General Information
NRLP – C – 115 Sub Base Structures 1 # 2 - 44 T
Lifting Plan No.: Date: 25 – 05 – 2023
ZB556
Location: ZB-556 Contractor/Sub-Contractor SLB / IDC – 37
Permit-To-Work No: Risk Assessment No:
Description of lifting operation:
Lloading / Positioning on (Sub Base Structures 1 # 2 - ) On Ground to Truck – Crane by Tandem Lift
130 t HOOK BLOOKS ON ( 7 )PARTS OF LINE MUST BE INSTALLED ON BOTH (KATO KA – 1300 SL )(NK-1000) AS AGREED WITH ENI LTA
Method Statement:
To perform Loading / Positioning on Sub Base Structures 1 # 2
By: 2 X Mobile Cranes, Lifting Supervisor, 2X Singers, 1X Banks man, and Flagmen as required
All required documents shall be in place and shall be confirmed before starting the job (JSA, PTW, LP, TBT, etc.)
using two of 3rd party mobile cranes For Lifting Operation.
Pre-work check of site, load, and lifting equipment (lifting appliances and lifting accessories)
All lifting equipment shall have clear and legible SWL, all lifting accessories shall be correctly colour coded
Size, weight, shape, CoG of load shall be confirmed
Load shall be checked for any loose / potential dropped objects
Check proximity hazards, obstructions, load path and lay down area load bearing capacity.
Pre-work check of environmental conditions (wind speed shall not exceed 10 m/s, rainfall, foggy weather, etc.)
Confirm competency requirements match lift team personnel
Confirm and agree methods of communication: standard hand signals & radio.
Responsibilities to be clearly defined for all personnel
Lifts to be controlled by banks man who is clearly identifiable by wearing high visibility waistcoat
Establish barrier surrounding lifting operation area, non-essential personnel to be excluded at all times
Safe access, egress and escape routes (scaffolding, platforms etc.)
Tagline requirement: Tag lines are not required for tandem lift
No hand contact with loads until below waist height, no hands and fingers near pinch points.
Cable trays, beams, and any other obstructions shall be removed to allow the proper set-up of the crane prior to lift.
Any obstacle that might become in contact with the sling shall be removed.
Part of lines: Crane #1: 7 Crane #: 7
Details of the Load
Description of load/s: SUB BASE STRUCTURES
Overall dimensions [m]: 18 X 3 X 1,8
Weight of load [t]: [A] 44 t √ Known weight □ Estimated weight
Centre of Gravity: OFFSET □ Known (by drawing) √ Estimated position
Details of the Lifting Appliance # 1
Type of Lift. Appliance: Mobile Crane Model: KA-1300SL
Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved
40 t Load share on crane #1 Total Weight (22) × 1.25 = 27.5 t For Each Crane
radius [t]: [B]
Details of the Lifting Appliance # 2
Type of Lift. Appliance: Mobile Crane Model: KA – 1300SL
Jib length [m] (if applicable): N/A Fly jib offset [angle]: N/A
SWL at maximum involved
40 t Load share on crane #1 Total Weight (22) × 1.25 = 27.5 t For Each Crane
radius [t]: [B]
Details of the Lifting Accessories
Types of Lifting accessory: Slings / webbing / chains / shackles / spreader beam
Weight Identification
Type Quantity Certificate # Expiry Date SWL [t]
[Kg] Number
Crane (1) HOOK BLOCK - (KA-1300SL ) 1 600 8210106 LTG-IQ/A241912 18 – 10 – 2023 130 Ton
B1108 / B1109
Single Wire Rope Slings 2 100 ST – 4391 – 05 19 – 08 – 2023 16.6 TON
Crane(2) HOOK BLOCK - (KA – 1300 SL ) 1 600 8210072 ST – 4391 – 04 12 – 02 – 2024 130 TON
Single Wire Rope Slings 2 100 B1110 / B1111 ST – 4391 – 05 19 – 08 – 2023 16.6 TON
Total weight of Lifting accessories [t] : [C]=(D/1000) Crane #1 = 0.7 T Crane #2 = 0.7 T
Colour code: Blue Certification of Lifting accessories: □ YES □ NO
Unity Check of # 1 [%]: 70.5 % Unity Check of # 2 [%]: 70.5 %
ENSURE THAT ALL LIFTING EQUIPMENT HAVE BEEN CHECKED AND DEEMED SUITABLE AND SAFE
Lifting Sketch – As required
Sketch of the General Arrangement / Rigging:
[crane position / lifted item / obstacles and any additional details, as required]
MOBILE CRANE 130 T (KA – 1300SL )
EACH CRANE CABACITY @ CONFIGURATION :-
2 X Single Wire Rope Slings 40 T
SWL = 16.6 Ton L=6M Load Share :- 27.5 T
Boom 16.4 M
Boom 19.8 M
SUB BASE
KA1300SL
KA-1300SL
Radius 9 m
Radius9 m
Is lay down / landing area(s) adequate in both size and load bearing capacity? Yes
Obstacles Has route to be travelled been selected and cleared of obstructions? Yes
Lighting Is the lighting condition adequate to perform the operations safely? Yes
Demarcation Have barriers been positioned to prevent access to unauthorised personnel? Yes
Environment Are the weather conditions within limits to avoid their effects on the safety of the lifting operation? Yes
IF ANY OF THE CONTROLS IS NOT IN PLACE, THE OPERATION SHALL NOT START!
Communication What are the means of communication between the lifting team?
The Non-Routine Simple lifting plan shall be submitted to LTA for review and approval. LTA shall evaluate, in collaboration with
other members of the team, all possible corrective actions and advice to:
Reference documents
Reference Documents / Evidences / Attachments:
NOTE - HSE documentation (JSA/RA) shall be updated accordingly, in collaboration with HSE involved personnel, to reflect the proposed actions.
Preparation and Review
Prepared by: Signature: Date: 25– 05 – 2023
Reviewed by: Signature: Date:
LTA comments and review
Reviewed and Acknowledged by LTA and PIC
LTA: Signature: Date:
PIC: Signature: Date: