General Information
NRLP – C – 132 Pipe Basket Tool box ( Drill Pipe &
Lifting Plan No.: Date: 25 – 05 – 2023
Drill Cellar ) Max Load 45 ton
Location: ZB-556 Contractor/Sub-Contractor SLB / IDC – 37
Permit-To-Work No: Risk Assessment No:
Description of lifting operation:
Loading / Positioning Pipe Basket Tool box ( Drill Pipe & Drill Cellar ) Max Load 45 ton On Ground to Truck – Crane by Tandem Lift
130 t HOOK BLOOKS ON ( 7 )PARTS OF LINE MUST BE INSTALLED ON BOTH (KATO KA – 1300 SL )(NK-1000) AS AGREED WITH ENI LTA
Method Statement:
To perform Loading / Positioning on Shaker Tank + MAD TANK
By: 2 X Mobile Cranes, Lifting Supervisor, 2X Singers, 1X Banks man, and Flagmen as required
All required documents shall be in place and shall be confirmed before starting the job (JSA, PTW, LP, TBT, etc.)
using two of 3rd party mobile cranes For Lifting Operation.
Pre-work check of site, load, and lifting equipment (lifting appliances and lifting accessories)
All lifting equipment shall have clear and legible SWL, all lifting accessories shall be correctly colour coded
Size, weight, shape, CoG of load shall be confirmed
Load shall be checked for any loose / potential dropped objects
Check proximity hazards, obstructions, load path and lay down area load bearing capacity.
Pre-work check of environmental conditions (wind speed shall not exceed 10 m/s, rainfall, foggy weather, etc.)
Confirm competency requirements match lift team personnel
Confirm and agree methods of communication: standard hand signals & radio.
Responsibilities to be clearly defined for all personnel
Lifts to be controlled by banks man who is clearly identifiable by wearing high visibility waistcoat
Establish barrier surrounding lifting operation area, non-essential personnel to be excluded at all times
Safe access, egress and escape routes (scaffolding, platforms etc.)
Tagline requirement: Tag lines are not required for tandem lift
No hand contact with loads until below waist height, no hands and fingers near pinch points.
Cable trays, beams, and any other obstructions shall be removed to allow the proper set-up of the crane prior to lift.
Any obstacle that might become in contact with the sling shall be
removed. Part of lines: Crane #1: 7 - Crane #2: 7
Details of the Load
Description of load/s: Positioning Pipe Basket Tool box ( Drill Pipe & Drill Cellar ) Max Load 45 ton
Overall dimensions [m]: 12 M X 3.2X 1.5
Weight of load [t]: [A] 45 T √ Known weight □ Estimated weight
Centre of Gravity: OFFSET □ Known (by drawing) √ Estimated position
Details of the Lifting Appliance # 1
Type of Lift. Appliance: Mobile Crane Model: Ka-1300sl
Maximum Capacity: 130 T Date of last Certification: 18 – 10 – 2023
Appliance Certificate: LTG-IQ/A241912 Appliance Serial #: 8210072
Boom length [m]: 19.8 Radius [m]: 9(Minimum Applicable , Radius)
Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved [Total Weight (22.5) × 1.25] × =28.125 t For Each
40 t Load share on crane #1
radius [t]: [B] Crane
Details of the Lifting Appliance # 2
Type of Lift. Appliance: Mobile Crane Model: KA – 1300SL
Maximum Capacity: 130 T Date of last Certification: 12 – 02 – 2024
EACH CRANE
2 X Single Wire Rope Slings
SWL = 16.6 ton L=6M
Boom 16.4 M
KA1300SL
Ka-1300sl
Radius 9 m
Radius 9 m
Slings Calcualtions
Critical Assumption of the loads share side = ( Load Waight / 2 ) x 1.25 = ( 45/2)x1.25 =28.125 t
Tension on each crane slings = ( Load Share / Namber Of Slings ) x Mode Factor =(28.125 / 2 ) x 1.0377= 15.92 t
1.5 M
3.2 M
Load chart to be used
Crane :- KATO (KA – 1300 SL )
130 HOOK BLOOKS ON 7 PARTS OF LINE MUST BE INSTALLED ON KATO (KA – 1300 SL ) AS AGREED WITH ENI LTA
Personnel involved in lifting operation
Position Name Certificate / Qualification Expiry Date
Lift. Appliance Operator #1 Ayad katia St-3471-02 28-8-2023
Lift. Appliance Operator #2 Hussain Nama Aifan [KA – 1300 SL ] AEC – 223332706 01 – 10 – 2023
Lifting Supervisor Tho alfuqar habeeb mardan Aec-223332969 14-10-2023
Banksman Ahmed Mohaned 19785-115-2 24 – 12 – 2024
Rigger Raed Abdul Rsool 19785-4 22 - 07 – 2023
Rigger Salam Hameed 19785-59-8 24 – 12 – 2024
Person in charge Tho Alfuqar Habib Mardan AEC – 223333376 29 – 10 – 2023
Any person involved with the job can call ”ALL STOP!” at any time if something wrong is observed
Physical and environmental consideration
Condition Verification Check
Is the ground made safe (e.g. Placing steel plate or wooden matts) Yes
Obstacles Has route to be travelled been selected and cleared of obstructions? Yes
Lighting Is the lighting condition adequate to perform the operations safely? Yes
Demarcation Have barriers been positioned to prevent access to unauthorised personnel? Yes
Environment Are the weather conditions within limits to avoid their effects on the safety of the lifting operation? Yes
IF ANY OF THE CONTROLS IS NOT IN PLACE, THE OPERATION SHALL NOT START!
Communication What are the means of communication between the lifting team?
The Non-Routine Simple lifting plan shall be submitted to LTA for review and approval. LTA shall evaluate, in collaboration with
other members of the team, all possible corrective actions and advice to:
STOP! Further engineering inputs and risk assessment are required.
PROCEED WITH CAUTION! Operation may be performed providing that all necessary actions
have been taken and JSA updated accordingly.
GO! Proceed with lifting operation following the instruction given by the PIC.
Reference documents
Reference Documents / Evidences / Attachments:
NOTE - HSE documentation (JSA/RA) shall be updated accordingly, in collaboration with HSE involved personnel, to reflect the proposed actions.
Preparation and Review