You are on page 1of 3

Date:

Name of site Incharge:


INVENTORY & CONDITION SURVEY OF BRIDGES
1 Name of Road
2 Road Section
3 Bridge Serial No. and Year of Construction
4 PWD No.
5 Location of Bridge in Km. and Chainage
6 Name of the River
7 No. of Spans
8 Span Arrangement (towards increasing chainage)
Span No. Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Length of Span between c/c of exp. Joint in m
Clear water way in m
9 @ starting of Bridge in m @ ending of Bridge in m
length of approach slab

10 Length of Bridge, face to face of dirtwall in m


11 High level or Submersible
12 Clear road way width between kerbs in m
13 Total outer width of bridge in m
14 Width of footpath in m
15 Details of Superstructure
A Gradient
B Type of Superstructure
C Type of Bearing
D Overall Depth of T-beam girder in m
E Material of Girder
F Hand rail & parapet thickness in m
16 Details of wearing course
A Type
B Approximate thickness in m
17 Details of Substructure
A Type of Pler
B Thickness of Pler Top
C Thickness of Pler Bottom
D Height of Pler
E Material used in pler
F Length of pler including cutwater at ends
G Height of Abutment
H Type of Abutment
I Material used in Abutment
18 Details of pler foundation
A Type of Foundation
B Material of Foundation
19 Details of Abutment Foundation
A Type of Foundation
B Material of Foundation
20 Details of Protection Works
A Bed
B Approach
21 Skew Angle in degree
22 Vertical Clearence (Below bottom of deck ) in m
23 Road Formation Level in m
24 Direction of Flow
25 Present Condition of Bridge
A Abutment
B Pler
C Girder
D Bearing
E Railling
26 Design Loading
27 High Floor Level (HFL)
28 Lowest Water Level (LWL)
29 Design Discharge (Cum/sec)
30 Maximum Design Velocity (m/sec)
31 Other Remarks
1 Height of embankment in m
2 Parapet top ht. from GL in m
3 Road ht. from min. Gl in m
4 Length of railling/parapet/kerb in m
Apron Type Condition

5 Watermark below soffit


6 Drainage Spouts
7 Services within 5/15m(for 4 laning)
8 Depth of Superstructure
9 Footpath requirement
32 SUPERSTRUCTURE
i Type
ii Condtion
iii Material used
Span No. 1 2 3 4 5 6 7
HC
Concrete Superstructure

Spalling
Corroded Reinforcement
Exposed Reinforcement
Crak
Leaching
Stains
Type of Expansion Joints
Type of Bearing (State Condition)
PIER SUBSTRUCTURES
Type Material
Direction of
Condition
Visible
Pler No. P1 P2 P3 P4 P5 P6 P7
Honey Combing
Superstructure

Spalling
Concrete

Corroded Reinforcement
Exposed Reinforcement
Crack
Leaching
PIER FOUNDATION
Direction of
Type
Visible
Pler No. P1 P2 P3 P4 P5 P6 P7 P8
Type of Foundation
Condition
Abutment No. A1 Abutment No. A2
Visible Cracks
Visible Cracks if any
if any
Condition Condition
Dirtwall
Dirtwall Condition
Condition
Side Return wall no. A1 Side Return wall no. A2
Type Type
Visible
Visible displacement at
displacement at
Condition Condition
Condition of
Condition of Protection of
Protection of
MISCELLANEOUS DETAILS
1 Railling Type
2 Drainage Spouts
3 Waearing Coat
4 Protection Works
INFORMATION ON RIVER & BRIDGE SITES
1 Upstream & Downstream
a Curvature of River
b Defined Channel
c On Rivers Banks
2 Type of Bed Materials
3 Vegetation in River Banks
4 Photograph Nos.
RECOMMENDATIONS