Professional Documents
Culture Documents
1.14 MASONRY
Brick/Blockwalling, Glass Walling, Natural Stone Rubble Walling
Walls; 225mm thickness Hollow sandcrete block in
1.14.1.2.4.1 foundation jointed with mortar ratio 1:6 4065 m2 8,425.75 34,250,679.41
Offer 439,376,008.22
ADD KNOWN Cost of Finance 17,693,000.00
457,069,008.22
470,131,508.22
Contingency 5.00% 23,506,575.41
Variation Of Prices 5.00% 23,506,575.41
SUBTOTAL (EXCLUDING VAT) 517,144,659.04
VAT 7.50% 38,785,849.43
555,930,508.47
127,187,500.00
SUBCONTRACTOR ADJUDICATION
Subtotal 1
Discount Offered
Subtotal 2
VAT 7.5%
WHT 5.0%
TOTAL
Payment Term
Delivery Period
Completion Period
REF S/NO PRELIMINARY ITEM QTY RATE DUR AMOUNT FIXED TIME
A PROJECT STAFF
1 Project Manager 1 300,000 12 3,600,000
2 Quantity Surveyor 1 250,000 10 2,500,000
3 Assistant QS 1 180,000 8 1,440,000
4 Site Engineer 2 200,000 12 4,800,000
5 Accountant 1 145,000 12 1,740,000
14,080,000 14,080,000.00
B SITE ACCOMMODATION
1 Site Office (Portacabin- 80m2) 80 85,000 1 6,800,000 6,800,000.00
2 staff Accommodation (2 flats) 2 1,200,000 1 2,400,000 2,400,000.00
9,200,000
C TRANSPORTATION
1 Worker Bus (Hiace) 1 26,000,000 1 26,000,000
2 Site Project Vehicle (Hilux) 1 22,550,000 1 22,550,000
Instalmental Recovery 4 12,137,500 12,137,500.00 36,412,500.00
D SCAFFOLDING/SHUTTERING
1 Scaffolding (2000m2) 2000 250 300 150,000,000
2 Shuttering 1500 80 300 36,000,000
Instalmental Recovery 5 37,200,000 186,000,000.00
E SITE EQUIPMENT
1 CAT Bulldozer D9 1 236,000 150 35,400,000
2 Compressor 7Bar 2 41,000 100 8,200,000
3 Double Drum Roller 10Ton 1 41,000 75 3,075,000
4 Double Drum Roller 8Ton 1 42,000 75 3,150,000
5 Excavator (2 M3 ) 1 99,000 150 14,850,000
6 Motor Grader 270 HP 1 110,000 75 8,250,000
72,925,000 72,925,000.00
Use:
19,500.00
Total 35,000.00
HAULAGE COST
Shrinkage 45%
Entrained Air 2%
Water Cement Ratio 0.45
Net Volume of Wet Mix 6.86
COST OF EQUIPMENT
NO. SPREADING & COMPACTION Running Cost Total ( N /DAY )
1.00 Asphalt Paver (2.5m) 10,000.00 10,000.00
1.00 Double Drum Roller 10Ton 10,000.00 10,000.00
1.00 Sweeping Machine 10,000.00 10,000.00
1.00 Pneumatic Roller 23Ton 10,000.00 10,000.00
1.00 Compressor 7Bar 10,000.00 10,000.00
1.00 Double Drum Roller 8Ton 10,000.00 10,000.00
60,000.0
B TOTAL COST OF EQUIPMENT 15.00 Cost/M2
LABOUR COST
6.00 Operator 10,000.00 60,000.00
5.00 Skilled 5,000.00 25,000.00
10.00 Unskilled Labour 2,500.00 25,000.00
110,000.0
C TOTAL COST OF LABOUR 27.50 Cost/M2
Mortar
Mix Ratio 1.00 6.00 7.00
Cement 0.14
Add shrinkage 40% 0.06
0.20
Cement (volume/bag) 0.0350 m3/bag
5.714 Total Bags 3,785.63 21,632.14
Sand 0.86
Add shrinkage 40% 0.34
1.20
1.200 Cost per m3 of sand 3,000.00 3,600.00
Mortar 25,232.14
Waste 20% 5,046.43
30,278.57
Plaster/ m2 of wall 0.0281 m3/m2
Labour Laying
2.000 Mason 4,000.00 per day 8,000.00
1.000 Labour 2,000.00 per day 2,000.00
10,000.00
Output/ day 150.00 blocks/ ay
15.00 m2
Cost/ m2 666.67
Total
Blocks 2,970.00
Mortar 851.58
Labour 666.67
Blockwork Cost/m2 4,488.25
Mortar
Mix Ratio 1.00 6.00 7.00
Cement 0.14
Add shrinkage 40% 0.06
0.20
Volume per bag 0.0350 m3
5.714 Total Bags 3,785.63 21,632.14
Sand 0.86
Add shrinkage 40% 0.34
1.20
1.200 Cost per m3 of sand 3,000.00 3,600.00
Mortar 25,232.14
Waste 20% 5,046.43
30,278.57
Plaster/ m2 of wall 0.0206 m3/m2
Labour Laying
2.000 Mason 4,000.00 per day 8,000.00
1.000 Labour 2,000.00 per day 2,000.00
10,000.00
Output/ day 150.00 blocks/ ay
15.00 m2
Cost/ m2 666.67
Total
Blocks 2,475.00
Mortar 624.50
Labour 666.67
Blockwork Cost/m2 3,766.16
0.00
Project Information
Surface Pavement structure:
(Binder- 6cm + Wearing- 4cm) 0.10 m
COST OF MATERIAL
Supply Cost of MC-1 to Site 350,000.00 COST/TON
VAT 7.50% 26,250.00
376,250.00 COST/TON
376.25 COST/LITER
Wastage 10% 37.63 COST/LITER
413.88 COST/LITER
Application Rate 1.30 lit/m2
Cost of MC-1 Application 538.04