NON-ROUTINE COMPLEX LIFTING PLAN

General Information
NRLP – C – 117 – Seat Back Aera Rig Floor 20 T
Lifting Plan No.: Date: 25– 05 – 2023
ZB556
Location: ZB-556 Contractor/Sub-Contractor SLB / IDC – 37
Permit-To-Work No: Risk Assessment No:
Description of lifting operation:
Lloading / Positioning Seat Back Area Rig Floor Truck to Ground – Crane by Tandem Lift
550 t HOOK BLOOKS ON 7 PARTS OF LINE MUST BE INSTALLED ON BOTH (TADANO GT-550 E )(NK500E-III) AS AGREED WITH ENI LTA
Method Statement:
To perform loading / Positioning Seat Back Area Rig Floor – Crane by Tandem Lift
By: 2 X Mobile Cranes, Lifting Supervisor, 2X Singers, 1X Banks man, and Flagmen as required
 All required documents shall be in place and shall be confirmed before starting the job (JSA, PTW, LP, TBT, etc.)
 using two of 3rd party mobile cranes For Lifting Operation.
 Pre-work check of site, load, and lifting equipment (lifting appliances and lifting accessories)
 All lifting equipment shall have clear and legible SWL, all lifting accessories shall be correctly colour coded
 Size, weight, shape, CoG of load shall be confirmed
 Load shall be checked for any loose / potential dropped objects
 Check proximity hazards, obstructions, load path and lay down area load bearing capacity.
 Pre-work check of environmental conditions (wind speed shall not exceed 10 m/s, rainfall, foggy weather, etc.)
 Confirm competency requirements match lift team personnel
 Confirm and agree methods of communication: standard hand signals & radio.
 Responsibilities to be clearly defined for all personnel
 Lifts to be controlled by banks man who is clearly identifiable by wearing high visibility waistcoat
 Establish barrier surrounding lifting operation area, non-essential personnel to be excluded at all times
 Safe access, egress and escape routes (scaffolding, platforms etc.)
 Tagline requirement: Tag lines are not required for tandem lift
 No hand contact with loads until below waist height, no hands and fingers near pinch points.
 Cable trays, beams, and any other obstructions shall be removed to allow the proper set-up of the crane prior to lift.
 Any obstacle that might become in contact with the sling shall be removed.
Part of lines: Crane #1 #2: : 7 Crane 7
Details of the Load
Description of load/s: Saet Back Aera Rig Floor 20t
Overall dimensions [m]: 8 M X 5 X 2.9
Weight of load [t]: [A] 20 T √ Known weight □ Estimated weight
Centre of Gravity: OFFSET □ Known (by drawing) √ Estimated position
Details of the Lifting Appliance # 1
Type of Lift. Appliance: Mobile Crane Model: NK-500B-V

Maximum Capacity: 50 t Date of last Certification: 6-10-2022

Appliance Certificate: St-3620-02 Appliance Serial #: 2010120.


Boom length [m]: 18.55 Radius [m]: 7.5 (Minimum Applicable , Radius)

Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved
18.6 Load share on crane #1 [Total Weight (10) × 1.25] =12.5 t for each crane
radius [t]: [B]
Details of the Lifting Appliance # 2
Type of Lift. Appliance: Mobile Crane Model: NK – 500 E -III

Maximum Capacity: 50 t Date of last Certification: 6-12-2022

Appliance Certificate: ST-4037 Appliance Serial #: 436904

Boom length [m]: 18.1 m Radius [m]: 7.5 Minimum Applicable , Radius)

Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved
18.5 t Load share on crane #1 [Total Weight (10) × 1.25] =12.5 t for each crane
radius [t]: [B]
Details of the Lifting Accessories
Types of Lifting accessory: Slings / webbing / chains / shackles / spreader beam
Weight SWL
Type Quantity Identification Number Certificate # Expiry Date
[Kg] [t]
50
Crane(1) HOOK BLOCK - (NK-500B-V) 1 570 2010120 St-3620-02 6-10-2022
Ton

LTG – IQ 18.3
2 Legs wire rope sling 1 100 B3757 15 – 09 – 2023
/A260133 TON
9.5
2 Bow Shackles 2 15 S45 / S46 / ST-4391-21 19 – 08 - 2023
TON
Ras-t- 50
Crane(2) HOOK BLOCK - (tg-500E-III ) 1 570 436762 6-12-2022
221230400 TON
LTG – IQ 18.3
2 Legs wire rope sling 1 100 B3758 15 – 09 – 2023
/A260133 TON
9.5
2 Bow Shackles 2 15 D12 /D 15 ST-4391-21 19 – 08 - 2023
TON
Total weight of Lifting accessories [t] : [C]=(D/1000) Crane #1 = 0.685 KG Crane #2 = 0 .685KG
Colour code: Blue Certification of Lifting accessories: □ YES □ NO
Unity Check of # 1 [%]: 70.88% Unity Check of # 2 [%]: 71.27 %
ENSURE THAT ALL LIFTING EQUIPMENT HAVE BEEN CHECKED AND DEEMED SUITABLE AND SAFE
Lifting Sketch – As required
Radius : TG500E
5m Sketch of the General Arrangement / Rigging:
[crane position / lifted item / obstacles and any additional details, as required]

50T CRANE kato (nk-500e)


CABACITY
@ CONFIGRATION :- 20.7 T
LOAD SHARE :- 12.5 t

FOR EACH CRANE


2 Leg Wire Rope Slings
SWL :- 18,3 t TON L = 6 M
Boom 18.1 m Boom : 18.55 m
2 Bow Shackles =
SWL – 9.5 TON

Nk-500e-iii

Nk-500b-v
Seat Back Area Rig Floor

7,5 m
7.5 m
Load chart to be used
Crane :- kato (nk500b-v)
550 HOOK BLOOKS ON 7 PARTS OF LINE MUST BE INSTALLED ON kato (nk500b-v)) AS AGREED WITH ENI LTA
Personnel involved in lifting operation
Position Name Certificate / Qualification Expiry Date
Lift. Appliance Operator #1 Abdulla khashan (NK500B-V) St-3236-03 8-7-2023
Lift. Appliance Operator #2 Alla jamil ( gt-500E-III) AEC-220710371 9-7-2023
Lifting Supervisor Tho alfuqar habeeb mardan Aec-223332969 14-10-2023
Banksman Alla Faris 19785-115-2 24 – 12 – 2024
Rigger Abdullah Muttir 19785-115-5 24 – 12 – 2024
Rigger Haider Helamy 19785-115-6 24 – 12 – 2024
Person in charge Tho alfuqar habeeb mardan Aec-223332969 14-10-2023
Any person involved with the job can call ”ALL STOP!” at any time if something wrong is observed
Physical and environmental consideration
Condition Verification Check
Is the ground made safe (e.g. Placing steel plate or wooden matts) Yes

Ground Conditions Are the outriggers evenly /adequately extended? Yes

Is lay down / landing area(s) adequate in both size and load bearing capacity? Yes

Obstacles Has route to be travelled been selected and cleared of obstructions? Yes

Lighting Is the lighting condition adequate to perform the operations safely? Yes

Demarcation Have barriers been positioned to prevent access to unauthorised personnel? Yes

Environment Are the weather conditions within limits to avoid their effects on the safety of the lifting operation? Yes

IF ANY OF THE CONTROLS IS NOT IN PLACE, THE OPERATION SHALL NOT START!
Communication What are the means of communication between the lifting team?

√ Verbal □ Radio √ Standard hand signals □ Others: ..............................


Operational Criticalities identification and Special Precautions
Tick the points relevant to the criticalities identified and provide adequate control measures/actions to address them
Yes Is the Weight of the load known No Lifting operation performed at night/low visibility
Yes CoG position is it unclear No Limited clearance / restricted height or areas
Yes Unstable load (High CoG or above lifting points) No Lifting operation performend in SIMOPS condition
Yes Large exposed wind surface No Blind or partially blind lifts
Yes Is there dedicated lifting points No Fragile load
No Is there dedicated rigging (lifting bridle) No Has the Load any sharp edges
Report any additional information and proposed control measures for the above listed identified criticalities: Tandem Lift
SIMOPS

The Non-Routine Simple lifting plan shall be submitted to LTA for review and approval. LTA shall evaluate, in collaboration with
other members of the team, all possible corrective actions and advice to:
STOP! Further engineering inputs and risk assessment are required.

PROCEED WITH CAUTION! Operation may be performed providing that all necessary actions
have been taken and JSA updated accordingly.

GO! Proceed with lifting operation following the instruction given by the PIC.
Reference documents
Reference Documents / Evidences / Attachments:
NOTE - HSE documentation (JSA/RA) shall be updated accordingly, in collaboration with HSE involved personnel, to reflect the proposed actions.
Preparation and Review
Prepared by: Signature: Date: 25– 05 – 2023
Reviewed by: Signature: Date:
LTA comments and review
Reviewed and Acknowledged by LTA and PIC
LTA: Signature: Date:
PIC: Signature: Date: