Project Proposal for 5-Star International Hotel Dire Dawa, 2022
Contents
0. EXECUTIVE SUMMARY ............................................................................. 3
1. BACKGROUND .......................................................................................... 4
1.1. PROJECT OBJECTIVES ..................................................................... 5
1.2. PROJECT LOCATION ........................................................................ 5
2. MARKET STUDY ...................................................................................... 6
2.1. TARGET MARKET ................................................................................. 6
2.2. DEMAND AND SUPPLY .......................................................................... 6
Table: Flow of Tourists ............................................................................ 7
Table: Demand Projection ........................................................................ 8
Table: Bedrooms Supply .......................................................................... 9
Table: Demand and Supply Gap ................................................................ 9
2.3. TARGET MARKET STRATEGY ............................................................... 10
2.4. PRICING ...................................................................................... 10
3. THE PROPOSED PROJECT ......................................................................... 10
3.1. GENERAL FEATURE ............................................................................ 10
3.2. SERVICE DESCRIPTION AND APPLICATION ........................................... 11
3.2.1. BED ROOMS ............................................................................... 11
3.2.2. FOOD SERVICES ......................................................................... 12
3.2.3. BEVERAGES (HOT & COLD) ........................................................... 12
3.2.5. JACUZZI..................................................................................... 12
3.2.6. SAUNA BATH .............................................................................. 13
3.2.7. STEAM BATH............................................................................... 13
3.2.8. MSSAGE SERVICE........................................................................ 13
3.2.9. MULTIPURPOSE HALL ................................................................... 13
3.2.10. BEAUTY SALON ......................................................................... 14
3.2.11. PLAYGROUND FOR KIDS ............................................................. 14
3.2.12 GYMNASIUM .............................................................................. 14
3.2.13. SWIMMING POOL ....................................................................... 14
4. THE HOTEL ............................................................................................ 15
4.1. MISSION .......................................................................................... 15
4.2. VISION ............................................................................................ 15
4.3. VALUES ........................................................................................... 15
5. BASIC INFORMATION OF THE HOTEL ......................................................... 16
0. EXECUTIVE SUMMARY
The owner of the project, Mr. Juhar Osman Musa, is a young Entrepreneur,
with more than 15 years of experience in managing various related
Businesses in outside of the Country.
The project is financially viable with an internal rate of return (IRR) of 81%
and a net present value (NPV) of ETB 739,292,604, discounted at 11%. The
investment cost and income statement projection are used to project the
pay-back period, the project will fully recover the initial investment and
working capital within three years.
1. BACKGROUND
Dire Dawa by virtue of its geo-physical location is acting as the trade center
for Harrari, Oromiya, Somali Regional States and the neighboring State of
Djibouti.
What makes Dire Dawa the ideal industrial and business center of Eastern
Ethiopia is its convenient location, situated close to Djibouti port and the
new railway station which has recently started operation. The investor that
establishes his industry or service-providing firm in the city is bound to be
overwhelmed by the sheer size of the demand he/she has to meet.
St. Michel’s Catholic Church was built over 115 years ago, and is
located 26 kilometers from the city near a place called Beyo Awale.
In view of the above mentioned tourist sites within the City Administration
and in view of the strategic location of the city in relation with the other
places of great tourist attraction in Eastern Ethiopia; that is, Eastern and
Western Hararghe zones of Oromiya, Harari, and Ethiopian Somali National
Regional States, the city can become an integral part of the well-developed
tourist industry in the areas mentioned above by taking the correct steps to
strengthen its promising tourist potential.
Despite the above mentioned potential, Hotel service is one of the untapped
investment areas in Dire Dawa Administration. Although Dire Dawa is the
ageist town next to Addis, hotel, tourism and Hotel development is lagging
behind the youngest towns like Hawassa and others in the southern region.
However, recently so many investors have shown interest to invest in the
hotel industry.
2. MARKET STUDY
2.1. TARGET MARKET
Generally, the tendency of tourists’ visiting destinations in developing
countries is increasing from time to time. The advance of infrastructures has
also contributed towards such increment.
The target market of the project can generally be described as singles and
couples, families with children, foreign and domestic tourists, travelers,
NGO, and governmental officials. Geographically, the target market includes
domestic and international tourists, business people, and others who come
to the city of Dire Dawa.
The project has targeted to render services to tourists (both domestic and
foreign). It is, therefore, assumed that tourists who come to Dire Dawa will
demand bed room services. Demand projection is calculated by taking as a
basis, the recently available domestic and foreign tourists flow data for the
years 2006 up to 2011 (no data is obtained for the year 2012).
Accordingly, data on both local and international tourists’ flow during the
past few years is shown in the table below.
During the period under reference (2006 – 2011), growth rate of tourists’
flow exhibit substantial fluctuations from year to year averaging at 26.88%.
Given, the considerable fluctuations, the average annual growth rate for the
years 2006 to 2011 is assumed to approximate the actual growth in the year
2012. Accordingly, the present flow of tourists to Dire Dawa in year 2012 is
estimated to be 130,583.
Thus, we learn that the average annual tourists flow growth rate is 26.88%.
Based on this, the number of Ethiopian tourists and Foreigners who came to
Dire Dawa in year 2012 is estimated to be 130,583.
Using the average growth rate, the number of foreign tourists coming to the
city of Dire Dawa for the number of bed nights that they would demand for
the next 10 years (2012- 2021 EC) is forecasted. The average number of
days that tourists would stay is assumed to be 10 days.
According to the data obtained from Dire Dawa Administration culture and
tourism department, the total supply of bedrooms in the city looks like the
following.
Based on the above demand and supply data, the demand and supply gap is
indicated in the following table. A 10% increase in total annual supply is
assumed in projecting unsatisfied demand.
Therefore, there is big unsatisfied demand for additional Hotel services in the
city.
2.4. PRICING
The pricing of hotel services depends considerably on the quality of service
rendered and its location. To establish affordable price at the beginning of
the operation of these luxury hotel service, prices of similar hotel services in
Dire Dawa are taken as bench marks to fix the prices of the proposed
services.
Spa, Beauty Salons, Tour & Travel Agency, Swimming Pool, Gymnasium, and
Cafeteria, Restaurant and other services.
Besides the construction, the project has sub components which include
procuring facilities, equipment and furniture for each rooms of the building.
People coming in to Dire Dawa from different corner of the country for
private or public business and tourists (both domestic and foreign) will be
the major customers of the services to be rendered by proposed project.
assumed that the bed rooms are fully occupied for 5 days every week or 260
days in one year period.
Regarding food services, the hotel can daily serve 60 dishes on breakfast, 80
dishes on lunch and 80 dishes on dinner on which it will charge Birr 120 for
breakfast and Birr 150 for lunch and dinner.
3.2.5. JACUZZI
Jacuzzi service will be given in two separate classes. Each class will have 8
seats for female users and 8 seats for male users at a time. This service will
stay open all days throughout the week for 16 hours. However, it is assumed
that every client will use the facility for a period of two hours and out of 16
hours; the facilities will be occupied for 10hours for 2days every week.
Other services which are going to be served will be laundry and provision of
processed chips. Laundry service will be given to customers coming to hotel
to use bed room service and processed chip will be served complementing
food served at hotel restaurant. It is assumed that the laundry will wash 20
suits every day for 365 days.
3.2.12 GYMNASIUM
The envisaged gymnasium will composed of one machine room (200sq. mt),
one Aerobics studio (100 sq. mt)
The swimming pool service will be provided to customer from guest room or
from outside. Lockers are provided for customers for clothing and other
belongings. The lockers require a coin to be inserted as deposit or payment.
Showers are also ready for customers (male and female), before and after
swimming. Other service requirements (deserts, hot and cold drinks) are
also provided to customers.
4. THE HOTEL
4.1. MISSION
4.2. VISION
4.3. VALUES
At its core, the proposed Hotel establishment holds the following values and
beliefs:
Respect - We respect the values of our guests, and the cultural difference in
Juhar Osman Musa is the owner of the envisaged project. He has got a very
good entrepreneurial skills and long years of experience doing independent
businesses in Ethiopia and other Countries.
6.3. UTILITIES
The major utilities required by the facilities are electricity, water, internet
and telephone.
Total 42,130
7. FINANCIAL ANALYSIS
The total fixed investment cost of the project including cost of building and
civil works and purchase of machineries, facilities and equipment is
presented in the following table.
Table: Depreciation
Expected Original value Annual Dep.
NO Description life (Birr) (Birr)
1 Building & Construction 20 439,754,206.22 2,707,351.27
2 Machinery & Equipment 20 51,918,830.00 1,885,924.00
3 Vehicles 20 780,000.00 39,000.00
Total 492,453,036.22 4,632,275.27
Due to expected increase in prices of raw materials, total operating costs are
projected to increase by 5% every year until the fifth year and remain
constant.
Investment cost components of the expansion project are the cost required
for the G+12 buildings, purchase of Hotel equipment, facilities and
machines, preproduction expenses and working capital to purchase the
required raw materials and auxiliary materials.
1 2 3 4 5
Sales 180,902,000 198,992,200 218,891,420 240,780,562 264,858,618
Direct cost of sales 8,915,763 9,361,551 9,829,629 10,321,110 10,837,166
Gross Profit 171,986,237 189,630,649 209,061,791 230,459,452 254,021,453
Operational expense 57,822,389 59,482,376 61,225,362 63,055,498 64,977,140
Profit before tax and interest 114,163,848 130,148,273 147,836,429 167,403,954 189,044,312
Depreciation 24,622,652 24,622,652 24,622,652 24,622,652 24,622,652
EBITDA (Earning before tax,
138,786,499 154,770,924 172,459,081 192,026,606 213,666,964
interest and depreciation)
Interest expense 33,357,961 35,113,644 35,113,644 35,113,644 35,113,644
Profit tax (35%) 0 0 0 46,301,609 53,875,734
Net profit 80,805,886 95,034,629 112,722,785 85,988,702 100,054,935
ASSETS 0 1 2 3 4 5
Current Assets
Cash 8,770,444 79,085,339 163,628,976 265,860,769 341,358,479 430,922,422
Other Current Assets
0 0 0 0 0
Total Current Assets
8,770,444 79,085,339 163,628,976 265,860,769 341,358,479 430,922,422
Fixed Asset
Building and Civil Work 439,754,206.22 417,766,496 395,778,786 373,791,075 351,803,365 329,815,655
Machinery & Equipment
51,918,830.00 49,322,889 46,726,947 44,131,006 41,535,064 38,939,123
Motor Vehicles 780,000.00 741,000 702,000 663,000 624,000 585,000
Total Fixed Asset 492,453,036 467,830,384 443,207,733 418,585,081 393,962,429 369,339,777
Pre-operating Costs 400,000 360,000 320,000 280,000 240,000 200,000
Total Asset 501,223,481 546,915,723 606,836,708 684,445,850 735,320,908 800,262,199
LIABILITIES
Short term liability - - - - - -
Long term liability (Bank
Loan) 351,136,436 316,022,793 280,909,149 245,795,505 210,681,862 175,568,218
Sub Total 351,136,436 316,022,793 280,909,149 245,795,505 210,681,862 175,568,218
CAPITAL
Owner's Equity 150,487,044 150,487,044 150,487,044 150,487,044 150,487,044 150,487,044
Retained Earnings -400,000 80,405,886 175,440,515 288,163,300 374,152,002 474,206,937
Earnings 80,805,886 95,034,629 112,722,785 85,988,702 100,054,935
Sub Total 150,087,044 230,892,930 325,927,559 438,650,345 524,639,046 624,693,981
Total Liability & Capital 501,223,481 546,915,723 606,836,708 684,445,850 735,320,908 800,262,199
Net Worth 150,087,044 230,892,930 325,927,559 438,650,345 524,639,046 624,693,981