Professional Documents
Culture Documents
ON
October, 2023
Page 1 of 5
Project title:
Gomal Zam Dam-Command Area Development and On-Farm Water Management for High
Value and High Efficiency Agriculture Project (GZD-CADP)
1. Appraisal History
Description Original PC-1 Revised PC-1
PDWP Clearance 06.03.2013 22.04.2022
CDWP Approval 01.10.2013 19.10.2022
ECNEC Approval 06.03.2014 N/A
Authorization Letter 16.06.2014 30.12.2022
Administrative Approval (AA) 17.09.2014 03.02.2023
Project Life /Completion date June, 2017 June, 2024
Page 2 of 5
6. Project Funding
Cumulative Cumulative Balance
Cost
PC-I Cost (M) Allocation / Expenditure Amount
Centre
Releases (M) (M) (M)
USAID 2,026.905 (48%) 1,618.367 1,308.663 718.242
ADP 1,756.089 (41%) 721.429 721.429 1,034.651
Farmer’s
450.593 (11%) 89.834 89.834 360.759
Share
Total 4,233.587 (100%) 2,429.630 2,119.936 2,113.652
Page 3 of 5
8. Financial Progress ADP Fund
9. Project Components
# Component Major Targets
Page 4 of 5
10. Physical progress on Component I
Total
# Physical Activities Units PC-I Targets % Achieved
Achieved
1 Revenue Chakbandi/Aqs Shajrah Nos 460 460 100%
2 Owners Lists Nos 460 448 97%
3 Water Users Association Nos 460 362 78%
Watercourses Surveys/Design/BoQs/Bidding
4 Nos 460 454 98%
documents
5 Watercourses awarded for construction Nos 460 421 91%
6 Watercourses completed & verified Nos 460 178 38%
7 Earthen Shingle Roads awarded Km 20.7 20.7 100%
8 Earth Shingle Roads completed unverified Km 20.7 11 53%
9 Area under improved irrigation (acres) Acres 191,139 75,013 40%
10 Beneficiaries from irrigation service Nos 12,576 6,114 49%
Page 5 of 5