You are on page 1of 11

Section 10 - Drawings

Section - 10

Drawings

NO OF
S.NO. DESCRIPTION DRAWING NO
SHEETS

LS OF “D” 1 CHANNEL CUM ROAD, 0+000 TO


01. IWWRMP/ME/CH-01 01
1+200 & ISSUE TREE

CSS OF ‘D’ 1CHANNEL CUM ROAD FROM 0+000


02. IWWRMP/ME/CH-02 01
TO 0+150

CSS OF ‘D’ 1CHANNEL CUM ROAD FROM 0+180


03. IWWRMP/ME/CH-03 01
TO 0+360

CSS OF ‘D’ 1CHANNEL CUM ROAD FROM 0+390


04. IWWRMP/ME/CH-04 01
TO 0+600

CSS OF ‘D’ 1CHANNEL CUM ROAD FROM 0+630


05. IWWRMP/ME/CH-05 01
TO 0+690

CONSTRUCTION OF ROAD CROSSING


06. IWWRMP/ME/CH-06 01
STRUCTURE OF ‘D’ 1 CHANNEL CUM ROAD

CONSTRUCTION OF CONCRETE LINING


CHANNEL WITH DROP FROM 0+000 TO 0+030,
07. 0+036 TO 0+105, 0+112 TO 0+226, 0+253 TO 0+260, IWWRMP/ME/CH-07 01
0+267.5 TO 0+690 OF ‘D’ 1 CHANNEL OF LB
MAIN CHANNEL
CONSTRUCTION OF 300mm DIA FARM TURN
08. OUT STRUCTURE AT 0+015m, 0+630m & 0+960m IWWRMP/ME/CH-08 01
OF ‘D’ 1 CHANNEL

CONSTRUCTION OF 225mm DIA 1.83m LONG


09. RCC PIPE OUTLET AT 0+330m & 0+890m OF ‘D’ IWWRMP/ME/CH-09 01
1 CHANNEL

10-1
Section 10 - Drawings

10-2