You are on page 1of 1

SYC EIA Project - KPI's

Group
Productivity Technician Type
Activity Unit No. of
(Unit/Day)
Persons Forman Instrumentation Electrical
Welders Helpers Fitter
Technician Skilled Worker
Support Fabrication Kg 175 4 1 1 1 1
Tray Fabrication No. 15 (Mixed Types) 3 1 1 1
Support Erection No. 50 4 1 1 1 1
Tray Installation
lm 100 (Straight) 4 1 1 1 1

Cable Laying
lm 500 13 1 2 10

Cable Systemize
lm 500 3 1 2

Cable Connection
No. 30 2 1 1

Meggering and Continuity Test


No. 30 3 1 1 1

Instrumentation Device Calibration No. 20 3 1 1 1


Loop Check
No. 10 4 1 2 1

Lighting System
No. 16 4 1 1 1 1

Cabinet Installation No. 2 5 1 2 2


Air Header No. 6 3 1 1 1
Tube SS
lm 25 3 1 1 1

Tube Connection No. 10 3 1 1 1

5.029-16 - KPI's