Total fuel consumed during the week: Diesel = 120L Petrol = 160L
Cummulative fuel consumed in 2024: Diesel = 2555L Petrol = 2900L
Notes:
Vehicle Fuel
AAP 0855 170L Petrol
nt
e overhaul
Completed 100%
Completed 100%
Completed 100%
On hold 0%
0
COMMENTS
nts
Additional Comments
# Continuous rains affected our progress.
# Handholes are out of stock and they are urgently required.
# Recruiting casual workers is not an easy task these days, it takes a lot of effort to find them.
Challenges
# Continuous rains and shortage of diesel affecting our progress.
# Handholes are out of stock and they are urgently required.
# Recruiting casual workers is not an easy task these days, it takes a lot of effort to find them.
Lessons Learnt
ts
Rein-statement Total Costs
$ 12,000.00 $ 842,600.96
$ - $ 404,723.34
$ 12,000.00 $ 437,877.62
Projects Weekly Dash
Project Name: HARARE -OLD MAZOWE DIVERT
Scope: To divert backborne
Report Period: 27/03/2024 -02/04/2024
Week Number: 4
Deployed by: NYASHA AND NAGO
Additional comments
Lomagundi sections all works completed expect stay installation,Carriers already done change over
now working at oOld Mazowe road section,with a total distance of 13km
Challenges
Unavailability of PPE is the other challenge,and casuals are at Risk of injuries.
d Costs
Enginnering Rein-statement Total Costs
cost
728.94 0 ###
$ 39,981.44
$ 728.94 $ 89,177.83
er
Projects Weekly D
Project Name: STROWGER EQUIPMENT RECOVERIES (51025
Scope: To recover Strowger Equipment at Norton Exchange
Report Period: 27/03/2024 -02/04/2024
Week Number: 6
Deployed by: Mutyoraringa , Zambuko
Total
Weekly Total Done Total Planned %age
Activities Target this week Cum. Done Activity complete
Norton Exchange
Strowger equipment 0 0 8 8 100%
Removing cables (m) 0 0 600 600 100%
Loading trash 0 0 1 1 100%
Clearance 4 3 3 3 75%
Overall Project Completion 94%
Projects Weekly Dashboard
change
Challenges
Additional comments
# Some of the cables amoungst the ones to be removed are currenlty working and we are working with
extreme care to avoid network disturbances .
Lessons learnt
Rein- Total Costs
statement
$ - $ 6,232.00
$ - $ 3,125.00
$ - $ 3,107.00
h
Projects Weekly Dash
Project Name: RGM AIRPORT ASSET NUMBER: 5104146
Scope: PROVIDE GPON AND LEASED CIRCUIT IN 12 RGM IT ROOMS
Report Period: 27/03/2024 -02/04/2024
Week Number: 3
Deployed by: Mhande
# completed on 26/03/2024
# PATs in progress
Additional Comments
#Due to the fact that RGM airport is a very sensitive area in terms of security clearence implentation is slowed
Challenges
#security clearence everyday at the RGM airport slows progress
# borrowing transport from garage everyday to go to to work hindering progress
Lessorn learnt
0
Total Costs
$ 48,456.85
$ 8,733.94
$ 39,722.91
Projects Weekly D
Asset Number 5104153
Project Name: Byo- Vic Falls -Kazungula Optic High Capacity Transmission Project
Scope: To deploy 10 km milestones
Report Period: 27/03/2024 to 2/04/24
Week Number: 42
Deployed by: Contractor (DP Telecoms)
Team leader : E Madzimure
DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 100 0%
Concrete encasements 0 0 0 250 0%
Bridge attachement - river crossing 0 0 0 1 0%
Fiber blowing 0 0 0 10000 0%
H/hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 1 0%
End to End Testing 0 0 0 1 0%
Milestone 4: 30-40km 47%
To deploy 10 km 5th milestone
Route Marking 0 0 10000 10000 100%
Brush clearing 0 0 3737 3737 100%
Pilot hole /search hole pits 0 0 2 2 100%
Trenching 0 0 10000 10000 100%
HDPE Duct laying Blue 0 0 10000 10000 100%
HDPE Duct laying green 0 0 10000 10000 100%
Warning tape laying backfilling 0 0 10000 10000 100%
DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 100 0%
Concrete encasements 0 0 0 500 0%
Bridge attachement - river crossing 0 0 0 100 0%
Fiber blowing 0 0 0 10000 0%
H/hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 1 0%
End to End Testing 0 0 0 1 0%
Milestone 5: 40-50km 47%
Additional Comments
# 0- 100km milestone 80 km cumulative trenched and full backfilled out of 100 km.
Challenges
Leasons Learnt
# As the project progresses, an issue log book becomes increasingly necessary
# It is critical to keep track of all risks as the project progresses.
Procurement
# contractor
Issues logged
0-50km milestone
# Warning tape was not booked to Telone stores
# Joint markers,,fibre and HDPE duct mid coupling rem for the 50km milestone.
# 3 Bridge attachements cumulative 169 m
50-100km milestone
#1200m of rocky area trenched,portions with snages : done.
# Soil importation for a stretch of 450m done.
# river crossing at 74 km done
#rock breaking to do at 86km and 89km total of 13m. Done
Additional Comments
Challenges
Leasons Learnt
Additional Comments
# a GPON card is required urgently
Only 6 GPON ports are available out of 10 ports required to avail a capacity of 624 clients for FDH 02.
Challenges
# unavailability of GPON cards
# unavailabilty of reliable splicing machines.
# 7 way microducts are out of stock .
# rains affects project activities
# lack of enough resources is affecting the project plan and might risk missing targets
Lessons Learnt
res.
Projects Weekly Da
Project Name: Mahatshula Ftth Asset Number 5104073
Scope: To deploy GPON FTTH capacity of 2760 households.
Report Period: 07/02/2024 - 13/02/2024
Week Number: 38
Deployed by: Mutyoraringa, Chasakara
useholds.
Additional comments
# Unavailability of splicing machines to use during project implementaion is affecting our progress as we are
borrowing machines from other departments whom most times took their machines before we are done splicing.
# We kindly request the department to take a look into this issue as it is dragging our progress to a greater extend.
# We also require a GPON card at Killarney RLU
Challenges
# Unavailability fuel (desiel) for material delivery to site has hindered our progress to a greater extend.We are slowly
getting behind planned schedule since some activities planned cannot be executed due to unavailablity of materials
sts
Reinstatements Total Costs
$ 81,000.00 $ 703,180.31
$ - $ 421,801.43
$ 81,000.00 $ 281,378.88
as we are
done splicing.
reater extend.
Additional Comments
Challenges
Leasons Learnt
Projects Weekly Dashboard
Project Name: BYO-V/FALLS LAST MILE BCS PROJECT ASSET
Scope: Implementation of backhaul link from BCS POPs to TelOne Exchanges VIC
Report Period: 18/07/2023 TO 25/07/2022
Week Number: 1
Deployed by: MHANDE FARAI
Pl
# splicing of 2 cores at exchange ,2 cores a
cts Weekly Dashboard
Additional Comments
Challenges
Lessorn learnt
Projects W
Project Name: IZAYI PARK FTTH (1706466)
Scope: To deploy a GPoN network for a capacity of 780 households
Report Period: 20/03/2024 -26/03/2024
Week Number: 26
Deployed by: M.MBOFANA
y of 780 households
I
Duration Start date Finish date
Planned 43
Actual 132 1/15/2018
Additional Comments
Challenges
Leasons Learnt
s
Rein-statement Total Costs
$ 3,750.00 $ 245,393.72
$ - $ 161,745.18
$ 3,750.00 $ 83,648.54
Project Name: GLENVIEW LTE BACKHAULING (510
Scope: To deploy fibre backhauling for LTE on 3 Sites
Report Period: 06/02/2024 - 13/02/2024
Week Number: 8
Deployed by: DZUDA , USHE
45
Additional Comments
Challenges
or vehicle shortages
ng machine sharing
Leasons Learnt
asking and teamwork ensures effective and efficient implementation of projects.
Projects Weekly Da
Project Name: SOUTHLEA PARK FTTH 5104079
Scope: To deploy GPON FTTH capacity of 828 households.
Report Period: 31/01/2024 - 06/02/2024
Week Number: 20
Deployed by: NYASHA AND NAGO
mpleted 02/02/2024
Additional Comments
Challenges
Leasons Learnt
mitment and perpetual supervision yeild positive results.
Rein- Total Costs
statement
$0 $ 140,382.93
$ - $ 145,859.71
$ - $ (5,476.78)
en another GPON card
Projects Weekly Dash
Project Name: HILLSIDE FTTH BULAWAYO 1706976
Scope: To deploy GPON FTTH capacity of 1536 households.
Report Period: 12/04/23 to 17/04/23
Week Number: 25
Deployed by: MADZIMURE & JECHE
Additional Comments
Leasons Learnt
Total Costs
$ 508,373.31
$ 350,844.15
$ 157,529.16