1. I attach a revised report by the International Staff on templates for Project Proposals
and Type B Cost Estimates submitted by Host Nations. This document is scheduled for the
Investment Committee meeting on 25 April, for agreement.
NATO UNCLASSIFIED
-1-
NHQD288212
NATO UNCLASSIFIED
Releasable to Sweden
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
INTRODUCTION
1. In June 2018, the Council agreed the new Common Funded Capability Delivery
Governance Model (CFCDGM, reference (a)). The model’s goal is to accelerate the delivery
of required capabilities that meet military requirements within agreed scope, timelines and
cost. As part of its work to operationalise the CFCDGM, in accordance with guidance from
the Resource Policy and Planning Board (RPPB) (reference (b), the Investment Committee
agreed the elements that should form the basis for Project Proposals submitted by Host
Nations at references (c) and (d). With reference (e), the Committee further agreed
measures to adapt existing Capability Package (CP) processes and products to align with
the CFCDGM.
2. In addition, the decision to broaden the use of common funding by Allies at the 2022
Madrid Summit provides an impetus for all stakeholders in the resource community to
implement ‘better, faster, smarter’. As briefed to the Committee on 12 July 2022 (reference
(f)), one of the improvement measures envisioned is the development of ready-to-use
templates for management products presenting the right level of information for governance
decision-making.
NATO UNCLASSIFIED
1-1
NATO UNCLASSIFIED
Releasable to Sweden
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
AIM
4. Seeking to align governance processes under the CP Process with the Model, this
document provides Host Nations a common format for the submission of Project Proposals
and Type B Cost Estimates and elaborates on the guidance issued in reference (c).
CONSIDERATIONS
5. As noted by the RPPB at reference (b), the CFCDGM introduces a culture change
at all levels with regard to the interaction between Nations at the governance level, the lead
management authority and the Staffs. For the IC, this means that, in practice, Project
Proposals submitted by the Host Nation, together with the Staff advice, will be the basis on
which the IC grants the single project-level authorisation (reference (c)). This is unlike the
arrangements under the CP Process, whereby the Staff Screening Report served this
purpose.
6. For Host Nations, the implication is such that technical and engineering details,
which are important for the development of Staff advice and coordination within the
Capability Management Function (CMF), should not obstruct the essential and strategic
elements required for a governance decision. Clearly, there is a requirement within the host
nation organisation to prepare, hold and manage all required project data, as per recognised
programme/project management disciplines, and to make this data available within the CMF
to ensure full coordination. On the other hand, this level of detail is not required for
governance decision-making.
8. With the view to further align governance processes under the CP Process with the
Model, the templates in Appendices 1, 2, and 3 are intended to be used for projects in CPs
and CPPs, and as such, replace existing guidance for the submission of TBCEs. In addition,
further work is required to develop a policy framework addressing risk management and
tolerances, as well as its application to projects in Capability Packages.
9. The template is based on the Committee’s decisions at references (c) and (d),
whereby the core elements of a Project Proposal should consist of:
9.1. a Project Overview that provides a statement of how and when a project’s
objectives are to be achieved, by showing the major products, activities and resources
required;
NATO UNCLASSIFIED
1-2
NATO UNCLASSIFIED
Releasable to Sweden
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
9.2. the Project Requirements including scope, schedule and (through-life) cost, noting
that the forecast expenditures and project implementation milestones must be recorded in
the Common-funded Integrated Resource Information System (CIRIS);
9.4. a Policy Compliance Statement confirming that the Project Proposal has been
developed in accordance with IC guidelines, as per reference (d), to be signed by the senior
leadership of the Host Nation. This is in accordance with the accountability arrangements
agreed by the RPPB at reference (b).
10. The template is designed to be succinct, with the main objective of highlighting key
information required for governance decision-making.
11. Appendicesx 2 & 3 provides a templates for the submission of technical information
supporting the C3/CIS/C4ISR or Civil Works proposals (respectively), with information
that could be required for the development of the Staff advice. Host Nations are invited to
consult with the Staff on the applicability of each element for their particular project.
12. The technical appendix also provides Host Nations with the opportunity to inform
the Committee of their efforts to incorporate gender perspectives in the development of the
Project Proposal, as applicable. As part of the NATO Action Plan for the Implementation of
the NATO/EAPC Policy on Women, Peace, and Security 2021-2025 (reference (g)), NATO
has committed to the integration of gender perspectives in capability development, including
the development of Capability Programme Plans. With reference (h), the Council noted the
RPPB and Military Committee’s conclusions that Capability Programme Plans and Joint
Staff Reports will specifically address gender perspectives for governance consideration at
Gate 2. Host Nations are encouraged, as applicable, to continue these efforts at Gate 3 to
ensure that common funded capabilities delivered through the NSIP have no differentiated
effect on women and men.
RECOMMENDATIONS
13.1. agree that the templates at Appendices 1, 2, and 3 will serve as the principal format
in which Project Proposals and Type B Cost Estimates are to be submitted by Host Nations;
13.2. agree that these templates be used for projects in Capability Programme Plans and
Capability Packages by no later than 01 September 2023January 2025;
13.3. invite Host Nations to engage and coordinate with the Staff as early as possible,
with the view of supporting the timely planning, submission, and technical advice of Project
Proposals;
NATO UNCLASSIFIED
1-3
NATO UNCLASSIFIED
Releasable to Sweden
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
13.4. invite the International Staff to develop guidance for Host Nations to request project-
level tolerances based on a risk management framework and present it to the Committee
by no later than the end of MarchJune 2023;
13.5. propose that the Staff conduct a training for HN personnel- regarding the
implementation of the templates and familiarization with the Risk Management Framework
by the end of JuneJuly 2023;
13.6. invite the International Staff to conduct a review and assessment of the
implementation of this template and present it to the Investment Committee for discussion
by September 2025January 2026.
Benjamin WILDER
Portfolio Delivery Branch
NATO Office of Resources
NATO UNCLASSIFIED
1-4
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 1
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
OVERVIEW:
1. This section provides a brief overview of the request by the Host Nation, and it is
intended to support governance review and authorization. It should be short and concise
with any detailed information provided as appendices or annexes.
2. Summary Table
SUMMARY
Project Description Short description of the project to be delivered.
CURRENT STATUS:
Through-life Estimated Date of Project Completion (month/year)
CapabilityProject Timeline Estimated End of In-Service Life (month/year)
Through-life Cost Estimate Investment - kEUR XXX,XXX from [year] to [year]
(Investment and Operations O&M – Budget(s)/Services impacted (year and amount)
& Maintenance)
SCOPE:
3. This section describes the project scope linked with the overall capability delivery
context and its traceability to the capability scope approved in the Capability Package (CP)
or Capability Programme Plan (CPP). In coordination with the Strategic Commands (SCs)
via the Capability Management Function (CMF), this section should also include an overview
of DOTMLPFI [Doctrine, Organization, Training, Material, Leadership, Personnel, Facilities,
& Interoperability] capability components, which are addressed by the project.
NATO UNCLASSIFIED
1-5
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 1
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
SCHEDULE:
4. This section provides a consolidated schedule chart, consistent with the CP/CPP,
describing the major project activities and milestones related to time. In coordination with
the SCs via the CMF, any deviations from CP/CPP schedule shall be highlighted with
operational impact.
THROUGH-LIFE COST:
7. For projects under the CPP process, in line with the RPPB’s decision on
operationalising the 2018 agreed CFCDGM, the Proposal should include a statement from
the Host Nation that the Project Proposal was developed and coordinated in full accordance
with the 2018 agreed Council decisions on the Common Funded Capability Delivery
Governance Model and the RPPB operationalisation guidelines.
8.2. the implementation timelines have been estimated on the basis of a developed Level
(X) Work Breakdown Structure (WBS)/Product Breakdown Structure (PBS) of the project
master programme having made necessary allowances to provide for potential delays in
activities and is in accordance with the IOC and FOC timeline stipulated in the military
requirements from the CP/CPP;
8.3. the project costs, the investment portion, have been estimated and represent a solid
and realistic basis for implementation and decision-making;
NATO UNCLASSIFIED
1-6
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 1
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
8.4. the project has been subject to a risk analysis process based on the [specify] method
which has been used to calculate risk and uncertainty of the project. Using this method, the
host nation anticipates that the cost level defined represents a level where there is a
probability of [xx]% that the project costs will not exceed this level.
RECOMMENDATIONS:
9. This section should include the recommendations to the IC- namely that:
NATO UNCLASSIFIED
1-7
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
This appendix provides a common format for further information which may be
required for the technical screening of a TBCE or PP, and for many projects, some of the
areas below will be optional or not applicable. Therefore, each section of the appendix is
marked as either “Required” or “If applicable.” Host Nations should coordinate with the Staff,
at the earliest possible opportunity, in advance of drafting and submission of the proposal to
receive guidance on recommended and/or required sections in support of technical
screening by the Staff. Maximum use should be made of summary tables, drawings, and
charts, which may be incorporated into the text or attached as annexes.
OVERVIEW:
1.1.1. (If applicable) the parent Capability Package (CP)/Capability Programme Plan
(CPP) (or lack thereof as appropriate);
1.2.2. (If applicable) key legal requirements, codes, or standards applicable to the project;
1.2.3. (If applicable) any known departure from established NATO policy or procedures.
NATO UNCLASSIFIED
1-8
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
appropriate level of the Capability Management Authority (CMA) for coordination and
resolution.
3. CAPABILITY REQUIREMENTS (Required): This section details the Capability
requirements applicable to the project, as they have been defined, or referred to, in the
approved Capability Programme Plan (CPP)/ Capability Package (CP) and/or Capability
Requirements Brief (CRB).
4. COORDINATION (If applicable): The appendix should also state whether the
proposal has been reviewed by other entities (e.g. Working Group of National Technical
Experts (WGNTE), Change Control Board, and/or Steering Committee) or whether other
supporting documents are already available (e.g. a Concept of Operations, a System
Specific Security Requirement Statement and Architectural Operational View Templates).
PROJECT REQUIREMENTS:
NATO UNCLASSIFIED
1-9
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
6.1. SCHEDULE CHART (Required): The appendix should contain a schedule chart,
consistent with the CP/CPP, describing the major project activities and milestones related
to time. Details of the models for schedule estimation should be provided.
6.2.1.4. Date of Authority to Issue the Invitation for Bids (IFB) Authorisation;
6.2.1.9. If multiple phases of a project are covered in the appendix, the milestones should
be described for each phase by establishing each phase/horizon/wave with a different
increment with a unique set of milestones (for reporting purposes to the IC).
NATO UNCLASSIFIED
1-10
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
6.2.2.8. If multiple phases of a project are covered in the appendix, the milestones should
be described for each phase.
6.3. ASSUMPTIONS (If applicable): This section should provide any project assumptions
which will or may affect the schedule.
6.6. SCHEDULE, MILESTONE, AND KPIs FOR RISK MANAGEMENT (Required): This
section should describe the schedule milestones for risk management and mitigation.
6.7. CRITICAL PATH ANALYSIS (Required): The project schedule should include a
discussion of the critical path analysis for the project.
7.1.1. Explanation of all Support and Overhead provisions and costs, including personnel
(NATO employed), maintenance, operating and running costs;
7.1.2. Explanation of the method of cost estimation. Use of parametric cost estimation, a
statistical quantitative approach considering historic and market data, at granularity levels
according to complexity, is highly preferred by governance.
NATO UNCLASSIFIED
1-11
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
7.3. CURRENCY (Required): In most cases, the cost estimate is prepared using the
currency of the territorial host nation (as required, totals are eventually converted in Euro
through official NATO rates).
8.2.1. (Required) A high-level operational concept graphic- detailing how the project fits
into the overarching capability programme/portfolio and operational environment;
8.2.2. (Required) A conceptual system diagram- detailing the system design, architecture,
components, boundaries, and internal & external interfaces;
NATO UNCLASSIFIED
1-12
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
10. SERVICE INTEGRATION (If applicable): This section describes the integration of
the solution into existing systems or services.
14. RISKS (RequiredIf applicable): This section should provide a thorough risk
analysis, risk register, and mitigation/management plan, with detailed elements,
interdependencies, and activities assessed and included within the project plan. This section
describes the Risk Management Plan presented by the Host Nation (ensuring that risks are
realistic and relevant) and covers risks, opportunities, and key assumptions. Changes
introduced after Decision Gate 2 approval should be highlighted and justified. Risks initially
NATO UNCLASSIFIED
1-13
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
identified at programme level and which could be managed at project level shall be
transferred to the project.
18. LIFE-CYCLE SUPPORT (Required): Provide details of plans for project Logistics
Support, Configuration Management, and in-life operations.
20. LINKAGES & DEPENDENCIES (If applicable): A description of the internal and
external linkages and dependencies with other projects, programmes, or agencies as well
as other DOTMLPFI elements. Analysis and description of interrelated works (such as
Communications for a Civil Works project), and links to other investment/initiatives (NATO,
national, multinational, etc.). For external dependencies, ensure that associated milestones
are included in the project schedule (under Section 6.4).
21. ASSUMPTIONS, LIMITATIONS, & CONSTRAINTS (If applicable): This section
shall provide the assumptions, limitations, and constraints that may impact the realization of
the project benefits.
22. VERIFICATION AND VALIDATION (Required): This section should describe how,
who, and when the testing, verification, and validation will be performed to ensure that
project deliverables meet the project acceptance criteria.
23. POLICY COMPLIANCE (If applicable): The technical solution proposed for
implementation should meet the Minimum Military Requirement (MMR) in the most cost
effective manner and follow all applicable Technical Standards and NATO Policies. Any
known deviation from NATO policies or standards should be described and justified.
NATO UNCLASSIFIED
1-14
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 2
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
NATO UNCLASSIFIED
1-15
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
This appendix provides a common format for further information which may be
required for the technical screening of a TBCE or PP, and for many projects, some of the
areas below will be optional or not applicable. Therefore, each section of the appendix is
marked as either “Required” or “If applicable.” Host Nations should coordinate with the Staff,
at the earliest possible opportunity, in advance of drafting and submission of the proposal to
receive guidance on recommended and/or required sections in support of technical
screening by the Staff. Maximum use should be made of summary tables, drawings, and
charts, which may be incorporated into the text or attached as annexes.
OVERVIEW:
1.1.1. (If applicable) the parent Capability Package (CP)/Capability Programme Plan
(CPP) (or lack thereof as appropriate);
1.2.2. (If applicable) key legal requirements, codes, or standards applicable to the project;
1.2.3. (If applicable) any known departure from established NATO policy or procedures.
NATO UNCLASSIFIED
1-16
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
appropriate level of the Capability Management Authority (CMA) for coordination and
resolution.
3. CAPABILITY REQUIREMENTS (Required): This section details the Capability
requirements applicable to the project, as they have been defined, or referred to, in the
approved Capability Programme Plan (CPP)/ Capability Package (CP) and/or Capability
Requirements Brief (CRB).
4. COORDINATION (If applicable): The appendix should also state whether the
proposal has been reviewed by other entities (e.g. Working Group of National Technical
Experts (WGNTE), Change Control Board, and/or Steering Committee) or whether other
supporting documents are already available (e.g. a Concept of Operations, a System
Specific Security Requirement Statement and Architectural Operational View Templates).
PROJECT REQUIREMENTS:
For most Infrastructure projects, the majority of the information in this section will
usually be provided in a technical report by an External A/E firm.
NATO UNCLASSIFIED
1-17
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
& formal project milestones- taking into account the risks, assumptions and constraints
applicable to the project.
6.1. SCHEDULE CHART (Required): The appendix should contain a schedule chart,
consistent with the CP/CPP, describing the major project activities and milestones related
to time. Details of the models for schedule estimation should be provided.
6.2.1.4. Date of Authority to Issue the Invitation for Bids (IFB) Authorisation;
6.2.1.9. If multiple phases of a project are covered in the appendix, the milestones should
be described for each phase by establishing each phase/horizon/wave with a different
increment with a unique set of milestones (for reporting purposes to the IC).
NATO UNCLASSIFIED
1-18
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
6.2.2.8. If multiple phases of a project are covered in the appendix, the milestones should
be described for each phase.
6.3. ASSUMPTIONS (If applicable): This section should provide any project assumptions
which will or may affect the schedule.
6.6. SCHEDULE, MILESTONE, AND KPIs FOR RISK MANAGEMENT (Required): This
section should describe the schedule milestones for risk management and mitigation.
6.7. CRITICAL PATH ANALYSIS (Required): The project schedule should include a
discussion of the critical path analysis for the project.
7.1.1. Explanation of all Support and Overhead provisions and costs, including personnel
(NATO employed), maintenance, operating and running costs;
7.1.2. Explanation of the method of cost estimation. Use of parametric cost estimation, a
statistical quantitative approach considering historic and market data, at granularity levels
according to complexity, is highly preferred by governance.
NATO UNCLASSIFIED
1-19
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
7.3. CURRENCY (Required): In most cases, the cost estimate is prepared using the
currency of the territorial host nation (as required, totals are eventually converted in Euro
through official NATO rates).
7.4. OPERATION & MAINTENANCE (O&M) COSTS (If applicable): A financial planning
profile for O&M costs funded by the MB, showing the current and future costs, and indication
the transition from legacy to new capability, taking into account the warranty for new
equipment.
7.5. NATO WORKFORCE (If applicable): If relevant for NSIP funding, overview of
additional Workforce requirements for the NATO Command Structure and for C3 projects
with the NCI Agency, quantified in Full Time Equivalent FTE.
For most Infrastructure projects, the majority of the information in this section will
usually be provided in a technical report by an External A/E firm.
8.2.1. (Required) A high-level operational concept graphic- detailing how the project fits
into the overarching capability programme/portfolio and operational environment;
8.2.2. (Required) A conceptual system diagram- detailing the system design, architecture,
components, boundaries, and internal & external interfaces;
NATO UNCLASSIFIED
1-20
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
8.2.4. (Required) Single line schematic drawings for Mechanical, Electrical, Plumbing,
Comms, etc.
10. SERVICE INTEGRATION (If applicable): This section describes the integration of
the solution into existing systems or services.
14. RISKS (RequiredIf applicable): This section should provide a thorough risk
analysis, risk register, and mitigation/management plan, with detailed elements,
NATO UNCLASSIFIED
1-21
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
interdependencies, and activities assessed and included within the project plan. This section
describes the Risk Management Plan presented by the Host Nation (ensuring that risks are
realistic and relevant) and covers risks, opportunities, and key assumptions. Changes
introduced after Decision Gate 2 approval should be highlighted and justified. Risks initially
identified at programme level and which could be managed at project level shall be
transferred to the project.
18. LIFE-CYCLE SUPPORT (Required): Provide details of plans for project Logistics
Support, Configuration Management, and in-life operations.
20. LINKAGES & DEPENDENCIES (If applicable): A description of the internal and
external linkages and dependencies with other projects, programmes, or agencies as well
as other DOTMLPFI elements. Analysis and description of interrelated works (such as
Communications for a Civil Works project), and links to other investment/initiatives (NATO,
national, multinational, etc.). For external dependencies, ensure that associated milestones
are included in the project schedule (under Section 6.4).
21. ASSUMPTIONS, LIMITATIONS, & CONSTRAINTS (If applicable): This section
shall provide the assumptions, limitations, and constraints that may impact the realization of
the project benefits.
22. VERIFICATION AND VALIDATION (Required): This section should describe how,
who, and when the testing, verification, and validation will be performed to ensure that
project deliverables meet the project acceptance criteria.
NATO UNCLASSIFIED
1-22
NATO UNCLASSIFIED
Releasable to Sweden
APPENDIX 3
ANNEX 1
AC/4-D(2022)0018-REV1 (INV)
23. POLICY COMPLIANCE (If applicable): The technical solution proposed for
implementation should meet the Minimum Military Requirement (MMR) in the most cost
effective manner and follow all applicable Technical Standards and NATO Policies. Any
known deviation from NATO policies or standards should be described and justified.