SCOPE OF WORK

EPCL WASTEWATER TREATMENT INTEGRATION PROJECT


Sr.# Item Discipline Unit Type of Scope Status Proposed Existing Remarks

1 PU-8701A/B Pump for PT-8701 Procurement WW-I Modification New

2 Mixing system PT-8701 Procurement WW-I New New

3 Pre-Settler Lamella Clarifier-NEW Civil WW-I New New

4 Lamella Sheets Procurement WW-I New New

5 Neutralization tank (PT-8702) Civil WW-I Modification Existing

6 Flash mixer Neutralization tank (PT-8702) Procurement WW-I New New

7 Acid (HCL) Dosing tank Procurement WW-I New New

8 Acid (HCL) Dosing Pumps Procurement WW-I New New

9 Caustic (NaOH) Dosing Tank Procurement WW-I New New

10 Caustic (NaOH) Dosing Pump Procurement WW-I New New

11 Coagulation tank (PT-8703) Civil WW-I Modification Existing

12 Flash mixer Coagulation Tank (PT-8703) Procurement WW-I New New

13 PAC Dosing Tank Procurement WW-I New New

14 PAC Dosing Pump Procurement WW-I New New

15 Flocculation tank (PT-8703) Civil WW-I Modification Existing

16 FT Mixer Flocculation tank (PT-8703) Civil WW-I New New

17 Anionic Polyelectrolyte Dosing Tank Procurement WW-I New New

18 Anionic Polyelectrolyte Dosing Pump Procurement WW-I New New

19 Sedimentation Basin(PT-8704) Civil WW-I Modification Existing

20 Lamella plates for PT-8704 Procurement WW-I New New

21 Sludge Transfer pumps Procurement WW-I New New

22 Pump for Clarifier Water Pit (PT-8708) Procurement WW-I New New

23 Sludge Holding Tank-1 Civil WW-I New New

24 Screw Press Feed Pumps Procurement WW-I New New

25 Screw Press-1 Procurement WW-I New New

26 Filtrate Pit Civil WW-I New New

27 Filtrate Transfer Pumps Procurement WW-I New New

28 Sludge Holding Tank-2 (PT-8706) Civil WW-I Modification Existing

29 Screw Press Feed Pumps Procurement WW-I New New

30 Screw Press-2 Procurement WW-I New New

31 Filtrate Pit (PT-8707) Civil WW-I Modification Existing

Client to confirm, that Cationic Polyelectolyte


32 Cationic Polyelectrolyte Dosing Tank Procurement WW-I New New tank is required as its not showing in current
PFD.

33 Dosing pumps Procurement WW-I New New


SCOPE OF WORK
EPCL WASTEWATER TREATMENT INTEGRATION PROJECT
Sr.# Item Discipline Unit Type of Scope Status Proposed Existing Remarks

34 Pumps for Equalization Tank (V-4503) Procurement WW-II New New

Mixing system (for Eq tank and pH


35 Procurement WW-II New New
Regulator tank)

36 pH Regulator tank Civil WW-II Modification Existing

Mixing system (for Eq tank and pH Regulator


36 Procurement WW-II New New
tank) for V-4505

37 Caustic (NaOH) Dosing Tank Procurement WW-II New New

38 Caustic Dosing pumps Procurement WW-II New New

39 Aeration Tank (V4511 A/B) Civil WW-II Modification Existing

40 Air blowers Procurement WW-II New New

41 Air diffusers Procurement WW-II New New

42 Coagulation tank (V-4521 A/B) Civil WW-II New Existing

43 Flash mixer Procurement WW-II New Existing

44 PAC Dosing Tank Procurement WW-II New Existing

45 Dosing pumps Procurement WW-II New Existing

46 Flocculation tank (V-4523 A/B) Civil WW-II New Existing

47 FT Mixer Flocculation tank (PT-8703) Procurement WW-II New Existing

48 Anionic Polyelectrolyte Dosing System Procurement WW-II New New

49 Dosing pumps Procurement WW-II New New

Nutrients Dosing System


50 Procurement WW-II New New
Phosphoric Dosing System

51 Urea Dosing System Procurement WW-II New New

52 Secondary Clarifier (V-4525 A/B) Civil WW-II New Existing

53 Sludge Scraper Procurement WW-II New New

54 RAS/WAS pumps Procurement WW-II New New

55 Weir Plate Mechanical WW-II New New

56 Observation tank (V-4528 B) Procurement WW-II New Existing

57 Effluent pumps (P-4529 A/B) Procurement WW-II New Existing

58 Condensation Tank (4541) Civil WW-II New Existing

59 Screw Press Feed Pumps Procurement WW-II New Existing

60 Screw Press-3 Procurement WW-II New Existing


MOC: Duplex SS

61 Filtrate Pit (V-4545) Civil WW-II New Existing

62 Filtrate Transfer Pumps Procurement WW-II New Existing

63 Cationic Polyelectrolyte Dosing Tank Procurement WW-II New New

64 Cationic Polyelectrolyte Dosing pumps (PAM) Procurement WW-II New Existing

The general concept of the advanced oxidation process, the CATADOX being the top of the
range, combines ozone, hydrogen peroxide, a proprietary catalyst and UV oxidation.
Advance Oxidation for 108m3/hr. Treated Effluent
65 Procurement WW-II New New
from Wastewater-02 Advance oxidation is recommended to break down the in organics in wastewater plant -02,
for future recycling plant which will be installed at the reject RO water and remaining
108m3/hr. Wastewater-2 Plant.

Client to confirm, if modification is required in


66 ETP Intake Tank (V-4701) Civil ETP-I Modification Existing
intake tank

67 P-4701 A/B for ETP Intake Tank (V-4701) Procurement ETP-I Modification Existing

Client to confirm, if mechanical filter is to be


68 F-4701 Mechanical filter ETP-I Existing
modified or not.

Client to confirm dosing availability for


69 Coagulation tank (V-4703 A/B) Civil ETP-I New Existing
coagulation tanks

70 PAC Dosing System tank Procurement ETP-I New New

71 Dosing pumps Procurement ETP-I New New


SCOPE OF WORK
EPCL WASTEWATER TREATMENT INTEGRATION PROJECT
Sr.# Item Discipline Unit Type of Scope Status Proposed Existing Remarks

Client to confirm dosing availability for


72 Flocculation tank (V-4704 A/B) Civil ETP-I New Existing
coagulation tanks

73 FT mixer (AG4704 A/B/C/D) Procurement ETP-I New Existing

74 Anionic Polyelectrolyte Dosing Tank Procurement ETP-I New New

75 Anionic Polyelectrolyte Dosing Pump Procurement ETP-I New New

76 Settling tank (V-4705 A/B) Civil ETP-I New Existing

77 Lamella plates Procurement ETP-I New Existing

78 Sludge Transfer pumps Procurement ETP-I New Existing

Client to confirm any change/modification in


79 CFS Product Water Tank (V-4706) Civil ETP-I New Existing
Hypo Dosing system P-4721

Client to confirm any change/modification in


80 Sand Filters (NEW ADDITION) Mechanical ETP-I New New existing Activated carbon filter (tank, piping
systems) due to addition of Sand Filters.

81 Back Wash Configuration Piping ETP-I New New Add Back wash filter configuration

Complete revamping of pits with protective coating recommended in annexure-XII Nuet pits are damaged by acid and caustic attack, steel
client to confirm if exiting pit are to be
Neutralization of Wastewater in to respective structure is exposed. Existing RCC structured Nuet pits are
demolised and replaced with tank system or
81 Protective Coating for Nuet Pits Process DM New Existing pits with continuous agitation/mixing and pH controllers for real time monitoring and not suitable for neutralization a proper repairing and
existing pits to be coated with recommended
discharging. As per EPCL, neutralization pits are to be eliminated and replace with tank and protective coating is required for reliable operation of
coating.
design neutralization system. Please see page #64 of BEP for proposed solution system.

AREA 800 WASTEWATER TREATMENT SYSTEM-


82 Mechanical A-800 New New
EDC-VCM STRIPPING-MF-801A

Client to provide annexure XV

AREA 800 WASTEWATER TREATMENT SYSTEM-


83 Piping
EDC-VCM STRIPPING-MF-801A
A-800 New New

AREA 800 WASTEWATER TREATMENT SYSTEM-


84 Procurement
EDC-VCM STRIPPING-MF-801A
A-800 New New Client to provide annexure XVI

Client to confirm type of exhanger in use and


AREA 800 WASTEWATER TREATMENT SYSTEM- that new exchanger to be installed of same
85 Mechanical A-800 New New
EDC-VCM STRIPPING-MF-801A capacity. And the its location as it would impact
the scope of piping, mechanical and civil work.

Existing RO Membranes are not suitable for wastewater. Extra fouling resistance RO Plant is designed with two trains. Each train has
membranes are required for a trouble free system. 60 membranes producing about 43m3/hr.
Permeate from each train.
DUPONT FORTILIFE CR100 RO membranes ( If replacement is due)

86 UF AND RO PLANT Process UF & RO Modification Existing

The performance curve of High Pressure pump give max. 13.5 bar at 57 m3/hr. For pressure
RO Plant high pressure pump is not meeting the Pressure
87 RO Plant high pressure pump Procurement UF & RO Re-designing Existing or head increase pump supplier could advise what should be done.
head for both Hydranautics and Dupont membranes
Annexure-III HP PUMP DATA SHEET

SS304 /SS316 isn’t recommended for this value. Low pressure piping should be non
metallic. However high pressure should be Duplex SS.

88 Piping Material Piping UF & RO Modification Existing

Annexure-IX
Piping Hydraulics - Pipeline Size and Material Selection

89 2nd UF and RO Plant Process 2ND UF & RO New New

90 UF Feed Pump Procurement 2ND UF & RO New New

91 Sand Filters Mechanical 2ND UF & RO New New

92 Sand Filters Piping 2ND UF & RO New New

92 Ultra Filtration Membranes Procurement 2ND UF & RO New New

93 Air Blower Procurement 2ND UF & RO New New


SCOPE OF WORK
EPCL WASTEWATER TREATMENT INTEGRATION PROJECT
Sr.# Item Discipline Unit Type of Scope Status Proposed Existing Remarks

94 Backwash Pump Procurement 2ND UF & RO New New

95 Sodium Hypochlorite Dosing Pump Procurement 2ND UF & RO New New

96 Sodium Hypochlorite Dosing Tank Procurement 2ND UF & RO New New

97 HCL Dosing Pump (CEB Acid) Procurement 2ND UF & RO New New

98 HCL Dosing Tank Procurement 2ND UF & RO New New

99 NaOH Dosing Pump (CEB Alkali) Procurement 2ND UF & RO New New

100 NaOH Dosing Tank Procurement 2ND UF & RO New New

101 Cleaning Pump Procurement 2ND UF & RO New New

102 CIP Tank Procurement 2ND UF & RO New New

103 UF Filtrate Storage Tank Procurement 2ND UF & RO New New

104 RO Feed Pump Procurement 2ND UF & RO New New

105 Cartridge Filter Procurement 2ND UF & RO New New

106 Anti scalent Dosing Pump Procurement 2ND UF & RO New New

107 Dosing Tank Procurement 2ND UF & RO New New

108 Biocide Dosing Pump Procurement 2ND UF & RO New New

109 NaOH Dosing Tank Procurement 2ND UF & RO New New

110 High Pressure Pump Procurement 2ND UF & RO New New

111 Pressure Vessels Mechanical 2ND UF & RO New New

112 RO Cleaning Pump Procurement 2ND UF & RO New New

113 CIP Tank Procurement 2ND UF & RO New New

114 Instrumentation for UF and RO System Instrumentation 2ND UF & RO New New

Annexure-VIII
List of Monitoring Instruments,
cable ladders installation
DCS/ESD installation of cabinets
LEL monitors

115 Instrumentation Scope Instrumentation New New

Roads, storm water, chemical drain channels, new and


116 Civil existing/new site visit to confirm details
walkways and other infrastructure modification/repair

new and
117 Electrical Electrical existing/new Earthing, lighting, cable tray installation, cable terminations, DBs &JBs, CCTV scope
modification/repair

GENERAL QUERIES:

1. CLIENT TO CONFIRM IF SCOPE OF WORK INCLUDE THE INSTALLATION/CONSTRUCTION/MAINTENACE/INTEGRATION OF STORAGE TANKS FOR CHEMICAL AGENTS BEFORE BEING TRANSFERRED TO DOSING TANKS.
2. SCOPE OF PIPING AND REQUIRED INSTRUMENTATION AND ELECTRICAL WORK CAN ONLY BE ASSESSED AFTER SITE VISIT AND PROVISON OF EXISITING PLANT LAYOUT AND SPACE ALLOTED FOR NEW PLANTS
3. FOR CIVIL WORK OF ROADS, STORM WATER AND WALKWAYS, SITE VISIT IS REQUIRED.
4. CLIENT TO CONFIRM PIPE MATERIAL AND SPEC.
5. CLIENT TO PROVIDE SAMPLE POINT AND ISOLATION VALVE LOCATIONS.
6. CLIENT TO CONFIRM PIPE ROUTES, CURRENT EQUIPMENT GADs AND LAYOUT FOR SCOPE OF CLARIFICATION OF PIPE RACKS, SLEEPERS, CABLE TRAY LAYOUTS AND FIREFIGTHING
7. CLIENT TO CONFIRM THAT FOR SEDIMENTATION TANKS OR WHERE APPLICABLE, SCRAPPER AND SKIMMER IS REQUIRED IN VENDOR SCOPE OR NOT.