General Information
Lifting Plan No.: 04 Date: From 25-06-2022 to 01-07-2022
Location: ZMDEI Contractor/Sub-Contractor Al-Bilal Company
Permit-To-Work No: Risk Assessment No:
Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
Use Protection
30 M
Lifting of Beam
Use Protection
6.0 M
Lifting of Column
1 Webbing Sling in chocker hitch
4T–3M
Use Protection
3.0 M
Lifting of Main Beam
Use Protection
15.0 M
Installation Area Steel Structure Postion
ZMDEI
SIMOPS
The Non-Routine Simple/Complex lifting plan shall be submitted to LTA for review and approval. LTA shall evaluate, in
collaboration with other members of the team, all possible corrective actions and advice to:
STOP! Further engineering inputs and risk assessment are required.
PROCEED WITH CAUTION! Operation may be performed providing that all necessary actions
have been taken and JSA updated accordingly.
GO! Proceed with lifting operation following the instruction given by the PIC.
Reference documents
Reference Documents / Evidences / Attachments:
NOTE - HSE documentation (JSA/RA) shall be updated accordingly, in collaboration with HSE involved personnel, to reflect the proposed
actions.