inspection of the site works as per the above listed items permission to proceed
with the subsequent work is hereby Granted/Refused to the Contractor.
Minutes of meeting
40
1. ______________________________ _______________________________
2. ______________________________ _______________________________
3. ______________________________ _______________________________
4. ______________________________ _______________________________
5. ______________________________ _______________________________
6. ______________________________ _______________________________
7. ______________________________ _______________________________
8. ______________________________ _______________________________
I ______________________________________
Outline of remarks and/or changes noticed.
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
41
1. The Construction of this ___________________________________________
is in accordance with plans & specifications.
2. Outlines of remarks given above are based on our observations and are to be notified
as per plan and specification.
C.C.
__________________________
__________________________
__________________________
Project : _______________________________________________
Location : _______________________________________________
Employer : _______________________________________________
Contractor : _______________________________________________
42
4. __________________________ " " _________________________
5. __________________________ " " _________________________
6. __________________________ " " _________________________
7. __________________________ " " _________________________
Have examined:
a) Contract documents, Drawings and Specifications:
b) _________________________________________________________________
c) _________________________________________________________________
and have proceeded with the ascertainment of the completion and Temporary Acceptance
of the above project on the bases of the following information:
A. Date when the contractor took possession of site ___________________________
B. Agreed length of completion time ______________ Calendar days (working days)
C. Commencing date ___________________________________________________
D. Completion date according to contract: _________________________________
E. Actual completion Date: ______________________________________________
F. Total Number of delay ________________________________________________
G. Number of justified days of delay _______________________________________
H. Number of Unjustified days of delay _____________________________________
I. Penalty of ________day Eth. Birr ______________ per day Eth. Birr ___________
ACCOUNT
DEDUCTIONS
43
works expected payable on the final acceptance
__________________________________________
Net Sum Payable to the Contractor ______________
Performance Bond: ________________________________
REMARKS: _________________________________________________________
_________________________________________________________
_________________________________________________________
Conclusion:
We witness thereof, we have written and signed this temporary acceptance of which one copy
is to be issued to the contractor for all practical purposes after due approval.
__________________________ _____________________
Construction Supervisor Contractor
ATTENDING PARTIES
44
Date ______________________
Project : _______________________________________________
Location : _______________________________________________
Employer : _______________________________________________
Contractor : _______________________________________________
Have examined:
45
a. Date of Temporary Acceptance ______________________
b. Date of Final Acceptance___________________________
c. Remarks made during the provisional Acceptance of the works:
1. __________________________________________________________________
2. __________________________________________________________________
3. __________________________________________________________________
A. Signs of visible defects: The general examination of the works as well as random checks
and test made of the different parts of the project have shown:
_______________________________________________________________________
_____________________________________________________________
B. New facts: Since the provisional Acceptance of the works, the following facts have
occurred:
1. ___________________________________________________________________
2. ___________________________________________________________________
3. ___________________________________________________________________
4. ___________________________________________________________________
D. General remarks: The comparison of the Report of the Provisional Acceptance of the
works with the present condition of the entire project, the contract and other
justificative documents have brought up the following remarks:
1. ___________________________________________________________________
2. ___________________________________________________________________
3. ___________________________________________________________________
46
4. ___________________________________________________________________
A C C O U N T:
B. D E D U C T I O N S
3. Various Deductions:
a.________________________
b. _______________________
CONCLUSION
Therefore, we do hereby declare that the work has been executed in the principle of good
workmanship, and have accepted the project definitely on behalf of
_______________________________________________________ .
47
Certificate No. 0019
Act of Renouncement
Any action or claim or reservation that we may take in the future shall be deemed as legally
covered by the present Act of Renouncement.
48
SECTION 3
USEFUL FORMATS FOR USE DURING CONSTRUCTION
49
FORM – 01
The Contractor, therefore, acknowledges the taking over of the site and immediately the work with
all its explanation clearly defined in the specification and drawings (sketches).
The Contractor, hereinafter, shall be responsible for the damages that occur as a result of his fault,
carelessness or negligence in connection with untimely commencement of the work.
The Contractor, in addition, acknowledges the completion of the said work shall count as from the
date mentioned above and comply with the terms and conditions of the Contract to the Contract to
the satisfaction of the Client.
IN WITNESS HEREOF THIS DOCUMENT HAS BEEN SIGNED BY ALL PRESENT IN SIX
COPIES OF WHICH THE CLIENT HAS ONE, THE SUPERVISOR ONE, THE
CONTRACTOR ONE, AND THE CONSULTANT THREE.
_____________________________ ___________________________
FOR THE CLIENT (EMPLOYER) THE CONTRACTOR
WITNESS
1. _____________________ 1. ___________________
2. _____________________ 2. ___________________
3. _____________________ 3. ___________________
50
FORM – 02
RECEIPT OF DOCUMENTS
PROJECT : ___________________________________________________
SITE : ___________________________________________________
EMPLOYER : ___________________________________________________
CONTRACTOR : ___________________________________________________
SUPERVISOR : ___________________________________________________
This is to acknowledge that I have received the following set of documents concerning the
project.
_________________________________
DOCUMENT RECEIVED BY
________________________________
DATE: ______________________________
53
FORM – 03
PROJECT : ____________________________________________________
SITE : ____________________________________________________
EMPLOYER : ____________________________________________________
CONTRACTOR : ____________________________________________________
SUPERVISOR : ____________________________________________________
REQUIRED TEST
APPROVED BY _____________________________________________________
CONSULTANT OR DESIGNER
DATE _____________________
54
FORM – 04
PROJECT : ___________________________________________________
SITE : ___________________________________________________
EMPLOYER : ___________________________________________________
CONTRACTOR : ___________________________________________________
SUPERVISOR : ___________________________________________________
APPROVED BY : _____________________________________________
CONSULTANT OR DESIGNER
C.C To Site Supervisor
To Contractor
To Employer
55
FORM – 05
PROJECT : _____________________________________________________
SITE : _____________________________________________________
EMPLOYER : _____________________________________________________
CONTRACTOR : _____________________________________________________
SUPERVISOR : _____________________________________________________
RECOMMENDATION OF
FOUNDATION ENGINEER ___________________________________________________
____________________________________________________________________________
INSTRUCTION PASSED TO
THE CONTRACTOR ____________________________________________________
_____________________________________________________________________________
ACKNOWLEDGEMENT OF SUPERVISOR _______________________________________
_____________________________________________________________________________
56
FORM – 06
SITE DIARY
Report No. _____
Date __________
Project : ____________________________________________________________
Site : ____________________________________________________________
Employer : ____________________________________________________________
Contractor : ____________________________________________________________
Consultant : ____________________________________________________________
Site Supervisor : ____________________________________________________________
1. Weather Conditions : Fine _________ Good ________ Bad _______ Lost Hrs. _______
2. Staff on Site :
Project Eng. ________________ Secretary ______________ Driver ____________
Civ. Eng. _______________ Clerk _________________ Guard ____________
Bld. Eng. _______________ Purchaser ______________ Messenger _________
Technician _______________ Cashier ________________ Cleaner ___________
Eng. Aide _______________ Dresser ________________ Others ____________
3. Labour Force
Gen. Forman _______________ Mason ________________ Plasterer __________
Gen. Operator _______________ Carpenter ______________ Painter __________
Forman ____________________ Barbender ______________ Chiselled __________
Operator ___________________ Plumber ________________ Glazier ___________
Mechanic __________________ Electrician ______________ Labourer _________
Welder ____________________ Helper _________________ Others ____________
4. Work in progress: __________________________________________________________
________________________________________________________________________
9. Remarks: ________________________________________________________________
________________________________________________________________________
________________________________________________________________________
57
FORM – 07
58
FORM – 08
for
1.0 INTRODUCTION
(Describe here briefly the contents of the project, the activities undertaken by the contractor
and consultant during the reporting period, the commencement and completion dates of the
project, etc. ).
(Under this title, contract data of the construction and consultancy services Agreements
can be inserted. Some of the data are presented below. Details of these data can be seen in
the Report Format presented after this report Format).
59
3. CURRENT STAGE OF CONSTRUCTION
Executed as % Executed as
of Total Work, % of Total
value of % of previous Rep- Work, This
Type or work Total work porting period Reporting
period
B. Super - structure
1. Concreting ……………………………
2. Roofing ……………………………….
3. Joinery and Carpentry ………………. .
4. Block Work …………………………. .
5. Metal Works (Windows etc.) ………. .
6. Finishing Works:
a) Plastering & Pointing )
)………….
b) Flooring & Ceiling )
7. Glazing ……………………………….
8. Painting ……………………………….
9. Internal Sanitary Installation …………
10. Internal Electrical Installation
……… .
Total ………………… ..
60
(B) FOR SITE WORKS
Executed as % Executed as %
of Total work, of Total work,
Type of work Value of % of previous Re- This Reporting
Total work porting period period
Site works :
Schedule Commencement
Date ________________________
Time Elapsed _________________
Description of works
1. Fence & Main Gate ……………
2. Guard House …………………..
3. Transformer House……………..
4. Access Roads …………………..
5. Retaining wall ………………….
6. Electrical Installation …………..
7. Sanitary Installation
. Underground Tank ………
. Water Supply Tower ……
8. Landscape ………………………
9. Sport Facilities ………………….
Total
REMARK:
% of work - % of Work-
Amoun Executed , Executed,
Building Unit : (Insert name of building) t in previous this
Birr Re- porting reporting
a) Contract amount in figures _____________ period period
b) Works executed upto last reporting period
from __________ 200_ to _______ 200_…
c) Status of work progress (in percent) as at
__________ 200__,________/200__…
d) Works executed during this reporting period
from ________ 200__ to______ 200__…
e) Status of work progress this reporting period
_____________________/ 200__ …….
f) Status of work progress to date (c + e)……….
61
5. PHYSICAL PROGRESS (IN BAR FORM) : ACTUAL AGAINST PLANNED
Administrati
on A
Building
P
Library A
P
Academic
Buil- A
ding
P
Social
Building A
Dormitory 1, A
Male
P
Dormitory 2, A
Male
P
Dormitory , A
Female
P
Senior Staff A
Residence
(1-8) P
Junior Staff A
Residence
(1-8) P
Site Works
62
6. Cash - Flow : Actual Against Planned
(S-Curve should be drawn in the following graph)
80
Academic
Buil-
ding 50
70
Social
PERCENT COMPLETE
60
Dormitory 1,
Male 40
50
Dormitory 2,
Male
30 40
Dormitory ,
Female 30
20
Senior Staff 20
Residence (1-
8)
10
10
Junior Staff
Residence (1-
0
8)
Site Works
0
REMARK :
63
7. Construction Material Availability
Quantity
Quantity as Quantity Incorporated Quantity due
Item Description / Unit Rate/Unit programmed on site in works under Contract
(1) (2) (3) (4) (5) (6) (7) = (4) - (5) + (6)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
REMARK:__________________________________________________________________________
64
8. Plant and Equipment Availability
Balance
Description of Agreed Fleet Actual Current Due
Item Plant/Equipment in Programme Fleet On Operational Under
Site Fleet Contract
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
REMARK:___________________________________________________________
65
9. Manpower Availability
REMARK : ________________________________________________________
66
10. Evaluation of Availability of Major Items for Satisfactory Execution of works
Yes/No
Previous This
Reporting Reporting
Item Description period period
A) Is there a shortage of :
a) Construction Materials ………………….
b) Equipment and plant …………………….
c) Professionals …………………………….
d) Skilled Manpower ……………………….
e) Cash-flow ………………………………..
D) Others …………………………………………
Previous This
Reporting Reporting
Evaluation (Mark: Poor, Fair, Good, Very Good) Period Period
67
12. Status of Payment to Contractor
REMARK: _______________________________________________________________________
68
13. Quality Control Tests Conducted During this Reporting Period
REMARK:
69
14. WEATHER REPORT
REMARK: _____________________________________________________________________
_____________________________________________________________________
70
15. CONTRACTOR'S AND CONSULTANT'S STAFF
ATTENDANCE RECORD FOR THE PERIOD OF ____________ TO ____________
Position Name 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1) Contractor's Staff
a) Professionals
Civil engineer
Building engineer
b) Skilled workers:
c) Unskilled workers:
2) Consultant's staff
a) professionals
Resident engineer
Construction engineer
b) Assistant Staff
71
16. VARIATION APPROVED
Reason for
Variation order Variation Summary of work Value
REMARK:
_______________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
________________________ ___________________
FORM 09
73
WORK ORDER
Project ___________________________________________________________
Employer ________________________________________________________
Contractor ________________________________________________________
Date ____________________
I, We ______________________________________________________________
___________________________________________________________________
have recommended and instructed the following.
____________________________________________
_____________________________________________
_____________________________________________
_____________________________________________ SKETCH
_____________________________________________ (Sketched and enclosed
_____________________________________________ drawings should be deta-
_____________________________________________ iled enough to work out
_____________________________________________ quantities.)
_____________________________________________
_____________________________________________
_____________________________________________
_____________________________________________
______________________
Consultant or designer
_______________________ _______________________
Contractor Site Supervisor
C.C:
Employer
74
SECTION 4
75
LIST OF MAJOR DUTIES AND RESPONSIBILITIES
3. Reviews the plans and specifications and other pertinent documents that
would be furnished to him for accuracy and completeness.
5. Inspects and approves work methods and quality of all materials used in
the work for conformity with the contract specifications.
8. Arranges periodic and regular site meetings with the line office representative and the
contractor.
9. Consulting with the line office representative, schedules for testing of materials
whenever necessary and submits to him detail field observations on material
characteristics with indications on tests required.
11. Advises the project owner on the need for special inspection or testing
other than those referred to in the contract documents.
12. Keeps a site book and records in it, for the duration of the project such as
the following and any other matter relevant to the works:
12.10 The date of receipt on site by the contractor of any part of designs
or modifications and the persons who delivered them;
12.15 And all other matters related to the construction works that have
caused delays and extra expenses or that have helped for the efficient operations;
12.16 The designer also records in the site book any observations be
made and clarifications he gave on the construction works;
15. Rejects any work or materials that fail to conform to the contract
specifications after the same are thoroughly assessed.
16. Suspends that portion of work where in his opinion there is an imminent
danger to the safety of the workers, provided, however, such suspension shall obtain the
approval of the ADP manager.
17. Examines any proposal submitted by the contractor and advises the
project owner and the line office regarding the same.
77
18. Conducts inspection and prepares certificates of completion jointly with line office
representative.
19. Conducts inspection and prepares certificates of final acceptance of the project jointly
with line office representative.
20. Accepts works executed and materials delivered on site in conformity with the contract
drawings, provisions and technical specifications.
21. Performs all other duties that may be delegated to him in writing by the ADP Manager.
78