Bauxite grinding Substation building quantity

Location
Sr. no. Structure name Height/Length Nos. Excavation/Earthwork PCC Shuttering R/F Concrete Remarks
Grid Row
1 Footing F10 1 to 10 C 3.1 m 8 153.45 cum 4.95 cum 48.00 sqm 2.7 MT 29.7 included r/f of C-4 columns
2 Proposed plinth beam 1 to 10 C 43.4 m 1 41.447 cum 2.821 cum 149.73 sqm 4.6 MT 38.626
3 Balance C1 columns 6 a, b, & d 11.6 m 3 NA NA 76.56 sqm 9.744 lvl 928.10 to lvl 939.700
4 Balance C3 column 6 c 6.35 m 1 NA NA 13.97 sqm 1.778 lvl 928.10 to lvl 934.450
5 Column C1 1 to 10 a to e 9.2 m 25 NA NA 506 sqm 64.4
6 Column C2 1 to 10 a to e 11.75 12 NA NA 310.2 sqm 39.48
7 Column C3 1 to 10 a to e 3.95 9 NA NA 78.12 sqm 9.954
8 Column C3a 8&9 c 2.75 2 NA NA 12.1 sqm 1.54
9 Column C4 1 to 10 c 2.6 8 NA NA 45.76 sqm 5.824
10 Column C5 7 a 9.2 1 NA NA 20.24 sqm 2.576
11 Column C6 7 b 9.2 1 NA NA 20.24 sqm 2.576
12 Column C7 7 c 3.95 1 NA NA 8.69 sqm 1.106
13 Grade slab 207.304
14 1st floor slab
15 Terrace slab