Professional Documents
Culture Documents
Retaining wall
Is a structure that holds or retains soil behind it. There are many types of materials that can be
used to create retaining walls like concrete blocks, poured concrete, treated timber, rocks or boulders.
To retain soil at a slope which is greater than it would naturally assume, usually at vertical or near
vertical position.
Are constructed with plain concrete or stone masonry. They depend for stability on their own
weight and any soil resting on masonry. This type of construction is not economical for high walls. In
many cases, small amount of steel maybe used for the construction of gravity walls, thereby minimizing
the size of the wall sections. Such walls are generally referred to as semigravity walls.
Resist external forces by the combined action of self weight, weight of soil above footing and
the flexural resistance of the wall components.
Is the most common type if retaining structure and is generally economical for heights up to
about 8m. The stucture consists of vertical stem, and a base slab made up of two distinct regions, a heel
slab and a toe slab.
Are similar to cantiliver walls. At regular intervals, however they have thin vertical concrete slabs
knon as counterforts that tie the wall and base slab together. Purpose is to reduce the shear and the
bending moments.
An Engineer must assume some of their dimensions in designing retaining walls, such
assumptions allow the engineer to check trial sections of the walls for stability.
Note:
Top of the stem retaining wall - >0.3m(12in.)
Depth to the bottom of base slab(D)- minimum of 0.6m(2ft.)
Counterfort slabs about 0.3m(12 in.)
Spaced at the center-to-center distance of 0.3H to 0.7H.
To use this theories in design , an Engineer must make several simple assumptions.
There are two Earth Pressure theories by Columb and Rankine. These two theories are still in
use in their original form and in som emodified forms to calculate the earth pressure.
Rankine active pressure is acting along a vertical plane AB drawn through the heel of the
structure. Pp – Rankine passive pressure.
The factor of safety against overturning about the toe – that is, about point C;
Check for sliding along Base
Indicates that the shear strength of the soil immediately below the base slab;
The sum of vertical forces acting on the base slab is ∑ V, and the horizontal force Ph is Pa
cos a. Let be the Resultant force.
Let the line of action of the resultant R intersect the base slab at E. Then the distance;
For maximum and minimum pressures, the value of y equals B/2 gives;
The factor of safety against bearing capacity failure can be determined;
Example:
Solution
A retaining wall may be constructed with one or more of the ff. joints;
1. Construction Joints
-are vertical and horizontal joints that are placed between two successive pours of
concrete.
2. Contraction Joints
– are vertical joints (grooves) placed in the face of a wall that allow the concrete to
shrink without noticeable harm; the grooves maybe about 6 to 8 mm wide and 12 to
16mm deep.
3. Expansion Joints
– vertical expansion joint from the base to the top of the wall may also be used. Maybe
filled with flexible joint fillers.
where:
F – filter
B – base material
Reinforcement materials such as metallic strips, geotextiles, and geo grids are now being used to
reinforce the backfill of retaining wall.
Soil Reinforcement
The used of reinforcement earth is a recent development in the design and construction
of foundation and earth- retaining structures. Reinforced earth is construction material
made from soil that has been strengthened by tensile elements such as metal rods or
strips, non-biodegradable fabrics, geo grids.
Metal strips - the average rate of corrosion of galvanized steel strips varies bet. 0.025
and 0.050 mm/yr. So in the actual design of reinforcement allowance must be made for
rate of corrosion. Thus,
1. Drainage 3. Separation
2. Filtration 4. Reinforcement
Geo grids – are high-modulus polymer materials, such as polypropylene and
polyethylene, and are prepared by tensile drawing. Its major function is reinforcement.
Two types of geo grids:
a) Uniaxial
b) Biaxial
Where:
Tie force
The tie force per unit length of the wall developed at any depth z is;
T = active earth pressure at depth z x area of the wall to be supported by the tie
Internal Stability
Step 1. Determine the active pressure distribution on the wall
Step 2. Select a geotextile fabric with an allowable strength of σG (lb/ft or Kn/m)
Step 3. Determine the vertical spacing of the layers at any depth z
Syep4. Determine the length of each layer of geotextile
Step 5 Determine the lap length; the minimum lap length should be 1m(3ft).
External Stability
Step 6. Check the factors of safety against overturning, sliding, and bearing
capacity failure
Example:
A geotextile-reinforced retaining wall 16ft. high is shown in the figure. For the granular backfill,
y1 = 110lb/ftᶟ and ᶲ’1 = 36°. For the geotextile σ = 80 lb/in. For the design of the wall, determine Sv, L,
G
and II.
Solution
Determination of Sv
Determination of L
Determination of lI
a) Wooden sheet piles – used only for temporary, light structures that are above the water table.
b) Precast concrete sheet piles – are heavy and are designed with reinforcement to withstand the
permanent stresses. About 500 to 800mm wide and 150 to 250mm thick.
c) Steel sheet piles – in the U.S. are about 10 to 13mm thick.
Construction Methods
The sheet pile maybe driven into the ground and then the backfill placed on the land side.
a) Cantilever
b) Anchored
a) Backfilled structure
b) Dredge structure
depth L1 below the top of the wall. Let the effective friction of the sand be ᶲ’. The intensity of
active pressure at a depth z = L1 is
Solution
a.)
b.)
c.)
In the absence of the water table, the net pressure diagram on the cantilever sheet pile
wall shown in the figure, which is a modified version.
When the height of the backfill material behind a cantilever sheet-pile wall
exceeds about 6m, trying the wall near the top to anchor plates, anchor walls, becomes
more economical.
The tie rod connecting the sheet pile and the anchor is located at a depth below
the top of the sheet-pile wall.
Depth of Penetration
Anchor Force
Maximum Moment
Example:
For the anchored sheet pile wall shown in the figure, determine the following. Use the CPD
method; assume that C= 0.68 and R= 0.6.
(a) D
(b) F
(c) Mmax
Solution
a)
b)
c)
Anchors
Anchor plates and beams are generally made of cast concrete blocks. The anchors are attached
to the sheet pile by tie-rods. A wale placed at the front or back face of a sheet pile for the purpose of
conveniently attaching the tie-rod to the wall. To protect the tie rod from corrosion, it is generally
coated with paint or asphaltic materials.
Mackenzie (1995) and Tschebotarioff (1973) identified the nature of variation of the
ultimate resistance of strip anchors and beams as a function of H, h and c (undrained cohesion
based on ᶲ= 0) in a non-dimensional form based on laboratory model results. And in the form of a
non-dimensional plot can be used to estimate the ultimate resistance of anchor plates in saturated
clay.
Braced Cuts
An excavation supported by suitable bracing system are called braced cuts.
Design of braced excavation means selection of wales, struts, sheet piles and soldier beams
to support the excavation without any collapse by estimating the lateral earth pressure to which
the braced cuts will be subjected to.
Shallow cuts
Deep cuts
Open cuts
Closed cuts
Temporary cuts
Permanent cuts
In shallow cuts depth of excavation is less than 6m. The bracing of this type of cut
generally standard. In deep cuts depth of excavation is more than 6m and the design of
suitable bracings (supporting system) necessary to safe guard the cut or trench against
collapse.
Vertical Timber Sheeting – consisting of planks about 8 to 10 cm thick driven around the
boundary of the proposed excavation to some depth below the base of excavation. Are
economical up to a depth of 4 to 6 m.
Steel Sheet Pile – in this method, are driven along the sides of the proposed excavation.
As the soil is excavated from the enclosure, wales and struts are placed. As the
excavation progress, another sets of whales and struts is inserted.
Soldier Beams - are H-piles which are driven at a spacing of 1.5 to 2.5 m around the
boundary of the proposed excavation. As the excavation proceeds, horizontal timber
planks called laggings are placed between the soldier beams. When the excavation
advances to a suitable depth, wales and struts are inserted .
Tie Backs - In this method, no bracing in the form of struts or inclined rakers is provided.
Therefore, there is no hindrance to the construction activity to be carried out inside the
excavated area. The tie back is a rod or a cable connected to the sheeting or lagging on
one side and anchored into soil (or rock) outside the excavation area. Inclined holes are
drilled into the soil (or rock), and the hole is concreted.
Use of Slurry Trenches - An alternative to use of sheeting and bracing system, which is
being increasingly used these days, is the construction of slurry trenches around the
area to be excavated and is kept filled with heavy, viscous slurry of a bentonite clay-
water mixture.
Braced cuts in clays may become unstable as a result of having of the bottom of
excavation.
For excavations of limited length L, the factor of safety can be modified to;
In homogeneous clay, if FS becomes less than 1.5, the sheet pile is driven deeper.
The force p per unit length of the buried sheet pile may be expressed as;
and
Example:
Assume that the length of the cut is 25 m and a hard stratum is located at a depth of 4 m below
the bottom of the cut. Calculate the factor of safety against bottom heave.
Solution
So;
Stability of the Bottom of a cut in Sand
DEWATERING
• A simple answer would be the process of removing water from sludge (suspension of solid
matter in liquid).
• Dewatering is the process of natural, chemical, or mechanical removal of water from sludge,
thereby reducing it to a damp solid with the lowest level of moisture attainable.
The separation of solids from fluids (dewatering) is one of the important subjects in the
field of mineral dressing
• Water purification
Mechanical separation of solids from liquids is accomplished by one of two general procedures:
• Thickening.
• settling
• Filtration
THICKENING:
• Flocculation of the minute solid particles so as to form aggregators flocs of many particles.
• Exudation of water from the settled flocs, under the influence of pulp pressure.
• Exudation of water from the settled and naturally exuded flocs by application of outside
pressure or suction
SLIME SETTLING ZONE IN DORR THICKENER.
DORR THICKNER:
• Although less expensive per square foot of settling area they are
FILTRATION:
• Filtration is that separation of finely divided solid particles from a fluid which is accomplished
by driving the pulp to a membrane or septum, porous to the fluid but impervious to the solid, through
which the fluid passes, and by the removal of the solid cake from the septum.
MECHANISM OF FILTRATION:
• The simplest type of filter consists of a tube of small bore through which
the fluid is sucked while the solid particles accumulate at the entrance. As the
device is operated, solids at first pass through the tube, but they quickly arch or
bridge across the opening, allowing only clear liquid to pass.
RATE OF FILTRATION:
• The filtering area.
• The average cross section of the pores within the filter cake
TYPES OF FILTERS:
• Pressure type: pressure is applied to push the liquid through the filter bed. (for
hydrometallurgical work in which interest centers on the filtrate, as in cyanidation.) eg. Hardinge
filter thickener.
• Suction type: suction is applied to pull the liquid through the filter bed. (used in chemical
laboratories, for mineral dressing in which interest centers on the cake.) eg. Genter thickener.