Professional Documents
Culture Documents
Indian Standard
ICS 93.020
© BIS 2018
FOREWORD
The Indian Standard (Part 5) was adopted by the Bureau of Indian Standards, after the draft was finalized by Hill
Area Development Engineering Sectional Committee had been approved by the Civil Engineering Division Council.
Retaining walls are structures, which support the backfill and maintain the difference in elevation of the two
ground surfaces. They are generally located at the toe of cut slopes on valley side of a hill road section or excavated
platform. Retaining walls are effectively utilized to tackle the problems of landslide in hill areas by providing
support to the hill slopes or cut slopes.
In general, 1 m of extra width in filling and requiring retaining wall at the end may cost more than excavating the
same width by cutting inside the hill. However, considering maintenance cost, progressive slope instability and
environmental degradation resulting from unprotected excavation, the use of retaining walls becomes essential.
This standard (Part 5) is therefore formulated to provide necessary guidelines for construction of cement stone
masonry retaining walls for stability of hill slopes this standard is being published in different parts. The following
parts have already been published:
Part 1 : 1998 Selection of type of wall
Part 2 : 1997 Design of retaining/breast walls
Part 3 : 1998 Construction of dry stone walls
Part 4 : 2018 Construction of banded dry stone masonry walls
Other parts being formulated are:
a) Construction of gabion walls,
b) Construction of RCC crib walls,
c) Design of RCC cantilever walls/buttressed walls/L-type walls, and
d) Design and construction of reinforced earth retaining walls.
Presently various types of retaining walls such as dry stone, gabion, banded dry stone, cement stone or other such
retaining walls are preferred for heights up to 4 m. The choice of a particular wall is dependent on the nature of
ground, available budget and availability of construction materials. In general, the cement stone retaining walls, if
constructed properly, perform better in most of the terrain conditions. However, it is preferable to construct
cement mortar masonry wall or RCC walls, when the height of retaining walls exceeds 4 m.
In most cases, the failures of retaining walls, particularly cement stone masonry walls and RCC walls, are often
resulted if the provisions of drainage are inadequate, especially during rains. Inadequate section of walls and poor
quality construction are other reasons for failure of cement stone masonry walls. This standard (Part 5) therefore,
provides suitable guidelines to the field engineers for construction of cement stone masonry retaining walls. Strict
supervision is essential for long life of these types of walls.
The composition of Committee responsible for the formulation of this standard is given in Annex A.
For the purpose of deciding whether a particular requirement of this standard is complied with, the final value,
observed or calculated, expressing the result of a test or analysis, shall be rounded off in accordance with IS 2 : 1960
‘Rules for rounding off numerical values (revised)’. The number of significant places retained in the rounded off
value should be the same as that of the specified value in this standard.
IS 14458 (Part 5) : 2018
Indian Standard
RETAINING WALL FOR HILL AREAS — GUIDELINES
PART 5 CONSTRUCTION OF CEMENT STONE MASONRY WALLS
1
IS 14458 (Part 5) : 2018
UNSTABLE
FIG. 2 TYPICAL SKETCH OF RETAINING WALL WITH BACKFILL MATERIAL AND THE TOP LAYER
at joints. However, the available boulders can be shaped filter for a thickness of 700 mm to 800 mm. The inverted
into rectangular pattern and used. There shall be no filter shall have materials ranging in size from boulder
dumping of stones. Stones shall be hand placed tight to sand, with boulders placed immediately behind the
with proper bonding of cement around the stones. The wall and sand towards the hill side. The filter should
masonry stones used for construction shall have a consist of three zones: about 300 mm thick layer of
maximum size of 300 mm × 300 mm × 200 mm with small boulders (30 mm to 40 mm in size) close to the
a weight of about 40 kg and the minimum size of wall, 200 mm to 250 mm thick gravel fill (5 mm
100 mm × 100 mm × 200 mm with a weight of about to 10 mm in size) in the middle and 200 mm to 250 mm
5 kg. The largest dimension, that is, the length shall be thick coarse sand (2 mm to 4 mm in size) further inside.
placed across the length of the retaining wall for The material of inverted filter should be properly
maximum stability. The stones may be placed row wise packed behind the retaining wall in layers of 200 mm
with suitable bonding of cement mortar. Where the to 300 mm to cover the whole height, leaving about
stones are not available, cement masonry blocks of 500 mm to 700 mm space towards the top of the
suitable strength may be used for construction. retaining wall. On the top close to the surface, natural
soil or impervious clayey soil shall be placed and
7 PLACEMENT OF BACKFILL compacted well to prevent ingress of surface water
The backfill behind the wall shall consist of inverted directly into the filter. The surface material should be
3
IS 14458 (Part 5) : 2018
filled in such a way that it forms a minimum angle of maximum pressure indicated in the standard design.
10° or more. Grass or other green plantation may be The standard design of cement stone masonry wall for
grown on the top slope surface. The inverted filter is varying heights of 3 m, 6 m and 8 m is given in Table 1.
essentially required as it will help to drain out the It is generally safe to construct this type of walls up to
subsurface water. A typical sketch of retaining wall with 5.0 m, although in exceptional conditions, these may
backfill material and the top layer is shown in Fig. 2. be constructed up to 8.0 m. This standard design is
based on Coloumb’s Wedge analysis. The wall design
8 DRAINAGE shall provide for inclined front face and near vertical
The seepage water collected in the backfill has to be back face. It should be ensured that the backfill is of
drained out safely without causing excessive pore good quality following the specifications as indicated
pressure, which may destabilize the retaining wall. In in 7.
order to efficiently drain out the sub-surface water, a The foundation pressure must not exceed the safe bearing
series of weep holes of 80 mm - 100 mm size should capacity of foundation material. The specifications as
be provided in the wall at a spacing of 1.0 m - 1.5 m c/c indicated for different heights of retaining walls shall
and in a staggered pattern. The weep holes should be vary under the following conditions:
inclined down towards the valley at gradients of about
10° to 15°. Preferably, the weep holes should be made a) The backfill is fair or poor and the
out of PVC/GI pipes and inserted in between the stones specifications do not follow as indicated in 7.
during construction of the retaining wall. The bottom b) Free drainage can be achieved following the
most row should be located as close as possible to the guidelines indicated in 8. If the specifications
ground and not more than100 mm above the ground. as indicated in 8 are not followed, it may lead
The PVC pipes shall end exactly at the back surface of to build-up of pore water pressures at the back
retaining walls and shall not extend into the backfill. of retaining wall leading to change in the
The inner free end of the pipe shall be provided with specifications of design of retaining walls.
two layers of wire meshes, coarse and fine wire meshes,
The above dimensions also include the effect of seismic
to prevent movement of backfill material in to the pipe.
forces.
9 TOE PROTECTION Table 1 Standard Design of Cement Stone
If the retaining wall is located on the hill side end of Masonry Retaining Walls
road/terrace, a 500 mm size curved toe drain (see Fig. 2) (Clause 10.1)
shall be provided with a gradient of 1 (vertical) : 20 Sl Height Top Width Base Width
(horizontal). This will help to collect the drained water No. m m m
through the pipe and safely dispose it off. However, if (1) (2) (3) (4)
the wall is located on the valley side end of the terrace i) 3 0.50 1.95-2.10
or no toe drain is provided, the toe of retaining wall ii) 6 0.65 3.90-4.20
should be suitably protected following anyone of the iii) 8 0.65 5.20-5.60
methods suggested in Fig. 3, as otherwise, the toe NOTE — The backfill should consist of sandy gravel type of
erosion may lead to destabilization of the wall. materials having good drainage properties.
4
IS 14458 (Part 5) : 2018
5
IS 14458 (Part 5) : 2018
ANNEX A
(Foreword)
COMMITTEE COMPOSITION
Hill Area Development Engineering Sectional Committee, CED 56
Organization Representative(s)
Indian Institute of Technology Roorkee, Roorkee DR R. ANBALAGAN (Chairman)
Advance Technology & Engineering Services, New Delhi DR V. M. SHARMA
Building Materials & Technology Promotion Council, New Delhi SHRI J. K. PRASAD
Central Public Works Department, Shillong SHRI SHEO PRASAD S INGH
SHRI PREM CHAND MATHUR (Alternate)
Central Soil & Materials Research Station, New Delhi DR MANISH GUPTA
SHRI HARI DEV (Alternate)
Central Water Commission, New Delhi DIRECTOR HCD (NW & S)
DIRECTOR (SARDAR SAROVAR) (Alternate)
CSIR-Central Building Research Institute, Roorkee SHRI ASHOK KUMAR
SHRI AJAY CHAURASIA (Alternate)
CSIR-Central Institute of Mining & Fuel Research, Roorkee DR R. K. G OEL
SHRI ANIL SWARUP (Alternate)
CSIR - Central Road Research Institute, New Delhi DR K ISHOR KUMAR
DR P ANKAJ GUPTA (Alternate)
Defence Terrain Research Laboratory (DRDO), New Delhi DR L. K. S INHA
Department of Science & Technology, New Delhi SHRI BHOOP SINGH
Directorate General of Border Roads, New Delhi BRIG V. S. K ATTARYA
BRIG R. K. SHARMA (Alternate)
G. B. Pant Institute of Himalayan Environment Development, Almora SHRI KIREET KUMAR
Geological Survey of India, Kolkata SHRI M. S. BODAS
Dr T. B. Goshal (Alternate)
Housing & Urban Development Corporation Ltd, New Delhi CHAIRMAN AND M ANAGING DIRECTOR
Indian Institute of Remote Sensing, Dehradun DR P. K. CHAMPATI RAY
DR AJANTA GOSWAMI (Alternate )
Indian Institute of Technology Roorkee, Roorkee DR M. N. VILADKAR
DR M AHENDRA S INGH (Alternate)
Indian Metrological Department, New Delhi DR O. P. MISHRA
DR H. S. MANDAL (Alternate)
Konkan Railway Corporation, Mumbai SHRI RAJESH AGARWAL
Maccaferri Environment Solution Pvt Ltd, Gurugram SHRIMATI M INI KORULLA
National Highway Authority of India, New Delhi DR RAM K UMAR
SHRI R. P. SINGH (Alternate)
National Hydroelectric Power Corporation Ltd, Hepali SHRI S. MURUGAPPAN
National Institute of Hydrology, Roorkee SHRI R. D. SINGH
DR SUDHIR KUMAR (Alternate)
Rail Vikas Nigam Ltd, Rishikesh SHRI SUMIT JAIN
SJVN Ltd, Shimla SHRI A. K. C HADHA (Alternate)
Snow Avalanche Study and Establishment (DRDO), Chandigarh COL P. MATHUR
THDC India Ltd, Rishikesh SHRI T. S. ROUTELA
Wadia Institute of Himalayan Geology, Dehradun DR S. K. BARTARYA
BIS Directorate General SHRI S ANJAY PANT, Head and Scientist ‘F’ (Civil Engg)
[Representating Director General (Ex-officio)]
Member Secretary
SHRI M ANOJ KUMAR RAJAK
Scientist ‘C’ (Civil Engg), BIS
6
Bureau of Indian Standards
BIS is a statutory institution established under the Bureau of Indian Standards Act, 2016 to promote
harmonious development of the activities of standardization, marking and quality certification of goods
and attending to connected matters in the country.
Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of BIS. This does not preclude the free use, in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations.
Enquiries relating to copyright be addressed to the Director (Publications), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewed
periodically; a standard along with amendments is reaffirmed when such review indicates that no changes are
needed; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standards
should ascertain that they are in possession of the latest amendments or edition by referring to the latest issue of
‘BIS Catalogue’ and ‘Standards : Monthly Additions’.
This Indian Standard has been developed from Doc No.: CED 56 (10719).