Document Reference

AMS_10006_LFP_001
Al Buraimi Rev. No. Rev. Date
00
Page
CRANE LIFTING STUDY / LIFT PLAN 1 of 7

Lift Plan – General Details:


Project: AMS Evergreen Shipping Date: 10/06/2020
L/Plan Revision
Site / Location: Sharjah 0
No:
AMS Evergreen
Appointed Person (AP) Client:
Don Billote Shipping
(Carrying out the Lifting Study)
AP Contact No.: 0501116813
Site Contact Person: Ahmed Contact No.: 0508965665

Lift Plan REF: AMS_10006_LFP_001

Description & Sequence


Lifting of Weight Block
of lift’s:
1. Supervisor to conduct TBT with the operatives and discuss the procedure stated on this lift plan.
Supervisor to check all necessary legal documents to be present and available.
2. Once the area of operation is clear, the supervisor will advise the mobile crane operator to mobilize
his crane onto the crane rigging area and rig the mobile crane as per crane manufacturer’s
instruction and LOLER 1998 regulation.
Safety Check
a. Supervisor and operator to check and ensure that access and egress are clear, ground condition
are level and compacted enough to support the load impose by the mobile crane and outrigger
b. Supervisor to ensure presence of flagman during the mobilisation of the mobile crane to the
rigging area.
c. Supervisor to check and ensure exclusion zones and watchmen are in position before rigging the
mobile crane.
d. Supervisor to ensure that no non operative personnel are inside the exclusion zone.
3. Once the mobile crane has been rigged, the lifting crew will attach the mobile crane slings to the
weight block.
4. Connect the mobile crane slings to the weight block lifting points and lift off the ground to check
integrity if the load is balanced and secured then continue weight block to the trailer.
5. Remove the mobile crane slings from the weight block once the weight block is loaded to the trailer.
6. The Crane supervisor will then instruct the mobile crane operator to de rig the mobile crane as per
crane manufacturer instruction.
Document Reference
AMS_10006_LFP_001
Al Buraimi Rev. No. Rev. Date
00
Page
CRANE LIFTING STUDY / LIFT PLAN 3 of 7

Details of Loads: Units Weight Block


Net: T 72
Weight Gross with 72.5
T
Lifting tackle:
11 x 4 x 5.4
Load Dimensions: m

Position of C of G 5.5 x 2 x 2.7


m
(Centre of Gravity) :

Height of Lift: m 3
12
Max. Radius: m

9
Min. Radius: m
Document Reference
AMS_10006_LFP_001
Al Buraimi Rev. No. Rev. Date
00
Page
CRANE LIFTING STUDY / LIFT PLAN 3 of 7

Crane 2 Crane 3
Details of Crane: Units Mobile Crane
(Alternative) (Alternative)

TEREX DEMAG Click here to enter Click here to enter


Crane Make & Model:
AC250-1 text. text.
Click here to enter Click here to enter
Crane Capacity (WLL): T 250
text. text.
Click here to enter Click here to enter
Hook Block Capacity (WLL): T 125
text. text.
Box-shaped, 6-
section
hydraulically
Click here to enter Click here to enter
Boom Type: telescopic type
text. text.
(Boom sections 6 /
5 simultaneously
operated)
Click here to enter Click here to enter
Boom Length Required: m 60
text. text.
Click here to enter Click here to enter
Length: m N/A
Fly / Luffing jib text. text.
(if required or N/A) Click here to enter Click here to enter
Angle: Deg. N/A
text. text.
Outrigger Spread Click here to enter Click here to enter
m 8.69 x 8.5
(Show dimensions on drawing): text. text.
Crawler Crane Track Load: Click here to enter Click here to enter
T/m2 N/A
(As per manufacturer spec.): text. text.
Max. Ground / Soil Bearing Click here to enter Click here to enter
T/m2 25
Capacity: text. text.
Mat / Pad Size Required Click here to enter Click here to enter
m2 3m x 3m
(Mobile Cranes): text. text.
Click here to enter Click here to enter
Weight of Hook Block: T 1.2
text. text.
Click here to enter Click here to enter
Counterweight: T 96
text. text.
Rigged Weight of Crane Click here to enter Click here to enter
T 241.8
(All Up Weight): text. text.
Document Reference
AMS_10006_LFP_001
Al Buraimi Rev. No. Rev. Date
00
Page
CRANE LIFTING STUDY / LIFT PLAN 4 of 7

Lifting Accessories:
Lifting Accessory Calculations (Minimum Requirement)
Slings – Chain Slings – Slings –
Calculations Shackles
Wire Rope Block web Chain
Number of Legs / N/A 4 N/A N/A N/A
Accessories: N/A N/A

Total Lift Load: N/A N/A 20 N/A 72 N/A N/A

Mode Factor: N/A N/A 2.1 N/A 2.1 N/A N/A


Actual Load/leg N/A N/A 2.8 N/A N/A
OR N/A N/A
Total Load:

WLL of Sling / N/A 36T 35 N/A N/A


Accessory Selected: N/A N/A

Diameter / Size of N/A N/A N/A 57mm pin N/A N/A


Accessory: N/A dia
Minimum Length of N/A N/A 8 N/A N/A N/A
leg: N/A

N/A Web Round N/A N/A N/A


Description of Sling
Accessory Selected: N/A

N/A N/A N/A N/A N/A N/A


Comments: N/A

NB: 50% reduction in load capability if Man Riding Basket is used.


Document Reference
AMS_10006_LFP_001
Al Buraimi Rev. No. Rev. Date
00
Page
CRANE LIFTING STUDY / LIFT PLAN 5 of 7

Load Angle Factor


Sling Angle (A) Load Angle Factor Load Calculation Per Sling Leg
90º 1.000 1. Take the total weight of the load and divide this by
the number of legs supporting the load. (Example –
85º 1.004
a 2.00T load is to be supported by 2 legs of a sling.
80º 1.015 The above will give a minimum weight for each leg
of the sling, 2.00T divided by 2 (number of legs on
75º 1.035
sling) = 1.00T minimum per leg.
70º 1.064 2. Determine the load factor by observing the Load
65º 1.104 Angle Factor chart. (Example – leg angle = 60º, the
load factor for 60º from the chart is 1.155.
60º 1.155 3. Multiply the load factor with the minimum load per
55º 1.221 leg (1.155 x 1.00T = 1.155T Actual load per sling
leg).
50º 1.305
4. The rated sling capacity needed is 1.155T x 2 =
45º 1.414 2.31T WLL.
40º 1.555
Note: other methods of calculation may be used,
35º 1.742
depending on the load to be lifted. Mark if
30º 2.000 applicable.

Identification of Hazards:
Proximity Hazards:
Hazard Present Hazard Present

Overhead Power Lines YES NO Restricted Access - Width YES NO

Other Overhead Obstacles YES NO Restricted Access - Height YES NO

Underground Services YES NO Other Vehicles / Plant YES NO

Excavations YES NO Other Hazards Identified (Specify) YES NO

Unstable/ Soft Ground YES NO The affected area must be barricaded throughout
the operational period.
Hazardous chemicals / Materials YES NO

Restricted Working Area YES NO


Document Reference
AMS_10006_LFP_001
Al Buraimi Rev. No. Rev. Date
00
Page
CRANE LIFTING STUDY / LIFT PLAN 6 of 7

Load Hazards:
Hazard Present Hazard Present

Slinging Difficulties YES NO Other Hazards Identified (Specify) YES NO

Top Heavy YES NO Click here to enter text.

Sharp Edges YES NO

Assessment of Hazard:
Hazard Present Harm Action to Avoid or Reduce Risk
 Check the weather forecast before starting the job.
Material damage,  Do not carry-out any outdoor activity in adverse weather
Adverse weather Serious injury, condition.
Fatality  Supervisor to check wind speed by use of Mobile Crane
anemometer.
 All operatives must use full body safety harness with double
lanyard and energy absorbers.
Serious injury,  Site to arrange suitable anchoring point from the trailer bed to
Fall of person.
Fatality reduce free fall distance maximum 1.5 meters.
 Personnel at all times to proceed slowly and with caution.
 All personnel working at heights must be trained for the same
 Access should be clearly demarcated and free of obstructions.
 Access and Egress through recognized routes only (i.e. trailer
Insufficient or Improper Access Slipping / Tripping & Falling,
ladders). Ensure ladders are fitted properly.
Egress to the Crane Serious Injury, Fatality
 Prior to climbing up or down the trailer, clean off soles of boots
of mud and possibly oil or grease.
 Pre-start checks to include agreement between operative for
Material & Property Damage, proper communication between banksman/riggers with the
Poor Communication
Serious injury, crane operators by means of radios or hand-signals.
 Check & confirm radio frequency before using.

Other personnel entering into  Site to provide exclusion zone barricaded off to Non-operational
Injury to Personnel personnel.
the working area accidentally  Provide caution signs, watchers & barricade the working areas.

Personal Involved In the Lifting Activity:


Position
Name of Person Required PPE
(Attach certificates / appointments)

Hard hat, steel toe cap safety shoes,


Don Billote Appointed Person
reflective jacket, eye protection & gloves.
Hard hat, steel toe cap safety shoes,
TBC Crane Supervisor
reflective jacket, eye protection & gloves.
Hard hat, steel toe cap safety shoes,
TBC Crane Operator
reflective jacket, eye protection & gloves.
Hard hat, steel toe cap safety shoes,
TBC Banksman / Rigger
reflective jacket, eye protection & gloves.

Document Reference
AMS_10006_LFP_001

Ali Buraimi Rev. No. Rev. Date


00
Page

CRANE LIFTING STUDY / LIFT PLAN 7 of 7

The Appointed Person may decide that one person can carry out more than one duty. This does not
however, include the crane driver who must concentrate on operating the crane.

Banksman / Flagman – The Banksman / Flagman are only to control Mobile Plant and Equipment or
assist with the movement of Cranes from one point to another, when the crane isn’t in use.

Weather Conditions
The Appointed Person or, in his absence, the Crane Supervisor, will ensure that the lifting operation
only takes place if the weather conditions are within the limits recommended by the crane manufacturer
and local regulation.

Contingency Statement:
The lift plan and method statement may only be amended by the Appointed Person who has
compiled this lift plan and method statement for the particular lift. Should there be a change in
the procedure or environment, the lifting task is then to be stopped and the Appointed Person
informed accordingly of the change.

Acceptance of Responsibility:
Appointed Person’s Acceptance of Responsibilities:
I confirm that the lifts have been planned and will be carried out in accordance with current legislation and British Standard 7121 and
that I accept responsibility for the preparation of this Risk Assessment and Method Statement.

Name: Don Billote Signature: Date:

Crane Supervisor Acceptance of Responsibilities:


I confirm that I have been fully briefed on the contents of this Risk Assessment and Method Statement and that I accept the duty of
ensuring that the lift(s) will be carried out in accordance with the method and procedures set out in this document.

Name: Click here to enter text. Signature: Date: