MINUTES OF MEETING

For Meeting No.


Client Consultants Meeting CCM / 00
Design Coordination Meeting DCM / 00
Design Team Meeting DTM / 00
Site Meeting X SM/ 001
Others (specify below) Presentation

MINUTES OF SITE MEETING


Client: Jabatan Kerja Raya Negeri Selangor
Project: Cadangan Membina Dan Menyiapkan Masjid
Kota Kemuning Seskyen 31, Shah Alam, Prepared by: ----------------------------
Daerah Klang, Selangor Darul Ehsan Harith Hisham Hashim

Endorsed by: ----------------------------


Project No: P1204 Zulkifli Haji Alang
PREVIOUS AND CURRENT MEETING MEETING NOTICE
PREVIOUS Issued by:
Subject : Mesyuarat Pra-Pembinaan ATSA ATSA Architects Sdn. Bhd.
Day/Date : Tuesday, 12 Sept 2017 Distribution:
Time : 9:30 am – 1:00 pm JKR Jabatan Kerja Raya
Bilik Mesyuarat Seroja, Bangunan SAAS, Shah
Venue : Fax:
Alam
ISLA Islah Niaga Sdn. Bhd.
CURRENT Fax:
Subject : Kick Off Meeting JTBSB Juru & Teras Bersekutu Sdn. Bhd.
Day/Date : Thursday, 19th October 2017 Fax:
Time : 9.30am TYPSB TY Perunding Sdn. Bhd.
Pejabat Tapak Masjid Kota Kemuning, Seksyen
Venue : Fax:
31, Shah Alam
ATTENDANCE LIST
No. Representing: Representing:
1. En. Zulkifli Haji Alang ZHA ISLA Islah Niaga Sdn Bhd
2. En. Fathill Hani FH
3. En. Haji Adnan HJA
4. En. Azim A Aziz VJ ATSA ATSA Architects Sdn. Bhd.
5. En. Muhammad Razif Abdul Aziz RAZ
6. En. Harith Hisham Hashim HH
7. En Zulqaisar Hamdin ZH
8. En. Mohd Ismail Abu Bakar MIAB
9. En. Wan Hassan bin Wan Musa WHM JKR Jabatan Kerja Raya Negeri Selangor
10. Pn. Rohana Binti Darhaman RBD
11. Pn. Nur Ain Binti Hurin NAH
12. Pn. Effa Irda Wati Binti Superman EFF
13. Ir. Abdul Khalid Abdullah AKA
14. Ir. Meor Mohd Mahazir Bin Meor Hassan MMM JTBSB Juru & Teras Bersekutu Sdn. Bhd.
15. En. Mohamad Helmi Bin Mohd Nurdin MHN JAIS Jabatan Agama Islam Selangor
16. Pn. Wan Azlina Binti Wan Aira WAB JAIS
17. En. Zahir Manaf ZM PT Perunding Trussmaju
18. Pn. Siti Nafihah Hamdan SFH
19. En. Muhammad Fakira MF PQS Praktikal QS
20. En. Muhammad Amirul Farris MAF
21. En. Abdul Hakim Bin Daud AHD
22. Sr. Ina Binti Abdul Bakar IBAB CICQS CIC-QS Service Sdn Bhd
23. Pn. Siti Hasnah M. Kassim SHK TYPSB TY Perunding Sdn. Bhd.
24. En. Mohamed Ajidee Bin Chih Wee MAC
25. Sr. Yusliza Parian YP

Project No.P1204/LBR/VJ/4/5/2024 Page 1 of 5


Item Particulars Description
1. Project Title The Proposed Construction and Completion of a Public Mosque
1.) Main Prayer Building
2.) 1 Unit TNB Substation,
3.) 1 Parking Lot and Other Related Works as part of ) Masjid Kota
Kemuning Seskyen 31, Shah Alam, Daerah Klang, Selangor Darul
Ehsan

2. Main Contractor ISLAH NIAGA SDN BHD


3. Form of Contract PAM 2006 (With Quantity)
4. Date of Letter of Award
5. Date of Site Possession
6. Contract Period 24 Months
7. Date of Commencement 13 September 2017
8. Date of Completion 10 September 2019
9. Original Contract Sum RM16, 285, 842.52
10. Current Certified Amount NA
11. Liquidated & Ascertained Damages RM20, 000.00 / Day
12. Defect Liability Period 18 Months
13. Performance Bond RM864,292.10 (5% of Contract Sum)
14. Insurances Coverage Amount Effective Date Expiry Date
Workmen’s Compensation (WC) RM TBC 13.09.2017 14.09.2019
Contractor’s All Risk (CAR) RM TBC 13.09.2017 14.09.2019
15. CIDB Reg. No. Effective Date Expiry Date
Registration
Levy
16. SOCSO (PERKESO) Code No. Effective Date

Project No.P1204/LBR/VJ/4/5/2024 Page 2 of 5


Item Subject Action By Date
1.0. INTRODUCTION
1.1.
Address Notes INFO
Site Meeting commenced at 9:30am chaired by En. Wan Hassan Bin Wan Musa, Jurutera
Daerah Selangor. Round table commenced with introductions from all consultants.

Chairperson emphasized that ISLA must at all times prioritize “SAFTEY & QUALITY” on the INFO
project and open lines of communication between all consultants is needed.
1.2. Letter of Award
1.2.1. The main contractor for the project is Islah Niaga Sdn. Bhd.(ISLA) INFO

1.2.2. Contract Information are per stated on Page 2 of the minute of


meeting.

1.3. Project Management Protocol


1.3.1 Juru & Teras Bersekutu informed the appointment of the C&S RE/CoW
was anticipated latest by 26.10.2017. Chairman emphasized the urgency for
site representation and advised ISLA to photograph dated and document all
current activities on site. ISLA
26.10.2017

1.3.2 All communication via letters / email should be addressed to all the respective
consultants and copied to JKR for information.

Item Subject Action By Date


2.0 MAIN CONTRACTOR’S MATTERS
2.1 Work Program / CMP
2.1.1 ISLA to submit their proposed work programme together with their S-
Curve Diagram (Physical & Financial) by next week. ISLA
Project No.P1204/LBR/VJ/4/5/2024 Page 3 of 5
26.10.2017
- All Consultants involved to be kept informed and to comment
before accepting proposed work programme prepared by ISLA.
2.2 ISLA
Site Organization Chart
2.2.1 Site Manager (ISLA) is Encik Haji Adnan 26.10.2017
- ISLA to appoint a Site Safety Supervisor by next week.
2.3 ISLA
Format for Monthly Progress Report 26.10.2017
2.3.1 ISLA to submit their draft monthly progress report by next week for
approval.

Documentation for Procedure of Site Works


2.4
2.4.1 Request for Work Inspection (RFWI)
- For Earth Works, all necessary steps must be taken and submitted
to JKR for their approval.
2.4.2 Request for Information (RFI)
- Any information required must be in proper documentation.
2.4.3 Schedule of Works (Two Weeks Before & After)
- Submit schedule for work every two weeks.
2.4.4 Material Approval
- All material specified in contract or drawings need to get approval
from consultants.

Qualified Safety Site Supervisor


ISLA
2.5.1 As required by CIDB & Safety Department.
2.5 26.10.2017

Item Subject Action By Date


2.0 MAIN CONTRACTOR’S MATTERS
2.6 Preliminary Items As Stated In Contract
2.6.1 ISLA have to provide as required by the contract such as; 26.10.2017
- Safety Boots
- Safety Helmet
- Wash Through
- Site Office with adequate Air-Conditioning
- Tele-Communications
- Portable Washrooms

2.7 Construction Drawings


2.7.1 All the necessary construction drawings from all related consultants need to be Consultants 26.10.2017
issued to ISLA.

As-Built Drawings for Earthworks & Piling Works


2.8 2.8.1 ISLA to submit the as-built drawings for earthwork & piling works with endorsements ISLA 27.10.2017
by qualified surveyor.

Item Subject Action By Date


3.0 MBSA’S MATTERS
Site Security & Workers Permits
Project No.P1204/LBR/VJ/4/5/2024 Page 4 of 5
3.1 MBSA raise issues in regards to over-flowing residual water from the site seeping into the
Public Lake which is perpendicular to the site. ISLA

- ISLA has dug trenches around the circumference of the site to ensure no residual
murky water seeps into the lake.

3.2 Site Restriction


MBSA has requested to keep Site Entrances closed when not being used, ISLA
as the entrance is by a main and busy road.

3.3 Submission of Drawings and Documents for MBSA’s Approval ISLA On Going
ISLA and Consultants to work together to ensure all necessary Forms and Plans have been
submitted and give the greenlight by MBSA as we venture forward into this project. MBSA
officials have offered to give as much assistance as possible.

7.0 ADJOURNMENT OF MEETING


7.1 Next Site Meeting:
To Be Confirmed

Project No.P1204/LBR/VJ/4/5/2024 Page 5 of 5