Epcl Discipline Wise Scope
Epcl Discipline Wise Scope
22 Pump for Clarifier Water Pit (PT-8708) Procurement WW-I New New
The general concept of the advanced oxidation process, the CATADOX being the top of the
range, combines ozone, hydrogen peroxide, a proprietary catalyst and UV oxidation.
Advance Oxidation for 108m3/hr. Treated Effluent
65 Procurement WW-II New New
from Wastewater-02 Advance oxidation is recommended to break down the in organics in wastewater plant -02,
for future recycling plant which will be installed at the reject RO water and remaining
108m3/hr. Wastewater-2 Plant.
67 P-4701 A/B for ETP Intake Tank (V-4701) Procurement ETP-I Modification Existing
81 Back Wash Configuration Piping ETP-I New New Add Back wash filter configuration
Complete revamping of pits with protective coating recommended in annexure-XII Nuet pits are damaged by acid and caustic attack, steel
client to confirm if exiting pit are to be
Neutralization of Wastewater in to respective structure is exposed. Existing RCC structured Nuet pits are
demolised and replaced with tank system or
81 Protective Coating for Nuet Pits Process DM New Existing pits with continuous agitation/mixing and pH controllers for real time monitoring and not suitable for neutralization a proper repairing and
existing pits to be coated with recommended
discharging. As per EPCL, neutralization pits are to be eliminated and replace with tank and protective coating is required for reliable operation of
coating.
design neutralization system. Please see page #64 of BEP for proposed solution system.
Existing RO Membranes are not suitable for wastewater. Extra fouling resistance RO Plant is designed with two trains. Each train has
membranes are required for a trouble free system. 60 membranes producing about 43m3/hr.
Permeate from each train.
DUPONT FORTILIFE CR100 RO membranes ( If replacement is due)
The performance curve of High Pressure pump give max. 13.5 bar at 57 m3/hr. For pressure
RO Plant high pressure pump is not meeting the Pressure
87 RO Plant high pressure pump Procurement UF & RO Re-designing Existing or head increase pump supplier could advise what should be done.
head for both Hydranautics and Dupont membranes
Annexure-III HP PUMP DATA SHEET
SS304 /SS316 isn’t recommended for this value. Low pressure piping should be non
metallic. However high pressure should be Duplex SS.
Annexure-IX
Piping Hydraulics - Pipeline Size and Material Selection
97 HCL Dosing Pump (CEB Acid) Procurement 2ND UF & RO New New
99 NaOH Dosing Pump (CEB Alkali) Procurement 2ND UF & RO New New
106 Anti scalent Dosing Pump Procurement 2ND UF & RO New New
114 Instrumentation for UF and RO System Instrumentation 2ND UF & RO New New
Annexure-VIII
List of Monitoring Instruments,
cable ladders installation
DCS/ESD installation of cabinets
LEL monitors
new and
117 Electrical Electrical existing/new Earthing, lighting, cable tray installation, cable terminations, DBs &JBs, CCTV scope
modification/repair
GENERAL QUERIES:
1. CLIENT TO CONFIRM IF SCOPE OF WORK INCLUDE THE INSTALLATION/CONSTRUCTION/MAINTENACE/INTEGRATION OF STORAGE TANKS FOR CHEMICAL AGENTS BEFORE BEING TRANSFERRED TO DOSING TANKS.
2. SCOPE OF PIPING AND REQUIRED INSTRUMENTATION AND ELECTRICAL WORK CAN ONLY BE ASSESSED AFTER SITE VISIT AND PROVISON OF EXISITING PLANT LAYOUT AND SPACE ALLOTED FOR NEW PLANTS
3. FOR CIVIL WORK OF ROADS, STORM WATER AND WALKWAYS, SITE VISIT IS REQUIRED.
4. CLIENT TO CONFIRM PIPE MATERIAL AND SPEC.
5. CLIENT TO PROVIDE SAMPLE POINT AND ISOLATION VALVE LOCATIONS.
6. CLIENT TO CONFIRM PIPE ROUTES, CURRENT EQUIPMENT GADs AND LAYOUT FOR SCOPE OF CLARIFICATION OF PIPE RACKS, SLEEPERS, CABLE TRAY LAYOUTS AND FIREFIGTHING
7. CLIENT TO CONFIRM THAT FOR SEDIMENTATION TANKS OR WHERE APPLICABLE, SCRAPPER AND SKIMMER IS REQUIRED IN VENDOR SCOPE OR NOT.