You are on page 1of 1

No Uraian Jmlh Satuan Harga Satuan Total Harga

1 Tenaga Enginer Onsite 1 orang 26,000,000 312,000,000


2 Administrasi 2 orang 9,500,000 228,000,000
3 Switch Layer 3 Unifi 2 Unit 2,000,000 48,000,000
4 Server 1 unit 6,000,000 66,000,000
5 Controler Ruckus 1 unit 1,500,000 16,500,000
6 Display Lcd monitoring 4 unit 1,000,000 44,000,000
7 PC i9 2 Unit 2,500,000 55,000,000
8 laptop i9 7 Unit 4,200,000 323,400,000
9 Router mikrotik ccr 5 Unit 2,500,000 137,500,000
10 Terminasi Layanan 1 lot 5,000,000 5,000,000
11 Instalasi 1 lot 16,000,000 16,000,000

Jumlah 1,251,400,000
PPN 11% 137,654,000
TOTAL 1,389,054,000