You are on page 1of 1

Construction Power Supply Application Form

Project Name: -
2x800 MW USCTPP, MAHAN ENERGEN LIMITED (PHASE-II)
Application Date: - Application Dept./ Agency: -
Agency Engaged For -
Power Supply Required For -
Power Supply Chargeable/ Non-Chargeable (Yes/No): -
Equipment Name: - Electrical Panel Capacity: -
Volume (KVA) : Ampere and Voltage required:
Installation Location
Date of Installation;
Date of charging:
1. Proper nut & bolt and Cable lugs should be used for Connection.
2. Rain proof shed should be there.
3. Necessary barricade, warning board, panel name & location, Insulation mat, 3-Phase Meter
and Emergency contact number must be available.
4. Reliable Two Earth Should be Connected.
5. 3.5 Core armored cable should be used instead be Flexible Cable.
6. Cable should be laid below ground (1 Mtr. Deep) and overhead should be more than
two point five (2.5) mtr. on insulated or wooden support and no temporary cable
shall be laid over the ground and cable route marker@15mtr span shall be placed .
7. Earth protection for personnel on the Sites shall be provided by a thirty milli-amp.
(30mA) ELCB/RCCB
8. Panel rooms/ distribution box pathways are clear and free from any obstructions.
9. Electrical system shall be handled by a competent and authorized person for the
voltage as per authorization and in line with the applicable statutory requirements.
10 Authorized Electrician and electrical engineer list should be attached with this form.

Note: - Please take self-inspection accord to the requirement above before submitting this application

Remarks:
Approval Contractor Electrical Engineer:

Contractor Project Site Incharge:

Contractor Safety officer:

Contractor Safety HOD/Incharge :


MEL Related Department Section incharge:

MEL Related Department HOD:

MEL Safety Department officer :

MEL Safety Department HOD/Incharge :


MEL Electrical Dept. concern Area Engineer/incharge:

MEL Electrical HOD:


Note- 1. Attach Signed Photocopy of Specific Agreed Point mentioned in Service Contract.

2. Attach the duly filled and signed Construction Power - Electrical Checklist – Annexure– A