MOORING
OPERATIONS
Point of
restraint
Point of
break
Point of
break
WHY CADET’S ????
INEXPERIENCED
MOORING TEAM
SAFERY CULTURE - AWARENESS
WEAK LINKS
BOOST SELF CONFIDENCE
IDENTIFY HAZARDS
MAINTENANCE
GOOD OFFICER
SCOPE
RISKY OPERATION
HAZARDS
MOORING LINE
IMPROPER WORK PROCESS
CREW COMPETENCE
CREW CONCENTRATION
WEATHER
NEW JOINER
MOORING EQUIPMENT
COMMUNICATION
INCIDENCES
SLIP TRIP FALLS
PARTING OF ROPES
OIL LEAKS
PARTING OF ROPE OR STOPPERS
FAILURE OF MACHINERY
NEAR MISSES
CONSEQUENCES
WHAT DOES MOORING SYSTEM DO?
0.5 Df 0.2 Df
CURRENT IKT
5 Df 2 Df
MOORING LINES- CONTROLS FORCES
1 6
2 3 5
4
1.HEAD LINE- BACKWARD FORCE (-Y)
2.BREAST LINE-TRANSVERSE FORCE (-X)
3. FWD SPRINGLINE – FWD FORCE (+Y)
4.AFT SPRING LINE – AFT FORCE (-Y)
5. AFT BREAST LINE – TRANSVERSE FORCE(-X)
6.STERN LINE – FWD FORCE (+Y)
EFFECTIVENESS OF LINES
NO SHORT LINES
DIP TO BE LESS THAN 30 DEGREE
(EFFECTIVENESS COSINE OF ANGLE)
SAME DIRECTION
SAME LENGTH
SAME MATERIAL
CARE AND MAINTENANCE
SNAP BACK
Line handlers must operate clear of the potential
snap – back path
Sudden release of stored static energy in the
stretched synthetic line when it breaks.
General rule,10 deg cone around line from point
of break to beyond point of secure to a distance
almost its own length.
SNAP BACK ZONE
Method Of Using - Bollards &
Rope stoppers
1. NO OF LAYERS BHC
1ST 100%
2ND 88%
3RD 80%
4TH 73%
5TH 67%
SPLIT DRUM WINCHES
SAFETY GUIDELINE:
SHIFTING LINE FROM TENSION DRUM TO
STORAGE DRUM
TO TENSION DRUM REQUIRES CARE AND
SUFFICIENT PERSONNEL
NO MORE THAN ONE TURN TO ME
MAINTAINED ON TENSION DRUM.
MAINTENANCE – FREE LINKS,PINS
SAFETY CULTURE- BEHAVIOUR
???