Qatar Foundation Education City: Research & Development

Complex
– Risk Assessment for Steel Structure Erection On Project Site
18-06-2013

Risk Assessment RA-02 Container Offloading


Download HSE Docs hseprof.com

Contract No. and Project No.: RA Number: Element of Work: Risk Assessment Author: Date:
QF/PD/13/M-009-MOF, QFE009 QFE009-EVS-PL-ST- Container Offloading J.James Victor 18 June 2013
0002

Severity Likelihood Evaluation of Risk


NO INJURY 1 RARE 1 12 - 25 High Action required urgently to control the risk, further resources may be required, work must stop immediately
MINOR 2 UNLIKELY 2
MODERATE 3 OFTEN 3 Action required to control the risk, interim measures may be necessary in the short term, able to proceed with work under
5 – 10 Medium
MAJOR 4 LIKELY 4 supervision
FATALITY 5 EXPECTED 5 1–4 Low This represents a low risk, although control measures must be maintained

Who might be Residual


Initial risk?
harmed? Risk?
Employees
Action

Risk Rating

Risk Rating
Contractors
Likelihood

Likelihood
Job / What are the What controls are required?
Severity

Severity
Public How? by
hazards? Others
Environment

Unloading of the Employees, Falling object / 5 5 25  Ensure all attended the job specific training 1 2 2 SE / SO
Container Contractors, crane or lifting gear  Ensure the crane is having valid certificate issued by third party
Others failure  Ensure the crane operator is having valid certificate issued by third party
 Follow work method statement.
 Ensure the lifting plan is followed properly.
 Ensure the lifting load is not exceeds the cranes lifting chart.
 Ensure all operatives are trained and competent.
 Ensure lifting permits is in place.
 Explain the potential hazards to the work force prior to start the work.
 Crane operator and riggers should be certified by third party.
 Daily crane inspection to be done prior to start the work.
 Minimize manual handling.
 Lift the materials as lowest as possible.
 Ensure workers not present under suspended load.

Date of current issue: 08.05.2013 Page 1 of 3 Form# 18018 Rev 0, Aug 2010

Download HSE Docs hseprof.com


Qatar Foundation Education City: Research & Development
Complex
– Risk Assessment for Steel Structure Erection On Project Site
18-06-2013
Who might be Residual
Initial risk?
harmed? Risk?
Download HSE Docs hseprof.com

Employees
Action

Risk Rating

Risk Rating
Contractors

Likelihood

Likelihood
Job / What are the What controls are required?

Severity

Severity
Public How? by
hazards? Others
Environment

 Use double fold the lifting chain / sling while free movement.
 Workers to be cleared from the area when moving the beam.
 Tagline to be provided both end of the load.
 Rigger must keep the whistle to alert the other workers.
 Lifting not to be carried out, if wind speed exeeds the project HSE rule.
 Do not carry out any lifting operation in adverse weather condition (Heavy wind,
poor visibility etc).
 Close supervision.

Moving equipments Employees, Traffic accident / 3 4 12  Equipments must have the reverse alarm and warning lights. 2 2 4 SE / SO
fork lift / trailer / Environment, reversing /  Make separate walk way for pedestrians.
mobile crane / major Others over turn  Put barricade and sign board aound the rotating equipment.
injury  Place and follow traffic sign board and speed limit.
 Mark and put the barricading sign boards on road crossings.
 No over loading on the equipments and no over speed.
 Ensure certified operator operates the equipment.
 Certified and trained banks man to guide the equipment.
 Maintain daily maintanance check list.
 Banks man shall wear visible jacket (Red) and keep whistle for signaling.
(coverall, helmet, safety shoe, googles and glouves)

Working under hot Employees Poor ventilation, 4 4 16  Openyard work to be stopped during midday break. (Summer) 2 2 4 SE / SO
climate / Heat Inadequate  Heat index to be followed.
stress, major injury / arrangements  Drink water frequently
illness  No direct expose to the sunlight during mid summer.
 Provide shelter close to the work area.
 Keep the work area free air flow.
 Temperature to be monitored every 1 hr and take precation as per heat index.
 Close supervision.

Date of current issue: 08.05.2013 Page 2 of 3 Form# 18018 Rev 0, Aug 2010

Download HSE Docs hseprof.com


Qatar Foundation Education City: Research & Development
Complex
– Risk Assessment for Steel Structure Erection On Project Site
18-06-2013
Who might be Residual
Initial risk?
harmed? Risk?
Download HSE Docs hseprof.com

Employees
Action

Risk Rating

Risk Rating
Contractors

Likelihood

Likelihood
Job / What are the What controls are required?

Severity

Severity
Public How? by
hazards? Others
Environment

 Appropriate PPE must be worn. (coverall, helmet, safety shoe, nose mask,
googles and glouves)

Working on open Employees Heavy wind / fall 3 3 9  Stop the crane activity if the wind speed exeeds 40 km /hr. 1 1 1 SE / SO
space / Serious from height, Flying  Openyard work to be stopped during sand strom and heavy wind.
injury Material  Mobile crane shall have wind speed meter.
 Manufacturer instruction to be followed when using mobile equipments.
 Tie all light weight materials and provide close support to the structures.
 Close supervision.
 Appropriate PPE must be worn. (coverall, helmet, safety shoe, nose mask,
googles and glouves)

Date of current issue: 08.05.2013 Page 3 of 3 Form# 18018 Rev 0, Aug 2010