DIFFICULTY
1. QUOTE:
- Standard quote format in which all the costs we will incur to manufacture and send the samples are
displayed:
RAW MATERIAL MEASURES CHARACTERISTICS HEIGHT LONG
AGLOMERADO 16 4120X2070X16 SIN EMPALME 188 1373
BASIC WHITE Ancho PP 395 mm - - -
COLA 45/m2 MERMA 2% - -
SIN CANTO - - - -
SIN ESPIGAS - - - -
OPERATOR
ASSUMPTIONS PRODUCTIVITY S MACHINE CHANGE
BARBERAN 1 15 ml/min 2 personas Standard
KOCH 1 10 piezas/min 2 personas Standard
KOCH 6 10 piezas/min 2 personas Standard
- Investments:
- MOQ: 260/pcs
- Qty/pallet: 260/pcs.
We have created an excel sheet to carry out the planning in a timely manner, this is the implementation
plan M:\ADVANCED\GERENCIA\Jorge\Foldeco\Cajones\Ikea\2024\Samples\IP M9052732 1356X179.xlsx
We have created a sample reference in our internal program "Management", we have registered this
reference in the implementation plan.
SAMPLE DEVELOPMENT MONITORING: MEDIUM
DIFFICULTY
OPERATOR
ASSUMPTIONS PRODUCTIVITY S MACHINE CHANGE
BARBERAN 1 15 ml/min 2 personas Standard
KOCH 1 10 piezas/min 2 personas Standard
KOCH 6 10 piezas/min 2 personas Standard
Establishment of assumptions.
- Potential problems:
Coating: It is the same as reference ND0000024712, without potential problems. Standard speed.
First drill: 2 potential machines, in one we have to make a small adjustment to a head to be able to have
two alternatives. The machine that is already prepared has full capacity but the other is at 45% so we
assume that we will do it on Koch 1. Standard speed.
Second drill pass: We will need an extra collaborator because, since the piece is so large, the unloader
cannot work at maximum speed. We do not expect excessive breakage of bits. Standard speed with two
workers or 50% with one worker. The machine is 43% in use. Other potential machines with worse
productivity.
All information relevant to sample development, order creation, order planning, raw materials
(inventory) planning, delivery dates is shared.
Review of assumptions.
New potential problem: Confirm that it is not necessary to cut the part after coating because the Koch 1
cannot profile as much.
Raw materials: OK
Tools: OK
Machine availability: OK
3. CREATION OF PROTOTYPES
We create an internal order with number 2024000289 using our “Management” program with which we
will have information about the quantity, machines and plans.
3rd meeting 02/06/2024 Attendees: full team. Meeting with the entire internal team to share the
implementation plan.
We create reports for quality control and efficiency. We discussed the assumptions of the machines,
possible incidents in manufacturing and finished product, theoretically.
We review the assumptions of the machines and possible incidents that may arise during the
manufacturing of the 1st batch, real, it is a real evaluation of the 1st batch.
Internal meeting to analyze quality and productivity reports, and take action if necessary.
5. SAMPLE DELIVERY
Meeting with the internal team to verify assumptions and prepare next steps 02/22/2024.
The team review of all assumptions, circumstances and results will finally give rise to the Quality Plan
through which to create a standard quality control procedure. M:\QUALITY\Ikea\QUALITY PLAN.rtf
Responsible: Borja O.