Projects Vehicle Establishment

Total number of vehicles: 14


Vehicles on the road : 6
Vehicles in the garage : 6
Vehicles borrowed by other departments: 2
Vehicles borrowed from other departments: 0

Total fuel consumed during the week: Diesel = 120L Petrol = 160L
Cummulative fuel consumed in 2024: Diesel = 2555L Petrol = 2900L

Vehicles on the road Vehicles in the garage


ADR 1520 - Harare - Old Mazowe Rd Divert ADA 4687 - Repairs - Engine overhaul
AGE 4688 - Bulawayo - Vic Falls Backbone AEF 8653 - Repairs - Engine overhaul
ACI 8485 - Izayi Park, Zvishavane AEK 6598 - Repairs - Engine overhaul
AGH 4150 - Belvedere ADA 4969 - Repairs - Engine overhaul
AAP 0855 - Harare - Old Mazowe Rd Divert AEL 1868 - Corporates
ACO 2948 - Norton Exchange Strowger Recovery
ADR 1680 - Repairs

Notes:

# ADL7054 swapped with ACI 8485 by Transport


# ADR 1848 has been withdrawn due to damage beyond repair.

Exceptions: All vehicles that consumed more fuel this week

Vehicle Fuel
AAP 0855 170L Petrol
nt

Vehicles borrowed by other Vehicles borrowed from other


departments departments
ADR 1518 - Corporates ADR 1868 - Harare - Old Mazowe Rd Divert
AAI 9035 - Transport

e overhaul

Reasons for exceeding


Harare - Old Mazowe Road Divert (including weekends)
Projects Weekly Dash
DURATION
Item Actual
PROJECT NAME MILESTONES Planned
No. Days
Target
passed

Milestone 1 Feeder U/G Network

Milestone 2 UG FDH 01 U/G Network

Mahatshula Ftth Asset Milestone 3 U/G FDH 02 U/G Network


Number 5104073
1 Milestone 4 U/G FDH 03 U/G Network

Milestone 5 U/G FDH 05 U/G Network

Milestone 6 U/G FDB 01 & FDB 02 U/G Network


Overall Project Progress Mahatshula FTTH 84 176
Milestone 1 Feeder
Milestone 2 FDH 01
Milestone 3 FDH 02
BELVEDERE FTTH- Milestone 4 FDH 03
2 5104075 Milestone 5 FDH 04
Milestone 6 FDH 05
Milestone 7 FDH 06
Milestone 8: ODN FDH 07 O/H Network
Overall Project Progress Belvedere FTTH 270 220
Milestone 1 Feeder
SOUTHLEA PARK FTTH
5104079 Milestone 2 FDH 01
3
Milestone 3 FDH 02
Overall Project Progress Southlea Park FTTH 60 111
Milestone 1: Feeder U/G Network
CHERUTOMBO & Milestone 2 FDH 01
RUSIKE PHASE 1 & 2 Milestone 3 FDH 02
4 FTTH- 5104175
Milestone 4 FDH 03
Milestone 5 FDH 04
Overall Project Progress Cherutombo &Rusike FTTH 210 85
Overall Projects Target Status
jects Weekly Dashboard 2024
STATUS COSTS
Planned Actual
Planned Total Actual Total
Progress Status %age %age
Costs Incured Costs
Complete Complete

Completed 100%

Completed 100%

Completed 100%

Completed 100% $703,180.31 $421,801.43


In progress 83%

On hold 0%

In progress 210% 81%


In progress 91%
In progress 92%
Partially completed 92%
Partially completed 92%
On hold 10% $842,600.96 $404,723.34
On hold 0%
On hold 0%
On hold 0%
On hold 81% 47%
In progress 92%
Completed 100%
$140,382.93 $145,859.71
Completed 100%
Completed 185% 97%
In progress 62%
On hold 0%
Completed 100%
$499,501.15 $213,796.68
Completed 100%
On hold 0%
On hold 40% 52%
Behind Schedule 129% 69% $2,185,665.35 $1,186,181.16

0
COMMENTS

# FDH 01 availed 39 out of 55 NAPs.


Capacity of 468 was handed over on
27/07/2023. #
FDH 01 remaining 16 NAPs were done
and availe a capacity of 192 to complete
a full capacity of 660 for this FDH.
# FDH
02 availed 54 Naps out of Naps #
Capacity of 648 was availed and
handover to be done 1/11/23

# FDH 02 and FDH 03 completed and


capacity availed. Both FDH require
handhole installations.
# FDH 01 road and driveway crossings
in progress.

# Feeder cable requires handholes.


#FDH 01 and 02 completed 02/02/2024

# FDH 02 and 03 completed 02/02/2024


Projects Weekly Da
Project Name: BELVEDERE FTTH-5104075
Scope: To provide 3660 GPON and 252 P2P clients
Report Period: 27/03/2024 -02/04/2024
Week Number: 44
Deployed by: GIDI, JECHE

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Feeder U/G Network
Location of manholes 0 0 33 33 100%
Duct clearing 0 0 9500 9500 100%
7 way Microduct pulling (in existing ducts) 0 0 9500 9500 100%
Pedestal construction 0 0 7 7 100%
ODF installation 0 0 1 1 100%
Trenching 0 0 600 600 100%
7 way microduct laying and backfilling 0 0 600 600 100%
Driveway crossing and re-instatements. 0 0 15 15 100%
Fiber blowing (96 core) 0 0 10010 10100 99%
Thrust boring 0 0 0 1 0%
Feeder cable splicing at FDHs 0 0 68 84 81%
joint splicing 0 0 1 1 100%
Fibre terminations at ODF 0 0 336 336 100%
Fibre Testing 0 0 336 336 100%
Milestone 1 Feeder 91%
ODN FDH 01 O/H Network
Trenching 0 0 4800 4800 100%
handhole installation 0 0 0 18 0%
Driveway crossing 0 0 76 76 100%
Thrust boring 0 0 28 28 100%
7 way microduct laying and backfilling 0 0 4800 4800 100%
Pole hole marking and digging 0 0 34 34 100%
Pole planting 0 0 34 34 100%
cable storage fitting 0 0 34 34 100%
fibre cable blowing 0 0 8350 8350 100%
NAP installation 0 0 35 35 100%
NAP splicing 0 0 528 528 100%
NAP testing and faulting. 0 0 35 35 100%
Milestone 2 FDH 01 92%
ODN FDH 02 O/H Network
Trenching 0 0 5700 5700 100%
handhole installation 0 0 0 6 0%
Driveway crossing 0 0 160 160 100%
Thrust boring 0 0 18 18 100%
7 way microduct laying and backfilling 0 0 5700 5700 100%
Pole hole marking and digging 0 0 36 36 100%
Pole planting 0 0 36 36 100%
cable storage fitting 0 0 35 35 100%
fibre cable blowing 0 0 12990 12990 100%
FDH Splicing 0 0 480 480 100%
NAP installation 0 0 37 37 100%
NAP Splicing 0 0 37 37 100%
NAP testing and faulting. 0 0 37 37 100%
Milestone 3 FDH 02 92%
ODN FDH 03 O/H Network
Trenching 0 0 8200 8200 100%
handhole installation 0 0 0 1 0%
Driveway crossing 0 0 224 224 100%
Thrust boring 0 0 28 28 100%
7 way microduct laying and backfilling 0 0 9120 9120 100%
Pole hole marking and digging 0 0 52 52 100%
Pole planting 0 0 52 52 100%
cable storage fitting 0 0 52 52 100%
fibre cable blowing ( 96 micro) 0 0 11000 11000 100%
FDH Splicing 0 0 648 648 100%
NAP installation 0 0 52 52 100%
NAP splicing 0 0 54 54 100%
NAP testing and faulting. 0 0 54 54 100%
Milestone 4 FDH 03 92%
ODN FDH 04 O/H Network
Trenching 250 250 1670 10200 16%
handhole installation 0 0 0 17 0%
Driveway crossing 4 4 43 320 13%
Thrust boring 2 2 17 47 36%
7 way microduct laying and backfilling 350 350 1450 10200 14%
Pole hole marking and digging 6 6 11 52 21%
Pole planting 6 6 11 52 21%
cable storage fitting 0 0 5 52 10%
fibre cable blowing 0 0 0 10300 0%
FDH Splicing 0 0 0 624 0%
NAP installation 0 0 0 52 0%
NAP splicing 0 0 0 52 0%
NAP testing and faulting. 0 0 0 52 0%
Milestone 5 FDH 04 10%
ODN FDH 05 O/H Network
Trenching 0 0 0 7400 0%
handhole installation 0 0 0 6 0%
Driveway crossing 0 0 0 258 0%
Thrust boring 0 0 0 46 0%
7 way microduct laying and backfilling 0 0 0 7400 0%
Pole hole marking and digging 0 0 0 43 0%
Pole planting 0 0 0 43 0%
cable storage fitting 0 0 0 43 0%
fibre cable blowing 0 0 0 7600 0%
NAP installation 0 0 0 43 0%
NAP splicing 0 0 0 43 0%
NAP testing and faulting. 0 0 0 43 0%
Milestone 6 FDH 05 0%
ODN FDH 06 O/H Network
Trenching 0 0 0 6400 0%
handhole installation 0 0 0 7 0%
Driveway crossing 0 0 0 168 0%
Thrust boring 0 0 0 41 0%
7 way microduct laying and backfilling 0 0 0 6400 0%
Pole hole marking and digging 0 0 0 28 0%
Pole planting 0 0 0 28 0%
cable storage fitting 0 0 0 28 0%
fibre cable blowing 0 0 0 6900 0%
NAP installation 0 0 0 28 0%
NAP splicing 0 0 0 28 0%
NAP testing and faulting. 0 0 0 28 0%
Milestone 7 FDH 06 0%
ODN FDH 07 O/H Network
Trenching 0 0 0 8500 0%
handhole installation 0 0 0 8 0%
Driveway crossing 0 0 0 264 0%
Thrust boring 0 0 0 38 0%
7 way microduct laying and backfilling 0 0 0 8500 0%
Pole hole marking and digging 0 0 0 44 0%
Pole planting 0 0 0 44 0%
cable storage fitting 0 0 0 44 0%
fibre cable blowing 0 0 0 8700 0%
NAP installation 0 0 0 44 0%
NAP splicing 0 0 0 44 0%
NAP testing and faulting. 0 0 0 44 0%
PATs and Hand-over 0 0 0 287 0%
Milestone 8: ODN FDH 07 O/H Network 0%
Overall Project Completion 47%
Projects Weekly Dashboard

nts

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone Labour T&S Transport

Planned Costs $ 483,335.56 $ 54,021.75 $ 110,806.48 $ 153,997.17 $ - $ 28,440.00


Actual Costs $ 301,102.84 $ - $ 37,212.00 $ 57,240.00 $ - 9,168.50
Variance $ 182,232.72 $ 54,021.75 $ 73,594.48 $ 96,757.17 $ - $ 19,271.50

Planned vs Actual Project time durations


Duration Start date Finish date
Planned 270 2/13/2023
Actual 220

This week's accomplishment


FDH 04
#250m trenched cum 1670m/10200m.
#6 planted cum 11/52
#2 road crossing done cum 17/47
#4 driveways thrust bored cum 43/320
# 350m microduct laid and backfilled 1450m/ 10200m.

Planned accomplishments next week


FDH 04
# Continue trenching 150m a day.
# microduct laying and backfilling.
# Continue digging Thrust pits, 6 pits a day
# Continue crossing roads and driveways.

Additional Comments
# Continuous rains affected our progress.
# Handholes are out of stock and they are urgently required.
# Recruiting casual workers is not an easy task these days, it takes a lot of effort to find them.
Challenges
# Continuous rains and shortage of diesel affecting our progress.
# Handholes are out of stock and they are urgently required.
# Recruiting casual workers is not an easy task these days, it takes a lot of effort to find them.

Lessons Learnt
ts
Rein-statement Total Costs

$ 12,000.00 $ 842,600.96
$ - $ 404,723.34
$ 12,000.00 $ 437,877.62
Projects Weekly Dash
Project Name: HARARE -OLD MAZOWE DIVERT
Scope: To divert backborne
Report Period: 27/03/2024 -02/04/2024
Week Number: 4
Deployed by: NYASHA AND NAGO

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
ODN FDH 01 O/H Network
Bush cutting 100 100 2000 2000 100%
Pole hole marking 43 43 224 224 100%
Pole hole digging 40 40 212 224 95%
Pole planting 40 40 212 224 95%
Mid-Span fittings 21 21 143 222 64%
Dead End fittings 38 38 172 318 54%
Cable Storage fittings 0 0 2 5 40%
Down lead clamp fitting 0 0 0 50 0%
Stay hole digging 0 0 10 72 14%
Stay wire making 0 0 10 72 14%
Stay set installation 0 0 0 72 0%
Cable Stringing(48cores) 2000 1500 9800 22000 45%
Cable stringing(24 cores) 0 0 4 10 40%
Joints splicing 0 0 0 36 0%
End to End Testing 0 0 0 36 0%
Milestone 2 FDH 01 44%
Overall Project Completion 22%
Projects Weekly Dashboard

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone T&S Transport
Labour
Planned Costs $ 88,038.74 $ 136.67 $ 14,551.77 19,663.15 0 6,040
Actual Costs $ 27,082.44 $ 6,040.00 $ 6,400.00 $ 459.00
Variance $ 60,956.30 $ 136.67 $ 8,511.77 $ 13,263.15 $ 5,581.00

Planned vs Actual Project time durations


Duration Start date Finish date
Planned 38 3/11/2024
Actual 20

This week accomplishments


212 poles planted out of 224 poles
59 accessories fitted cummulative 315 accossories
1,500m cable strung cummulative 9,800m out of 22,000m

Planned accomplishments next week


to complete pole planting,accessories fitting by Thursday
to continue with cable stringing,target of 6km

Additional comments
Lomagundi sections all works completed expect stay installation,Carriers already done change over
now working at oOld Mazowe road section,with a total distance of 13km

Challenges
Unavailability of PPE is the other challenge,and casuals are at Risk of injuries.
d Costs
Enginnering Rein-statement Total Costs
cost
728.94 0 ###
$ 39,981.44
$ 728.94 $ 89,177.83

er
Projects Weekly D
Project Name: STROWGER EQUIPMENT RECOVERIES (51025
Scope: To recover Strowger Equipment at Norton Exchange
Report Period: 27/03/2024 -02/04/2024
Week Number: 6
Deployed by: Mutyoraringa , Zambuko

Total
Weekly Total Done Total Planned %age
Activities Target this week Cum. Done Activity complete
Norton Exchange
Strowger equipment 0 0 8 8 100%
Removing cables (m) 0 0 600 600 100%
Loading trash 0 0 1 1 100%
Clearance 4 3 3 3 75%
Overall Project Completion 94%
Projects Weekly Dashboard

change

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone T&S Transport
Labour
Planned Costs $ - $ - $ - $ 4,312.00 $1,920.00
Actual Costs $ - $ 770.00 $ 540.00 $ - $ 1,815.00
Variance $ - $ (770.00) $ (540.00) $ 4,312.00 $105.00

Planned vs Actual Project time duration


Norton Duration Start date Finish date
Planned 14 11/3/2024 28/03/2024
Actual 14 11/3/2024

This week accomplishment


# 3 out of 4 loads of recovered material transported from Norton Exchange to Massa.

Planned accomplishments next week


# Complete cable removal and removal of trash from Exchange to Massa.

Challenges

Additional comments
# Some of the cables amoungst the ones to be removed are currenlty working and we are working with
extreme care to avoid network disturbances .

Lessons learnt
Rein- Total Costs
statement
$ - $ 6,232.00
$ - $ 3,125.00
$ - $ 3,107.00

h
Projects Weekly Dash
Project Name: RGM AIRPORT ASSET NUMBER: 5104146
Scope: PROVIDE GPON AND LEASED CIRCUIT IN 12 RGM IT ROOMS
Report Period: 27/03/2024 -02/04/2024
Week Number: 3
Deployed by: Mhande

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete

OPTICAL DISTRIBUTION NETWORK


Cable pulling 24microduct 0 0 3500 3600 100%
patch panel Preparation and installation 0 0 12 12 100%
ODF mounting 0 0 1 1 100%
patch panel and splitter splicing 0 0 288 144 100%
ODF preparation and splicing 0 0 144 144 100%
End to End Testing & FAULTING 50 50 50 50 100%
Milestone RGM AIRPORT 100%
Overall Project Completion
Projects Weekly Dashboard

UIT IN 12 RGM IT ROOMS

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone Labour T&S Transport Rein-
statement
Planned Costs $ 43,770.87 $ 1,148.33 $ 1,987.11 $ - $ 1,050.00
Actual Costs $ 5,464.44 $ - $ 320.00 $ 2,570.00 $ - $ 379.50 $ -
Variance $ 38,306.43 $ - $ 828.33 $ (582.89) $ - $ 670.50 $ -

This week's accomplishment

# completed on 26/03/2024
# PATs in progress

Planned accomplishments next week

# PAT's anad handover

Additional Comments

#Due to the fact that RGM airport is a very sensitive area in terms of security clearence implentation is slowed

Challenges
#security clearence everyday at the RGM airport slows progress
# borrowing transport from garage everyday to go to to work hindering progress
Lessorn learnt
0
Total Costs

$ 48,456.85
$ 8,733.94
$ 39,722.91
Projects Weekly D
Asset Number 5104153
Project Name: Byo- Vic Falls -Kazungula Optic High Capacity Transmission Project
Scope: To deploy 10 km milestones
Report Period: 27/03/2024 to 2/04/24
Week Number: 42
Deployed by: Contractor (DP Telecoms)
Team leader : E Madzimure

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
To deploy 10 km first milestone
Route Marking 0 0 10000 10000 100%
Brush clearing 0 0 6856 6856 100%
Pilot hole /search hole pits 0 0 20 20 100%
Trenching 0 0 10000 10000 100%
HDPE Duct laying Blue 0 0 10000 10000 100%
HDPE Duct laying green 0 0 10000 10000 100%
Warning tape laying backfilling 0 0 10000 10000 100%
DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 107 0%
Concrete encasements 0 0 107 107 100%
Bridge attachement - river crossing 0 0 0 1 0%
Fiber blowing 0 0 0 10000 0%
hand hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 1 0%
End to End Testing 0 0 0 1 0%

Milestone 1: 0-10km 53%


To deploy 10 km, 2nd milestone
Route Marking 0 0 10000 10000 100%
Brush clearing 0 0 9684 9684 100%
Pilot hole /search hole pits 0 0 1 1 100%
Trenching 0 0 10000 10000 100%
HDPE Duct laying Blue 0 0 10000 10000 100%
HDPE Duct laying green 0 0 10000 10000 100%
Warning tape laying backfilling 0 0 10000 10000 100%
DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 1 0%
Concrete encasements 0 0 0 1 0%
Bridge attachement - river crossing 0 0 0 1 0%
Fiber blowing 0 0 0 10000 0%
h/hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 1 0%
End to End Testing 0 0 0 1 0%
Milestone 2: 10- 20km 47%
To deploy 10 km 3rd milestone
Route Marking 0 0 10000 10000 100%
Brush clearing 0 0 6162 6162 100%
Pilot hole /search hole pits 0 0 5 5 100%
Trenching 0 0 10000 10000 100%
HDPE Duct laying Blue 0 0 10000 10000 100%
HDPE Duct laying green 0 0 10000 10000 100%
Warning tape laying backfilling 0 0 10000 10000 100%
DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 100 0%
Concrete encasements 0 0 33 200 17%
Bridge attachement - river crossing 0 0 0 100 0%
Fiber blowing 0 0 0 10000 0%
h/hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 48 0%
End to End Testing 0 0 0 1 0%
Milestone 3: 20-30km 48%
To deploy 10 km 4th milestone
Route Marking 0 0 10000 10000 100%
Brush clearing 0 0 5385 5385 100%
Pilot hole /search hole pits 0 0 2 2 100%
Trenching 0 0 10000 10000 100%
HDPE Duct laying Blue 0 0 10000 10000 100%
HDPE Duct laying green 0 0 10000 10000 100%
Warning tape laying backfilling 0 0 10000 10000 100%

DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 100 0%
Concrete encasements 0 0 0 250 0%
Bridge attachement - river crossing 0 0 0 1 0%
Fiber blowing 0 0 0 10000 0%
H/hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 1 0%
End to End Testing 0 0 0 1 0%
Milestone 4: 30-40km 47%
To deploy 10 km 5th milestone
Route Marking 0 0 10000 10000 100%
Brush clearing 0 0 3737 3737 100%
Pilot hole /search hole pits 0 0 2 2 100%
Trenching 0 0 10000 10000 100%
HDPE Duct laying Blue 0 0 10000 10000 100%
HDPE Duct laying green 0 0 10000 10000 100%
Warning tape laying backfilling 0 0 10000 10000 100%
DIT 0 0 0 10000 0%
Road Crossing- thrust boring 0 0 0 1 0%
Joint/ Trench markers 0 0 0 50 0%
Special encasement /drain crossing 0 0 0 100 0%
Concrete encasements 0 0 0 500 0%
Bridge attachement - river crossing 0 0 0 100 0%
Fiber blowing 0 0 0 10000 0%
H/hole installation 0 0 5 5 100%
Cable Splicing 0 0 0 1 0%
End to End Testing 0 0 0 1 0%
Milestone 5: 40-50km 47%

Overall Project Completion 47%


Projects Weekly Dashboard
pacity Transmission Project

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Telone Labour T&S Transport
Labour
Planned Costs $0.00 $0.00 $0.00 $0.00 $ - $0.00
Actual Costs $ 270,400.00 $ - $ - $ 293,628.00 $ 9,045.00 $ 31,165.50
Variance $ (270,400.00) $ - $ - $ (293,628.00) $ (9,045.00) $ (31,165.50)

Planned vs Actual Project time durations


Duration Start date Finish date
Planned 84 6/7/2023
Actual 214 6/7/2023

This week's accomplishment

# 80Km - 90Km milestone,


# Trenched 3250m open trench cum 7950m out of 10000m open trench
# ducts covering a distance of 10km received on site
Planned accomplishments next week

# 80 -90km milestone : to trench rem 2050m


# bedding pipe laying/full backfill to cover a distance of 8000m.

Additional Comments

# 0- 100km milestone 80 km cumulative trenched and full backfilled out of 100 km.

Challenges
Leasons Learnt
# As the project progresses, an issue log book becomes increasingly necessary
# It is critical to keep track of all risks as the project progresses.

Procurement
# contractor

Issues logged
0-50km milestone
# Warning tape was not booked to Telone stores
# Joint markers,,fibre and HDPE duct mid coupling rem for the 50km milestone.
# 3 Bridge attachements cumulative 169 m

50-100km milestone
#1200m of rocky area trenched,portions with snages : done.
# Soil importation for a stretch of 450m done.
# river crossing at 74 km done
#rock breaking to do at 86km and 89km total of 13m. Done

Potential clients along fiber route


#Umguza toll gate ZINARA # Nyamandlovu -Prisons # 2 Netone BTS.# Vocational training centre #Roselyne Lodge-
expressed interest # Insuza shoping centre- Clinic,Police.Nyamandlovu Telone
s
Rein- Total Costs
statement
$0 $ -
$ - $ 604,238.50
$ - $ (604,238.50)
entre #Roselyne Lodge-
Project Name: WTTX FIBRE BACKHAULING (5104336
Scope: To deploy fibre backhauling for LTE on 5 Sites
Report Period: 22/02/2023-27/02/2024
Week Number: 1
Deployed by: DZUDA , MUSHAYAHEMBE NAGO

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
BOKA Planned Costs
P0le hole marking 0 0 2 2 100% Actual Costs
Pole hole digging 0 0 2 2 100% Variance
Pole planting 0 0 2 2 100%
Cable stringing 0 0 250 250 100% Planned vs Actual Project
Cable splicing 0 0 4 6 67%
End to end testing 0 0 2 2 100%
Milestone 1 BOKA 94% Planned
CHITUNGWIZA UNIT J
Pole hole marking 0 0 0 6 0%
Pole hole digging 0 0 0 6 0%
Pole planting 0 0 0 6 0%
Cable stringing 0 0 0 550 0%
Stay wire hole digging 0 0 0 3 0%
Stay preparation & installation 0 0 0 3 0%
Cable splicing 0 0 0 20 0%
End to end testing 0 0 0 2 0%
Milestone 2 CHITUNGWIZA UNIT J 0%
CHITUNGWIZA ZENGEZA 3
Pole hole marking 0 0 0 5 0%
Pole hole digging 0 0 0 5 0%
Pole planting 0 0 0 5 0%
Stay wire hole digging 0 0 0 5 0%
Stay prep & installation 0 0 0 3 0%
Cable stringing 0 0 0 400 0%
Cable splicing 0 0 0 8 0%
End to end testing 0 0 0 2 0%
Milestone 3 ZENGEZA 3 0%
Overall Project Completion 31%
Multitasking and teamwork ensures ef
Budgeted/Planned vs Actual Incurred Costs
Materials Wayleave Casual Telone Labour T&S Transport Rein- Total Costs
Labour statement
$ 54,636.02 $ 4,087.00 $ 29,841.05 $ 7,870.00 $ - $ 96,434.07
$ 256.52 $ - $ 110.00 $ 736.00 $ - $ 270.00 $ - $ 1,372.52
$ 54,379.50 $ - $ 3,977.00 $ 29,105.05 $ - $ 7,600.00 $ - $ 95,061.55

Planned vs Actual Project time durations


Duration Start date Finish date

This week's accomplishment

Planned accomplishments next week

Additional Comments

Challenges
Leasons Learnt

sking and teamwork ensures effective and efficient implementation of projects.


Project
Project Name: CHERUTOMBO & RUSIKE PHASE 1 & 2 FTTH- 5104175
Scope: To provide GPON Connectivity to 2496 Clients.
Report Period: 21/02/2024 - 27/02/2024
Week Number: 17
Deployed by: GIDI

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Feeder U/G Network
Duct Clearing 0 0 6000 11820 51%
Locating of manholes 0 0 6 10 60%
7 way Microduct pulling (in existing ducts) 0 0 6000 11820 51%
handhole installation 0 0 0 2 0%
Pedestal construction 0 0 4 4 100%
Fibre pulling microduct 144 core 0 1000 6400 13230 48%
FDH mounting 0 0 4 4 100%
Fibre terminations at ODF 0 0 144 288 50%
Trenching 0 0 1380 1380 100%
Thrust boring 1 1 4 5 80%
Driveways crossings 0 0 51 60 85%
7 way microduct laying and backfilling 0 0 1380 1380 100%
Cable Splicing 0 0 12 48 25%
Fibre Testing 0 0 12 48 25%
Milestone 1: Feeder U/G Network 62%
ODN FDH 01 O/H Network
Pole hole marking 0 0 0 250 0%
Pole hole digging 0 0 0 250 0%
Pole planting 0 0 0 250 0%
Dead End fittings 0 0 0 400 0%
Mid-Span fittings 0 0 0 70 0%
Cable Storage fittings 0 0 0 54 0%
NAP installations 0 0 0 54 0%
Stay hole digging 0 0 0 110 0%
Stay wire making 0 0 0 110 0%
Stay set installation 0 0 0 110 0%
O/H Cable Stringing 0 0 0 11366 0%
FDH splicing 0 0 0 648 0%
NAP splicing 0 0 0 54 0%
NAP Testing and faulting 0 0 0 54 0%
Milestone 2 FDH 01 0%
ODN FDH 02 O/H Network
Pole hole marking 0 0 235 235 100%
Pole hole digging 0 0 235 235 100%
Pole planting 0 0 235 235 100%
Dead End fittings 0 0 340 340 100%
Mid-Span fittings 0 0 100 100 100%
Cable Storage fittings 0 0 52 52 100%
NAP installations 0 0 52 52 100%
Stay hole digging 0 0 100 100 100%
Stay wire making 0 0 100 100 100%
Stay set installation 0 0 100 100 100%
OH/Cable stringing 72 core ADSS 0 0 11700 11700 100%
FDH splicing 0 0 624 624 100%
NAP splicing 0 0 52 52 100%
NAP Testing and faulting 0 0 52 52 100%
Milestone 3 FDH 02 100%
ODN FDH 03 O/H Network
Pole hole marking 0 0 230 230 100%
Pole hole digging 0 0 230 230 100%
Pole planting 0 0 230 230 100%
Trenching 0 0 150 150 100%
duct laying and backfilling. 0 0 150 150 100%
Dead End fittings 0 0 478 478 100%
Mid-Span fittings 0 0 194 194 100%
Cable Storage fittings 0 0 51 51 100%
NAP installations 0 0 51 51 100%
Stay hole digging 0 0 94 94 100%
Stay wire making 0 0 94 94 100%
Stay set installation 0 0 94 94 100%
O/H Cable Stringing 48 core 0 0 12000 12000 100%
O/H Cable Stringing 24 core 0 0 4000 4000 100%
FDH splicing 0 0 612 612 100%
NAP splicing 0 0 51 51 100%
NAP Faulting and testing 0 0 51 51 100%
Milestone 4 FDH 03 100%
ODN FDH 04 O/H Network
Pole hole marking 0 0 0 270 0%
Pole hole digging 0 0 0 270 0%
Pole planting 0 0 0 270 0%
Trenching duct layin & back filling 0 0 0 1600 0%
Thrust boring 0 0 0 3 0%
handhole installation 0 0 0 1 0%
Dead End fittings 0 0 0 450 0%
Mid-Span fittings 0 0 0 120 0%
Cable Storage Fitting 0 0 0 54 0%
NAP installations 0 0 0 54 0%
Stay hole digging 0 0 0 140 0%
Stay wire making 0 0 0 140 0%
Stay set installation 0 0 0 140 0%
O/H Cable Stringing 0 0 0 12560 0%
FDH splicing. 0 0 0 648 0%
NAP splicing 0 0 0 54 0%
Milestone 5 FDH 04 0%
Overall Project Completion 52%
Projects Weekly Dashboard
& 2 FTTH- 5104175
Clients.

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone T&S
Labour
Planned Costs $ 335,665.04 $ 3,926.58 $ 24,545.24 $ 59,317.63 $ 29,469.00
Actual Costs $ 177,083.68 $ - $ 19,520.00 $ 13,060.00 $ 2,774.00
Variance 158,581.36 $ 3,926.58 $ 5,025.24 $ 46,257.63 $ 26,695.00

Planned vs Actual Project time durations


Duration Start date Finish date
Planned 210 8/16/2023
Actual 85

This week's accomplishment


#FDH 01
On hold

Planned accomplishments next week


FDH01
# the project now temporarily on HOLD waiting for the availability of poles and fibre cable at Msasa stores.

Additional Comments
# a GPON card is required urgently
Only 6 GPON ports are available out of 10 ports required to avail a capacity of 624 clients for FDH 02.

Challenges
# unavailability of GPON cards
# unavailabilty of reliable splicing machines.
# 7 way microducts are out of stock .
# rains affects project activities
# lack of enough resources is affecting the project plan and might risk missing targets

Lessons Learnt

# a proper workplan ensures effective deployment of a project.


# casuals must be paid on time so that casual turnout can be improved.
Transport Rein-statement Total Costs

$ 43,800.00 $ 2,777.66 $ 499,501.15


1,359.00 $ - $ 213,796.68
$ 42,441.00 $ 2,777.66 $ 285,704.47

res.
Projects Weekly Da
Project Name: Mahatshula Ftth Asset Number 5104073
Scope: To deploy GPON FTTH capacity of 2760 households.
Report Period: 07/02/2024 - 13/02/2024
Week Number: 38
Deployed by: Mutyoraringa, Chasakara

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Feeder U/G Network
Manhole searching 0 0 12 12 100%
Duct reparing & clearing 0 0 3200 3200 100%
Micro-duct pushing in existing ducts 0 0 3200 3200 100%
Pilot Hole digging(Trenching preparation) 0 0 20 20 100%
Trenching 0 0 4100 4100 100%
Micro-duct laying and backfilling 0 0 4100 4100 100%
Railway crossing 0 0 1 1 100%
Roadcrossings ( Requires thrust boring) 0 0 10 10 100%
Cable pulling 0 0 8000 8000 100%
FDH Pedestal construction 0 0 4 4 100%
FDH cabinet mounting 0 0 4 4 100%
Fibre termination 0 0 48 48 100%
Milestone 1 Feeder U/G Network 100%
U/G FDH 01 U/G Network
Pilot Hole digging(Trenching preparation 0 0 60 60 100%
Trenching 0 0 10000 10000 100%
Microduct laying 0 0 10000 10000 100%
Complete backfilling 0 0 10000 10000 100%
Road crossings( Requires Thrust boring ) 0 0 35 35 100%
Driveway crossings( 15 Thrust boring required) 0 0 65 65 100%
Microduct cable pulling 0 0 17127 17127 100%
Pole hole digging 0 0 55 55 100%
Pole planting 0 0 55 55 100%
Nap Preparation 0 0 55 55 100%
Nap splicing 0 0 55 55 100%
Nap Testing and Faulting 0 0 55 55 100%
PATs 0 0 55 55 100%
Handover 0 0 55 55 100%
Milestone 2 UG FDH 01 U/G Network 100%
U/G FDH 02 U/G Network
Trenching 0 0 9200 9200 100%
Duct laying and complete backfilling 0 0 9200 9200 100%
Road crossings( Requires Thrust boring ) 0 0 26 26 100%
Microduct cable pulling 0 0 12934 12934 100%
Pole hole digging 0 0 54 54 100%
Pole planting 0 0 54 54 100%
Nap Preparation 0 0 54 54 100%
Nap splicing 0 0 54 54 100%
Nap Testing and Faulting 0 0 54 54 100%
PATs 0 0 54 54 100%
Handover 1 1 1 1 100%
Milestone 3 U/G FDH 02 U/G Network 100%
U/G FDH 03 U/G Network
Trenching 0 0 900 900 100%
HDPE Duct laying 0 0 900 900 100%
Complete backfilling 0 0 900 900 100%
Route marking & pole hole digging 0 0 230 230 100%
Pole planting 0 0 230 230 100%
Accessory fittings 0 0 385 385 100%
Cable stringing 0 0 16320 16320 100%
Nap Preparation 0 0 54 54 100%
Nap splicing 0 0 54 54 100%
Stay set hole digging & stay sets installations 0 0 28 28 100%
Nap preparation & splicing 0 0 54 54 100%
FDH preparation & splicing 0 0 648 648 100%
Nap Testing and Faulting 0 0 54 54 100%
PATs and Handover 0 0 1 1 100%
Milestone 4 U/G FDH 03 U/G Network 100%
U/G FDH 04 U/G Network
Pole hole digging and planting 0 0 250 250 100%
Over head accessory fittings 0 0 510 400 100%
Overhead cable stringing 0 0 15620 15620 100%
Stay set hole digging & stay sets installations 0 0 40 40 100%
Nap preparations and splicing 0 0 55 55 100%
Cable storage fittings installation 0 0 55 55 100%
Trenching from ODN to FDH 0 0 1000 1000 100%
U/G Cable pulling from ODN to FDH 0 0 1200 1200 100%
FDH preparations and splicing 0 0 55 55 100%
Nap Testing and Faulting 0 0 55 55 100%
PATs 0 0 0 1 0%
Handover 0 0 0 1 0%
Milestone 5 U/G FDH 05 U/G Network 83%
U/G FDB 01 & FDB 02 U/G Network
Trenching 0 0 0 2400 0%
Microduct laying 0 0 0 2400 0%
Complete backfilling 0 0 0 2400 0%
Road crossings( Requires Thrust boring ) 0 0 0 8 0%
Microduct cable pulling 0 0 0 3500 0%
Pole hole digging 0 0 0 11 0%
Pole planting 0 0 0 11 0%
Nap Preparation 0 0 0 11 0%
Nap splicing 0 0 0 11 0%
Nap Testing and Faulting 0 0 0 11 0%
PATs 0 0 0 1 0%
Milestone 6 U/G FDB 01 & FDB 02 U/G Network 0%
Overall Project Completion 81%
Projects Weekly Dashboard

useholds.

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone Labour T&S Transport

Planned Costs $ 328,159.36 $ 66,645.08 $ 189,369.87 $ - $ 12,464.00 $ 25,542.00


Actual Costs $ 325,388.93 $ - $ 57,580.00 $ 6,103.00 $ 15,999.00 $ 16,730.50
Variance $ 2,770.43 $ 66,645.08 $ 131,789.87 $ (6,103.00) $ (3,535.00) $ 8,811.50

Planned vs Actual Project time durations


Duration Start date Finish date
Planned 84 2/1/2023 3/2/2023
Actual 176 2/3/2023

This week's accomplishment


FDH 04
Completed and waiting for GPON card.

Planned accomplishments next week

Additional comments
# Unavailability of splicing machines to use during project implementaion is affecting our progress as we are
borrowing machines from other departments whom most times took their machines before we are done splicing.
# We kindly request the department to take a look into this issue as it is dragging our progress to a greater extend.
# We also require a GPON card at Killarney RLU

Challenges
# Unavailability fuel (desiel) for material delivery to site has hindered our progress to a greater extend.We are slowly
getting behind planned schedule since some activities planned cannot be executed due to unavailablity of materials
sts
Reinstatements Total Costs

$ 81,000.00 $ 703,180.31
$ - $ 421,801.43
$ 81,000.00 $ 281,378.88

as we are
done splicing.
reater extend.

nd.We are slowly


lity of materials
Project Name: NORTON UNDERGROUND CABLE DIV
Scope: To divert Norton undergroud cable
Report Period: 15/11/2023 - 21/11/2023
Week Number: 3
Deployed by: MUTAYIWA & NAGO

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Backbone Divert Planned Costs
Trenching 0 0 1500 1500 100% Actual Costs
7Way microduct laying & back fillin 0 0 1500 1500 100% Variance
Handhole Building 0 0 0 4 0%
Road crossing 0 0 6 6 100%
Fiber Cable pulling 0 0 2560 2675 96% Planned vs Actual Projec
Overall Project Completion 79%

project on hold waiting for thrust bor

Waiting for roads to be crossed .


Budgeted/Planned vs Actual Incurred Costs
Materials Wayleave Casual Telone Labour T&S Transport Rein- Total Costs
Labour statement
$5,321.40 $2,600.00 $6,200.46 $ - $420.00 $0 $ 14,541.86
$ 6,155.00 $ - $ 300.00 $ 640.00 $ - $ 120.00 $ - $ 7,215.00
$ (833.60) $ - $ 2,300.00 $ 5,560.46 $ - $ 300.00 $ - $ 7,326.86

Planned vs Actual Project time durations


Duration start date Finish date
27 6/3/2023 28/03/2023

This week's accomplishment


t on hold waiting for thrust boring.

Planned accomplishments next week

Additional Comments

ng for roads to be crossed .

Challenges
Leasons Learnt
Projects Weekly Dashboard
Project Name: BYO-V/FALLS LAST MILE BCS PROJECT ASSET
Scope: Implementation of backhaul link from BCS POPs to TelOne Exchanges VIC
Report Period: 18/07/2023 TO 25/07/2022
Week Number: 1
Deployed by: MHANDE FARAI

Total Total Total B


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Last Mile Fibre Backhauling Planned Costs
Route Marking 0 0 120 120 100% Actual Costs
Duct clearing for existing 0 0 180 180 100% Variance
Trenching 0 0 120 120 100%
Duct laying & Backfilling 0 0 120 120 100% Planned vs Actual Project tim
Cable Blowing/ Pulling 0 0 300 300 100%
Cable Splicing & Testing 0 0 0 4 0% Planned
Overall Project Completion 83% Actual
Variance

#96core microduct cable pulling 30m pulle


#patch panel terminated

Pl
# splicing of 2 cores at exchange ,2 cores a
cts Weekly Dashboard

lOne Exchanges VIC

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone Labour T&S Transport Rein- Total Costs
statement
$ 158,351.20 $ - $ 36,717.87 $ 48,418.00 $ 40,656.00 $ 44,820.00 $ - $ 328,963.07
$ 1,420.00 $ - $ 510.00 $ 1,360.00 $ 418.00 $ 76.50 $ - $ 3,784.50
$ 156,931.20 $ - $ 36,207.87 $ 47,058.00 $ 40,238.00 $ 44,743.50 $ - $ 325,178.57

Planned vs Actual Project time durations


Duration Start date Finish date
105 7/18/2023 7/28/2023
7

This week's accomplishment


re microduct cable pulling 30m pulled 300m total done
panel terminated

Planned accomplishments next week


ing of 2 cores at exchange ,2 cores at BCS manhole, fiber testing

Additional Comments

Challenges
Lessorn learnt
Projects W
Project Name: IZAYI PARK FTTH (1706466)
Scope: To deploy a GPoN network for a capacity of 780 households
Report Period: 20/03/2024 -26/03/2024
Week Number: 26
Deployed by: M.MBOFANA

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Feeder U/G Network
Bush cutting 0 0 1800 1800 100%
Trenching 0 0 2320 2320 100%
Duct laying and Backfilling 0 0 2320 2320 100%
Handhole installation 0 0 8 8 100%
Road crossing 0 0 10 10 100%
Driveway crossing 0 0 9 9 100%
Cable Blowing/ Pulling 0 0 2600 2600 100%
Cable Splicing and Testing 0 0 24 24 100%
Milestone 1 FEEDER Network 100%
ODN FDH 01 O/H Network
Trenching 0 0 450 450 100%
Pole hole digging 0 0 190 190 100%
Pole planting 0 0 190 190 100%
Dead End fittings 0 0 317 317 100%
Mid-Span fittings 0 0 85 85 100%
Cable Storage fittings 0 0 42 42 100%
Down lead clamp fitting 0 0 42 42 100%
Stay hole digging 0 0 15 15 100%
Stay wire making 0 0 15 15 100%
Stay set installation 0 0 15 15 100%
Cable Stringing 0 0 10850 10850 100%
Cable Splicing and Testing 0 0 504 504 100%
FDH Pedestal Construction 0 0 1 1 100%
FDH Cabinet Mounting 0 0 1 1 100%
FDH Cable Terminations 0 0 8 8 100%
Splitter Fitting 0 0 8 8 100%
NAP Installation and Splicing 0 0 42 42 100%
End to End Testing 0 0 504 504 100%
Milestone 2 FDH 01 100%
ODN FDH 02 O/H Network
Trenching 0 0 940 940 100%
Pole hole digging 0 0 180 180 100%
Pole planting 0 0 180 180 100%
Dead End fittings 0 0 302 302 100%
Mid-Span fittings 0 0 74 74 100%
Cable Storage fittings 0 0 41 41 100%
Down lead clamp fitting 0 0 45 45 100%
Stay hole digging 0 0 30 30 100%
Stay wire making 0 0 30 30 100%
Stay set installation 0 0 30 30 100%
Cable Stringing 0 0 8500 8500 100%
Cable Splicing and Testing 0 0 504 504 100%
FDH Pedestal Construction 0 0 1 1 100%
FDH Cabinet Mounting 0 0 1 1 100%
FDH Cable Terminations 0 0 7 7 100%
Splitter Fitting 0 0 8 8 100%
NAP Installation and Splicing 0 0 41 41 100%
End to End Testing 0 0 12 12 100%
Milestone 3 FDH 02 100%
Overall Project Completion 100%
Projects Weekly Dashboard

y of 780 households

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone Labour T&S Transport

Planned Costs $ 151,603.96 $ 6,261.83 $ 14,913.33 $ 28,259.60 $ 17,400.00 $ 23,205.00


Actual Costs $ 126,832.68 $ - $ 10,100.00 $ 14,818.00 $ 3,030.00 $ 6,964.50
Variance $ 24,771.28 $ 6,261.83 $ 4,813.33 $ 13,441.60 $ 14,370.00 $ 16,240.50

I
Duration Start date Finish date
Planned 43
Actual 132 1/15/2018

This week's accomplishment


Project completed on 01/12/2022

# Stay set installation completed on 22/03/2024

Planned accomplishments next week

Additional Comments
Challenges

Leasons Learnt
s
Rein-statement Total Costs

$ 3,750.00 $ 245,393.72
$ - $ 161,745.18
$ 3,750.00 $ 83,648.54
Project Name: GLENVIEW LTE BACKHAULING (510
Scope: To deploy fibre backhauling for LTE on 3 Sites
Report Period: 06/02/2024 - 13/02/2024
Week Number: 8
Deployed by: DZUDA , USHE

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
GLEN NORAH Planned Costs
P0le hole marking 0 0 4 4 100% Actual Costs
Pole hole digging 0 0 4 4 100% Variance
Pole planting 0 0 4 4 100%
Stay wire hole digging 0 0 3 3 100%
Stay prep & installation 0 0 3 3 100%
Cable stringing 0 0 300 300 100% Planned vs Actual Projec
Cable splicing 0 2 6 6 100%
End to end testing 0 2 2 2 100%
Planned
Milestone 1 Glen Norah 100%
BUDIRIRO
Pole hole marking 0 0 6 6 100%
Pole hole digging 0 0 6 6 100% Completed BTS end terminations and
Pole planting 0 0 6 6 100%
Cable stringing 0 0 550 550 100%
Stay wire hole digging 0 0 3 3 100%
Stay preparation & installation 0 0 3 3 100%
Cable splicing 0 2 20 20 100%
End to end testing 0 2 2 2 100%
#testing for all sites
Milestone 2 Budiriro 100%
MUFAKOSE
Pole hole marking 0 0 5 5 100%
Pole hole digging 0 0 5 5 100%
Pole planting 0 0 5 5 100%
Stay wire hole digging 0 0 5 5 100%
Stay prep & installation 0 0 3 3 100% #waiting for the BTSes to be installed
Cable stringing 0 0 400 400 100%
Cable splicing 0 2 8 8 100%
End to end testing 0 2 2 2 100%
Milestone 3 Mufakose 100% # motor vehicle shortages
Overall Project Completion 100% #splicing machine sharing

Multitasking and teamwork ensures e


Budgeted/Planned vs Actual Incurred Costs
Materials Wayleave Casual Labour Telone Labour T&S Transport Rein- Total Costs
statement
$ 2,486.84 $ 217.90 $ 10,362.29 $ 1,170.00 $ - $ 14,237.03
$ 2,120.64 $ - $ 490.00 $ 184.00 $ - $ 5,022.50 $ - $ 7,817.14
$ 366.20 $ - $ (272.10) $ 10,178.29 $ - $ (3,852.50) $ - $ 6,419.89

Planned vs Actual Project time durations


Duration Start date Finish date

45

This week's accomplishment

eted BTS end terminations and testing

Planned accomplishments next week


g for all sites

Additional Comments

ng for the BTSes to be installed on all sites

Challenges
or vehicle shortages
ng machine sharing

Leasons Learnt
asking and teamwork ensures effective and efficient implementation of projects.
Projects Weekly Da
Project Name: SOUTHLEA PARK FTTH 5104079
Scope: To deploy GPON FTTH capacity of 828 households.
Report Period: 31/01/2024 - 06/02/2024
Week Number: 20
Deployed by: NYASHA AND NAGO

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Feeder U/G Network Planned Costs
Handhole Construction 0 0 0 2 0% Actual Costs
Duct Clearing 0 0 8000 8000 100% Variance
Pole planting 0 0 2 2 100%
Pilot holes 0 0 18 18 100%
Midspans fittings 0 0 65 65 100% Planned vs Actual Project
Dead End fittings 0 0 43 43 100%
Cable Pulling(144 core) 0 0 4400 4400 100% Planned
Cable stringing(72 core) 0 0 5600 5600 100% Actual
Trenching 0 0 5000 5000 100%
7way Microduct laying 0 0 5000 5000 100%
Backfilling 0 0 5000 5000 100%
Cable Splicing 0 0 244 244 100%
End to End Testing 0 0 144 144 100%
Milestone 1 Feeder 92%
ODN FDH 01 O/H Network # Completed 02/02/2024
Route Marking 0 0 8 8 100%
Trenching 0 0 500 500 100%
Duct laying and backfilling 0 0 500 500 100%
Pole hole marking 0 0 250 250 100%
Pole hole digging 0 0 250 250 100%
Pole planting 0 0 250 250 100%
Mid-Span fittings 0 0 195 195 100%
Dead End fittings 0 0 380 380 100%
Cable Storage fittings 0 0 54 54 100%
Down lead clamp fitting 0 0 50 50 100%
Stay hole digging 0 0 80 80 100% # to complete as built drawings
Stay wire making 0 0 80 80 100%
Stay set installation 0 0 80 80 100%
O/H C/Stringing (72 cores 0 0 10200 10200 100%
O/H C/Stringing (48 cores 0 0 800 800 100%
Cable pulling 72 core 0 0 1000 1000 100%
Cable pulling 48 cores 0 0 250 250 100%
FDH Pedestal Construction 0 0 1 1 100%
FDH Cabinet Mounting 0 0 1 1 100%
FDH Tray preparation 0 0 50 50 100%
FDH TRAYS Terminations 0 0 50 50 100%
Splitter Fitting 0 0 10 10 100%
NAP Preparation 0 0 50 50 100%
NAP Splicing 0 0 50 50 100%
Nap testing and faulting 0 0 50 50 100%
End to End Testing 0 0 600 600 100%
Milestone 2 FDH 01 100% Unavailability of reliable vehicle hinderi
ODN FDH 02 O/H Network Only 8 ports are available at Waterfalls O
Route Marking 0 0 5 5 100% purchased
another GPON card purchased
Trenching 0 0 150 150 100%
Duct laying and backfilling 0 0 150 150 100%
Pole hole marking 0 0 100 100 100%
Pole hole digging 0 0 100 100 100%
Pole planting 0 0 100 100 100% #commitment and perpetual supervision
Dead End fittings 0 0 200 200 100%
Mid-Span fittings 0 0 107 107 100%
Cable Storage fittings 0 0 21 21 100%
Down lead clamp fitting 0 0 20 20 100%
Stay hole digging 0 0 40 40 100%
Stay wire making 0 0 40 40 100%
Stay set installation 0 0 40 40 100%
O/H Cable Stringing{72cores} 0 0 1100 1100 100%
O/H Cable Stringing(48 cores) 0 0 4540 4540 100%
FDH Pedestal Construction 0 0 1 1 100%
FDH Cabinet Mounting 0 0 1 1 100%
FDH Tray preparation 0 0 19 19 100%
FDH Tray splicing 0 0 19 19 100%
Splitter Fitting 0 0 4 4 100%
NAP Preparation 0 0 19 19 100%
NAP Splicing 0 0 19 19 100%
End to End Testing 0 0 228 228 100%
Milestone 3 FDH 02 100%
Overall Project Completion 97%
Projects Weekly Dashboard

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone T&S Transport Enginnering
Labour cost
$99,827.74 $2,373.33 $10,151.27 $20,762.59 $ - $4,820.00 $2,448.00
$ 102,634.25 $ - $ 17,070.00 $ 25,266.00 $ - $ 3,702.00 $ 3,000.00
$ (2,806.51) $ 2,373.33 $ (6,918.73) $ (4,503.41) $ - $ 1,118.00

Planned vs Actual Project time durations


Duration Start date Finish date
60 3/10/2023 5/9/2023
111

This week's accomplishment

mpleted 02/02/2024

Planned accomplishments next week

omplete as built drawings

Additional Comments
Challenges

ailability of reliable vehicle hindering the progress of project.


8 ports are available at Waterfalls OLT to avail a capacity of 512 households,the remaining will be availed when another GPON card
ased
er GPON card purchased

Leasons Learnt
mitment and perpetual supervision yeild positive results.
Rein- Total Costs
statement
$0 $ 140,382.93
$ - $ 145,859.71
$ - $ (5,476.78)
en another GPON card
Projects Weekly Dash
Project Name: HILLSIDE FTTH BULAWAYO 1706976
Scope: To deploy GPON FTTH capacity of 1536 households.
Report Period: 12/04/23 to 17/04/23
Week Number: 25
Deployed by: MADZIMURE & JECHE

Total Total Total


Weekly Done this Cum. Planned %age
Activities Target week Done Activity complete
Feeder U/G Network Planned Costs
Manhole Locating 0 0 14 14 100% Actual Costs
Duct Clearing 0 0 3800 3800 100% Variance
7way microduct pulling 0 0 3800 3800 100%
Cable Blowing/ Pulling 0 0 3800 3800 100%
Pilot holes 0 0 15 15 100%
Trenching 0 0 455 455 100% Planned vs Actual Project
Road Crossing 0 0 2 2 100%
Driveway crossing 0 0 4 4 100%
7way Microduct laying 0 0 500 500 100% Planned
Backfilling 0 0 455 455 100% Actual
Cable Splicing 0 0 84 84 100%
End to End Testing 0 0 84 84 100%
Milestone 1 FEEDER Network 100%
ODN FDH 01 O/H Network #Completed PATs and handover on 14/
Route Marking 0 0 395 395 100%
Bush cutting 0 0 20500 20500 100%
Pole hole marking 0 0 370 370 100%
Pole hole digging 0 0 370 370 100%
Pole planting 0 0 370 370 100%
Mid-Span fittings 0 0 216 216 100% Project Handover.
Dead End fittings 0 0 314 314 100%
Cable Storage fittings 0 0 55 55 100%
Down lead clamp fitting 0 0 55 55 100%
Stay hole digging 0 0 200 200 100%
Stay wire making 0 0 180 180 100%
Stay set installation 0 0 180 180 100%
O/H Cable Stringing 72 Core ADS 0 0 23400 23400 100%
FDH Pedestal Construction 0 0 1 1 100% Capacity availed in 2022 (Total = 708)
FDH Cabinet Mounting 0 0 1 1 100% FDH 02 = 144
FDH TRAYS Terminations 0 0 660 660 100% FDH 03 = 216 Completed
Splitter Fitting 0 0 11 11 100% FDH 01 = 660 Completed
NAP Installation 0 0 55 55 100%
NAP Splicing 0 0 660 660 100%
End to End Testing 0 0 660 660 100%
Milestone 2 FDH 01 100%
ODN FDH 02 O/H Network
Route Marking 0 0 312 312 100%
Bush cutting 0 0 20300 20300 100% #Heavy rains disturbed our weekly pro
Pole hole marking 0 0 312 312 100%
Pole hole digging 0 0 312 312 100%
Pole planting 0 0 312 312 100%
Dead End fittings 0 0 351 351 100%
Mid-Span fittings 0 0 296 296 100%
Cable Storage fittings 0 0 55 55 100%
Down lead clamp fitting 0 0 55 55 100%
Stay hole digging 0 0 115 150 77%
Stay wire making 0 0 82 150 55%
Stay set installation 0 0 93 150 62%
O/H Cable Stringing 72 Core
ADSS 0 0 23000 23000 100%
FDH Pedestal Construction 0 0 1 1 100%
FDH Cabinet Mounting 0 0 1 1 100%
FDH Tray Terminations 0 0 660 660 100%
Splitter Fitting 0 0 11 11 100%
NAP Installation 0 0 55 55 100%
NAP Splicing 0 0 660 660 100%
End to End Testing 0 0 660 660 100%
Milestone 3 FDH 02 95%
ODN FDH 03 O/H Network
Route Marking 0 0 186 186 100%
Bush cutting 0 0 1300 1300 100%
Pole hole marking 0 0 176 176 100%
Pole hole digging 0 0 176 176 100%
Pole planting 0 0 176 176 100%
Dead End fittings 0 0 186 186 100%
Mid-Span fittings 0 0 130 130 100%
Cable Storage fittings 6 0 18 18 100%
Down lead clamp fitting 0 0 18 18 100%
Stay hole digging 0 0 70 70 100%
Stay wire making 0 0 70 70 100%
Stay set installation 0 0 70 70 100%
O/H Cable Stringing 72 Core
ADSS 0 0 10000 10000 100%
FDH Pedestal Construction 0 0 1 1 100%
FDH Cabinet Mounting 0 0 1 1 100%
FDH Tray Terminations 0 0 216 216 100%
Splitter Fitting 0 0 4 4 100%
NAP Installation 0 0 18 18 100%
NAP Splicing 0 0 216 216 100%
End to End Testing 0 0 216 216 100%
Milestone 4 FDH 03 100%
Overall Project Completion 94%
rojects Weekly Dashboard

Budgeted/Planned vs Actual Incurred Costs


Materials Wayleave Casual Labour Telone Labour T&S Transport Rein-statement

$277,740.58 $1,070.00 $15,045.85 $185,342.88 $ 9,576.00 $10,583.00 $9,015


$ 231,604.15 $ - $ 38,890.00 $ 54,421.00 $ 11,590.00 $ 14,339.00 $ -
$ 46,136.43 $ 1,070.00 $ (23,844.15) $ 130,921.88 $ (2,014.00) $ (3,756.00) $ 9,015.00

Planned vs Actual Project time durations

Duration Start date Finish date


84 4/10/2022 6/17/2022
117

This week's accomplishment


pleted PATs and handover on 14/04/2023

Planned accomplishments next week


t Handover.

Additional Comments

ity availed in 2022 (Total = 708)


02 = 144
03 = 216 Completed
01 = 660 Completed
Challenges
y rains disturbed our weekly progress

Leasons Learnt
Total Costs

$ 508,373.31
$ 350,844.15
$ 157,529.16