Before proceeding with the molding process for the slump cone, ensure the interior surface of

the slump cone is moist, and the area designated for the slump test is level, non-absorbent, and
free of any vibrations.

Once the mold is prepared, prior to pouring the fresh concrete, step on the ears of the cone and
carefully pour the first layer of the fresh concrete mix into the slump cone while rotating the
mixture into the mouth of the cone for even distribution. Next, using a tamping rod, tamp the
fresh concrete 25 times at an angle or in an inclined position to penetrate the very bottom of
the fresh concrete, and then strike the outside of the cone 15 times using a rubber mallet.
Prepare for the second layer by filling the mold two-thirds of the way and tamping it 25 times
until reaching the level of the second layer, then strike the cone 15 times again before
proceeding to the third layer where the mold will be completely filled. Repeat the process by
tamping the third layer 25 times until reaching its starting level and striking it with the rubber
mallet 15 times on the sides of the cone to ensure even filling. Use the tamping rod to remove
any excess fresh concrete and create a smooth surface.

To test the slump of the cone, promptly lift the slump mold without unnecessary extra
movements such as torsion or side-to-side movements. Place the slump cone upside down
beside the fresh concrete and measure the slump. Position the tamping rod above the upside-
down cone and measure the slump value using a tape measure.

The height of the slump cone before lifting the cone:


- The height from the base plate to the tamping rod is 14 inches.
- The height of the base plate from the ground is 2 inches.
- The total height is 16 inches.

The height of the fresh concrete after the cone was lifted:
- The height of the slump was 6 inches.
- Height of the base plate from the ground is 2 inches + Height of the slump is 6 inches = 8
inches.
Molding Fresh Concrete

Before layering, ensure that the inside of the cylinder mold is coated with a thin layer of grease
or oil.

The cylinder cone's dimensions are 4”x 8”, and it should contain two layers of mixed cement.
Each layer requires 25 tamps with a rod and 15 strikes with a rubber mallet on the sides of the
cylinder cone. This procedure effectively solidifies the cement inside the cone.

Once the cylinder mold is filled, use either a rod or a trowel to level off the top, smoothing it and
removing any excess cement.