Earliest Start (ES) - The earliest time that an activity can begin after all preceding activities
have been completed
Earliest Finish (EF) - EF = ES + activity time Latest Finish (LF) - The latest time that an activity can finish without changing the project completion time Latest Start (LS) - LS = LF - activity time
Slack (or Float) (SL) = either LS-ES OR LF-EF
Forward pass—earliest times
o How soon can the activity start? (early start—ES)
o How soon can the activity finish? (early finish—EF)
Backward pass—latest times
o How late can the activity start? (late start—LS)
o How late can the activity finish? (late finish—LF)
o Which activities represent the critical path?
o How long can activity be delayed? (slack or float—SL)