Professional Documents
Culture Documents
9 Part B
ENGINEERING PROCEDURES
JUNE 1988
CONTENTS
Page
FOREWORD iii
BRIEF HISTORY iv
1. SCOPE 1
2. REFERENCES 1
3. DESIGN 1
4. WORK PLANNING 3
5. SITE PREPARATION 3
5.2 Equipment 3
5.3 Excavations 4
6. INSERTION 8
6.3 Winching 9
Page
7. COMPLETION 12
7.4 Anchorage 12
TABLES
FIGURES
FOREWORD
This specification has been adopted by Transco and is an editorial revision of the former British Gas TransCo
specification BG/PS/DIS 5.9 Part B. It reflects the identity and organizational structure of Transco - a part of
BG plc.
This Transco specification has been approved for use throughout Transco.
Comments and queries regarding the technical content of this Transco specification should be directed to:
Further copies of this Transco specification can be obtained from Dataform Print Management using the print
requisition form G004 quoting the Form Number of this Transco specification (not the designation) and your
cost code.
Transco specifications are revised, when necessary, by the issue of amendments or new editions. Users should
ensure that they are in possession of the latest versions by referring to the Transco Register of Engineering
Documents available on the Transco Information Library.
Contractors and other users external to Transco should direct their requests for further copies of Transco
specifications to the department or group responsible for the initial issue of their contract documentation.
Compliance with this specification does not confer immunity from prosecution for breach of statutory or other
legal obligations.
DISCLAIMER
This specification is provided for use by Transco and such of its contractors as are obliged by the terms of
their contracts to comply with this specification. Where this specification is used by any other party it is the
responsibility of that party to ensure that the specification is correctly applied.
BRIEF HISTORY
© BG plc 1988
This Transco specification is copyright and must not be reproduced in whole or in part by any means without
the approval in writing of BG plc.
ENGINEERING PROCEDURES
SECTION 5 - PIPE SYSTEM CONSTRUCTION
MODULE 5.9 - MAINS INSERTION
PART B
1. SCOPE
This Part B of Module 5.9 of the Transco Engineering Procedures* (formerly known as the Code of Practice
for Distribution) gives guidance on the replacement of existing mains by 'dead' insertion of PE (polyethylene)
pipe, other than by moling operations.
2. REFERENCES
This Module 5.9 makes reference to the documents listed below. Unless otherwise specified the latest edition
of these documents, including all addenda and revisions, shall apply.
Transco specifications
P12 - Specification for polyethylene (PE) pipes and fittings for natural gas
and suitable manufactured gas:
Part 1 - Pipes
Engineering Procedures:
3. DESIGN
3.1 Selection of insertion pipe
3.1.1 There shall be sufficient annular clearance to avoid damage to the insertion pipe. This clearance
may have been reduced by corrosion or by fittings protruding into the main, and by other factors. The internal
condition of the main should be assessed for its suitability for insertion e.g. for debris and harmful chemicals.
3.1.2 For pipes with SDR higher than 17, e.g. thin wall pipe consideration should be given to the effects
of external hydrostatic head caused by annular flooding.
should be both recorded and marked on the highway surface. It should be noted that changes of direction in
the vertical plane are equally significant. Where there is doubt about the accuracy of significant details, trial
excavations should be made.
3.2.2 The route of the main should be assessed for traffic conditions, vehicular access points, bus stops,
pedestrian crossings and other significant features which may affect the selection of excavations for the
launch intermediate and reception of the insertion pipe. Wherever practicable, excavations made for the
removal of installed plant, bends, etc., should be used for launch, reception or intermediate excavations.
3.2.3 When the largest possible size of insertion pipe is being used, it is usually necessary to remove all
bends and installed plant before insertion takes place. Where a long length of main is to be inserted, additional
intermediate excavations may be required. However, particularly when the insertion pipe is considerably
smaller than the carrier pipe, it may be possible for some minor degree bends to be retained, provided that the
resulting radius of curvature of the insertion pipe is not less than that specified in Module 5.3.
3.2.4 The length of main which can be inserted will be affected by pipe size, gradient, changes of
direction, annular clearance, the number of services connected, etc., and it is not possible to specify maximum
lengths.
a) to provide, so far as is possible, security and protection from impact damage and vandalism;
and
b) to permit pre-assembly of lengths of pipe to form pipe strings in safety and with a minimum
obstruction to pedestrians and other road users.
3.3.2 Where radiography is employed, the working area shall be fenced off and all safety precautions
recommended by the Test Engineer shall be implemented. When making radiographs in areas normally
accessible to the public, it is necessary to notify the Health and Safety Executive.
a) a change in temperature between above and below ground ambient conditions which should
always be considered.
b) recovery from any tensile forces applied during insertion which will only apply when the main
is pulled in.
When the main is pushed in, the problems of change due to recovery of insertion loads can be ignored.
3.5.3 If for any reason the main is pulled in, time shall be allowed for the tensile stresses induced to
recover before tie-in.
3.5.4 The coefficient of expansion of PE (15. × 10 −4 / 0 C ) is about 15 times that for steel or ductile iron.
Therefore, expansion or contraction of the inserted length may occur as the temperature of the pipe reaches
equilibrium. For example, the change in length of a 100 m PE main will be 15 mm/ 0 C . Ground temperatures
at mains depth vary seasonally from about 18 0 C down to 5 0 C in mid-winter.
3.5.5 Pressurisation may commence during the relaxation period. To confirm when pressures are stable,
pressure readings should be taken at 10 min intervals. Once two readings coincide, the pressure test may
commence. No relaxation period is necessary prior to making the final connection after pressure test.
3.5.6 For long term protection of the main system from the effects of ground temperature changes on the
PE main, local anchorage of the PE main is necessary. Anchorage shall be provided:
a) at end connections to existing pipes where the connection may not be capable of sustaining an
end load;
b) where the existing main system may not sustain a tensile load; and
c) at any other non-end loaded fittings used in the inserted length.
3.5.7 Where inserted PE mains are exposed to wide seasonal extremes of atmospheric temperature, e.g. at
bridge crossings, the main shall be anchored at both ends adjacent to the crossing. Any butt joints should be
inspected in accordance with Module 5.3.
4. WORK PLANNING
4.1 Insertion of PE pipe into an existing main is straightforward, but it is necessary to plan carefully if
delays on site are to be avoided.
4.2 Attention should be given to the details of the existing main recorded on project drawings and of the
expected positions of other Utilities plant.
5. SITE PREPARATION
5.1 Site survey
Before excavation work commences, a survey of the site should be made using cable locating equipment and
the position of cables in the vicinity of proposed excavations should be marked on the surface.
5.2 Equipment
In addition to the tools and equipment regularly used for mainlaying, arrangements should be made for the
following special equipment to be available:
5.3 Excavations
5.3.1 General
Excavations should be made in accordance with Module 4.1 at each end of the existing main and at the
position of bends and siphons as indicated on the project drawing. Additional excavations (also shown on the
project drawing) may be required.
NOTE - It may not be necessary for the whole length of the excavation to be the
same width (see Figure 1).
a) Plan
b) Elevation
5.4.2 It may be necessary to place all or part of the bypass just below the surface, as determined by the
Engineer or his representative (see Module 5.7).
5.6.2 Where coiled pipe is to be used for insertion, a straight length may be fused to the leading end to
reduce the resistance during insertion. Butt jointing on coiled pipe should be avoided wherever possible, and
therefore the leading straight length should be removed before connection. Butt jointing between coils should
also be avoided.
A coil dispenser should be used whenever possible, but if one is not available, the pipe should be uncoiled
prior to insertion.
5.6.3 Butt fusion bead removal shall be done with the correct tool, without damage to the pipe. Bead
inspection shall be carried out in accordance with Module 5.3.
5.7.2 Butt jointing on coiled pipe should be avoided wherever possible, due to the difficulty of adequate
re-rounding and straightening.
5.8.2 The pipe string being tested shall be anchored temporarily because the pipe may straighten or snake
when pressurized. Warning signs advising that pressure testing is in progress shall be placed at each end of
the site.
5.8.3 An air test of not greater than 40 mbar shall be applied. All joints shall be tested immediately using
an approved leakage detection solution, which shall be washed off with clean water.
5.8.4 Following successful testing, the air pressure should be released slowly, the test ends or caps
removed and the ends temporarily sealed using expanding screwed stoppers or other suitable means. To avoid
confusion, pipe strings which have been tested may be marked.
5.8.5 Where radiographic examination is required by the Engineer or his representative, the working area
shall be fenced off and the special safety precautions recommended by the Test Engineer shall be observed.
5.10.2 An operative wearing eye protectors, and positioned at the end of the main or intermediate
excavation should:
5.10.3 After intermediate fittings have been removed, the main should be cleared of dust, scale, chemical
deposits and debris using rods, or pull-throughs, or scraper pigs pulled through by a wire cable.
5.10.4 If, in an extreme case, the Engineer or his representative decides that internal de-scaling is
necessary, special equipment shall be used and special precautions taken.
6. INSERTION
6.1 Gauging of existing main
6.1.1 To confirm that the existing main is clear of obstructions and sharp edges, a proving length of the
main to be inserted should be pulled through after the cleaning operations. For mains larger than 180 mm, and
where multiple bends are involved, this length should be not less than the minimum length stipulated in
Table 2.
6.1.2 This proving pipe should be carefully examined for signs of deep scratching or scoring.
Examination of the pipe surface at each intermediate excavation as the pipe is pulled through will help to
pinpoint unacceptable damage. The position, secure mounting and adequacy of guide rollers to assist the pipe
to negotiate any bends should be checked at this stage.
6.1.3 Surface scratching is inevitable, but where deep scratching or scoring of the pipe occur the Engineer
or his representative shall be notified. Further investigation of the existing main will then be necessary before
proceeding with the insertion operation.
6.2.2 The inserted pipe should be protected from the sharp edge of the existing main in the launch and
intermediate excavations e.g. as shown in Figure 2.
6.2.3 Rollers or other suitable packing should be set up both at road level and in the launch excavation to
guide the inserted main into the existing main as shown in Figure 1.
6.3 Winching
6.3.1 The preferred method is for the pipe to be inserted under controlled conditions by 'pushing' from the
launch end. Alternatively, the pipe may be inserted by pulling from the receive end.
6.3.2 Wherever possible, hand winching should be chosen in preference to powered winching and a steel
wire cable should be used in preference to natural fibre ropes. Ropes made from man-made fibres shall not be
used. A current test certificate shall be available for the steel wire cable.
6.3.3 All cables to be used during the insertion process shall be approved by the Engineer or his
representative and examined before and during use for signs of damage. Any damage shall be reported before
the work proceeds. Damaged cables shall not be used.
6.3.4 The safe working load (SWL) of the rope or cable shall be equal to, or greater than the load
capacity of the winch.
6.3.5 The winch should be fitted with a suitable means of control to limit the maximum allowable 'pull-in'
force on the PE pipe, to that shown in Table 3.
NOTE - This table is based on 1/2 the minimum yield stress for medium density
PE in PL2: Part 1.
6.3.6 All winches shall be securely anchored. During winching operations no one should stand in the
direct failure path of the cable. To minimize the possibility of accidents arising from a failure of the cables,
timber shoring may be securely fitted across the trench width, above and below the line of the cable.
Protective gloves shall be worn at all times when handling cables.
6.4.2 When each new pipe string is added, the new joint shall be allowed to cool before the PE main is
handled or subjected to a pressure test in accordance with 5.8.
6.4.3 During the insertion process, the passage of the pipe should be checked at the intermediate
excavations. The pipe surface should be examined for signs of deep scratching or scoring as detailed in 6.1.
6.4.4 Where the inserted pipe is required to change direction, e.g. where a bend has been removed, the
leading end should be slowly and carefully guided into the main opening, rollers or sand bags having been
positioned to assist the pipe to negotiate the bend.
6.4.5 On completion of the insertion process, the surface of the leading pipe should once again be
examined and the Engineer or his representative notified of any deep scoring or scratching.
a) by hand;
b) pusher machine;
c) the use of a winch.
6.5.2 Care shall be exercised when the free end of the inserted pipe is close to the launch trench, the pipe
may whip or bow.
6.6.2 A winch and pulley assembly should be assembled at the receive end of the existing main. The
cable should be passed from the winch, through the existing main and secured to the pipe to be inserted.
6.6.3 The winch operator at the receive end shall maintain contact with personnel at the launch trench, by
radio contact if necessary. The inserted pipe should not be allowed to drag over rough surfaces or sharp edges.
Rollers or a coil dispenser should be used to enable the pipe to enter the existing main at a slow walking pace.
6.6.4 When using a power operated winch, the operator shall not exceed the pull-in force which will be
stated by the Engineer or his representative. If the tension in the cable rises suddenly, the winch shall be
stopped immediately and the tension shall be released before any attempt is made to investigate the
obstruction.
7. COMPLETION
7.1 Relaxation period
When a main is pulled in, a relaxation time shall be allowed.
Pressure testing may be carried out during this period provided a stable pressure condition is achieved.
Annular spaces between the inserted main and the existing main should be sealed as determined by the
Engineer. Pipework shall be adequately supported.
7.4 Anchorage
7.4.1 Where the inserted main connects to the existing metallic system, provision shall be made to protect
the existing mains from end loads imposed by the inserted PE main.
7.4.2 In the case of welded steel mains, an end loading transition fitting will suffice.
7.4.3 The casing pipe (i.e. the old main) should preferably be used for anchorage. Where the PE main
size is such that an electrofusion coupler exists, this can be fused over a scraped area of pipe adjacent to the
exit of the PE main from the carrier pipe, sandwiching a flange between the coupler and the end of the casing
pipe. A 3m length of undisturbed main should be left at the dead pipe end. Figure 3 shows a typical
arrangement.
7.4.4 For larger sizes, it will be necessary to provide anchorage by other methods: a flanged fitting is
suitable. This arrangement shall transmit the load to the end of the carrier pipe (see Figure 4). If the end of the
carrier pipe cannot be used to react the end load, a ground anchor can be used, giving due consideration to the
ground conditions prevailing on site.