Professional Documents
Culture Documents
4-2022
Design Report of the 2022 High Voltage Battery Pack and System
for FSAE TigerRacing Electric Vehicle
Clay Knight
Recommended Citation
Knight, Clay, "Design Report of the 2022 High Voltage Battery Pack and System for FSAE TigerRacing
Electric Vehicle" (2022). Honors Theses. 798.
https://repository.lsu.edu/honors_etd/798
This Thesis is brought to you for free and open access by the Ogden Honors College at LSU Scholarly Repository. It
has been accepted for inclusion in Honors Theses by an authorized administrator of LSU Scholarly Repository. For
more information, please contact ir@lsu.edu.
Design Report of the 2022 High Voltage
Battery Pack and System for FSAE TigerRacing Electric Vehicle
by
Clay Knight
Submitted to the LSU Roger Hadfield Ogden Honors College in partial fulfillment
of
the Upper Division Honors Program.
April 2022
Background ..................................................................................................................................... 5
2
Block Diagram of Subsystem ....................................................................................................... 26
Manufacturing ............................................................................................................................... 27
Wiring Diagram......................................................................................................................... 35
Ideal Timeline ........................................................................................................................... 36
Testing Timeline ....................................................................................................................... 37
3
Abstract
Figure 1: Main Components of the High Voltage Battery Pack Rendered by Josh Brooks
students must complete a senior design project. This involves designing and manufacturing of a
project and all project management associated. This paper presents the design of one subsystem,
the high voltage battery pack, for the 2021-2022 Project 48. Project 48’s objective is to design a
rules-compliant, safe, and optimized electric drivetrain to enable future LSU TigerRacing teams
to win the electric vehicle category in the Formula Society of Automotive Engineers design
competition. Two prior teams have attempted this project without successful completion. This
team has built on their progress to present a working prototype to the project sponsor for future
implementations.
4
Author and Project Introduction
My name is Clay Knight and presented is my design report of the Capstone project. I am
Electrical Design Engineering at BASF. I have accepted a full-time position with BASF as a
During the first two weeks of the fall semester, students are presented a multitude of
projects by their perspective sponsors. The two TigerRacing projects caught my attention as they
are some of the only Electrical Engineering heavy projects presented. The TigerRacing electric
vehicle (EV) project specifically was my first choice as it involved creating an entire drivetrain
and associated controls for a racecar. In this paper, the battery pack is discussed in different
units. One hundred eighty-four individual battery cells make up a module and four modules
make up the high voltage battery pack. Unless noted otherwise, work presented in this paper is
my own.
Background
where universities design and build a formula-style open-wheeled racecar each year and compete
against each other. TigerRacing has had much success with their internal combustion car, but
they are looking to race in the recently developed electric vehicle category. They tasked the team
with designing and building a working EV that is comparable, preferably better, to the internal
combustion (IC) car in the 2018 IC chassis. After a successful design and model is complete, the
TigerRacing team will be able to duplicate the drivetrain and controls in a new frame to race in
5
competition. This project has been attempted by two capstone teams before without successfully
producing a working vehicle; however, the previous team made great strides and left many of the
large parts behind for a new team to figure out how to make work together. These include all the
main parts of the drivetrain: motor, motor controller, battery management system, and the battery
cells.
The Formula Society of Automotive Engineers has a combined rule book where they
release new versions throughout the year detailing rules applicable to all racing vehicles and
features sections explicitly directed at electric vehicles. To begin, FSAE uses some non-
traditional terms and abbreviations throughout the rules to refer to different parts and systems.
The main definitions needed are as follows. [Formula SAE Rules 2022 2021]
EV.1.3 Accumulator
All the battery cells or super capacitors that store the electrical energy to
The following is a condensation of the key rules applicable to the high voltage battery
pack, and its related system. There are also guidelines for required documentation of each
6
EV.4.1.1 The maximum power drawn from the Accumulator must not exceed 80
kW.
EV.4.1.2 The maximum permitted voltage that may occur between any two points
EV.4.2.3 All power supplying the Tractive System must flow through the Energy
Meter.
Maximum energy of 6 MJ
Nonflammable Material (F.1.18) (not air) between the segments in the container
7
Previous Design
This is the third iteration of this specific senior design project. The first team had
designed their vehicle; however, they were disbanded due to the Covid-19 pandemic. The second
team made great strides in furthering the design of an electric racecar. This team fell short when
designing and implementing a homemade battery management system. They spent too much
time focused on this and were unsuccessful in welding and connecting their battery modules. The
second team did purchase all the main, expensive drivetrain components that this team reused.
This includes the motor, motor controller (inverter), battery management system, and the battery
cells themselves. At the conclusion of their assembly, they could only get the car to go five miles
per hour with a single battery module strapped to the overhead rollover bar of the vehicle.
Safety Concerns
Battery Pack
The first concern of the team is the arcing of the battery pack that needs to be addressed.
During assembly in the previous year, one of the battery modules arced on the welding table
creating a fire that had to be extinguished. This module will need to be evaluated for each cell’s
effectiveness and the arcing possibility limited. The team will take proper pre-cautions this year
to mitigate issues when handling the batteries like wearing high voltage gloves and ensuring that
8
Left: Image of Battery Pack Post Fire; Right: Damaged Module Separated in Containers
Battery Housing
The previous team did not properly implement a steel or aluminum housing as required
per the FSAE rules. The single battery module that did work was put into an oversized high
density polyethylene container which was then strapped to the rollover bar of the vehicle by duct
tape. This oversized housing allowed too much movement of the module resulting in arcing
occurring. After the current team disassembled the damaged module, approximately 20% of the
Design Requirements
The design requirements of the high voltage battery pack were driven by MATLAB and
Optimum Lap simulations as well as real-life data from the internal-combustion car. Optimum
Lap simulations were done over a 22km course to see how much energy would be needed to
complete the course with the vehicle. After each team member compared their specifications, it
was determined that the battery needed a minimum voltage around 280 volts, 50 amps nominal
9
Concepts Evaluated
Battery Connections
Metallic Strips
It is known that each series connection is about 20 amps maximum. From that, a chart
like that for wire gauge was sought detailing the different sizes and materials of wiring strips for
batteries. It was found that the strips would need to be 8mm wide by 0.7mm thick for nickel or
5mm wide by 0.3mm thick for copper. This would be about equivalent to a 16 AWG wire.
(Ampacity of Battery Metal Strips 2016) There was a desire to not use multiple strips as the previous
Metallic Rolls
There are now manufacturers who make metallic rolls in a standard grid pattern for
18650 cells. These can come in any length and up to twelve cells wide. The spacing between
cells must be able to work with the existing plastic spacers used to construct a battery module.
One preferred style was found which used a thinner piece of metal at each cell, so if the cell
discharged more than twenty amps, the metal would melt at just that cell. This would essentially
protect the module by fusing each cell. Rolls were found in multiple metals including the desired
nickel or copper, but some (mainly those on Amazon) did not provide thickness or ampacity in
details.
After reviewing other collegiate FSAE teams’ designs, it was discovered that multiple
teams used an oversea’ s manufacturer called Energus Power Solutions. (Design Report of the High
Voltage Battery Pack for Formula SAE Electric 2016) (LI2X4P25R: Li-Ion Building Block 3.6v/20ah/18c)
10
This company makes "building blocks" specifically for 18650 cells. They come in different cell
dimensions and include a variety of necessary features. The key feature about this is that each
block is fused and has a micro-PCB for cell monitoring and temperature collection. It is designed
to connect to their BMS, but they do sell the harness for other BMS integration. After that, the
blocks get bolted to each other in whatever desired connection style using copper bars. The
drawback of this is the cost; each block is about $75.00 USD. Even if this team cannot
implement this, it should be a goal of future iterations of the vehicle to upgrade the battery
Module Insulation
The battery will feature two stacks of two modules of cells. For insulation, the team and
LSU PCB Lab have on hand HDPE (High Density Polyethylene) sheets from the previous year’s
team. This provides a sturdy and protective layer between cell modules but will be improved
upon to ensure full electric isolation between layers of cells. This is enough insulation per FSAE
rules, but additional insulation will be added to ensure proper insulation. This shall be
accomplished by anodizing the aluminum housing, as well as covering the inside of the housing
with electrically insulating paper. Paper alone is what failed the last team, so it was not included
A tape style insulation would be beneficially to insulate individual cells since it has
adhesion properties. However, it is difficult to make a solid layer out of multiple strands of tape.
(i.e., Kapton Tape). This tape could also be at risk for friction related tearing due to its thinness.
11
Plastic Sheeting Insulation
Provides rigid insulation layer between cell packs and can give uninterrupted protection
per each layer; this means less chance for arcing. HDPE is a sturdy plastic that would be great
due to its robustness in applications where it will face frictionally wear due to rubbing of the
Foam Insulation
This would provide uninterrupted protection, but this style of insulation is bad for its heat
dissipation properties. Foam insulation is what is typically used around car batteries to protect
them from engine heat or keep warm for cold starts, but this is a negative effect for this race
12
Analysis
Five different module possibilities were evaluated. The team wanted the modules to be
the same size for ease of install and duplication for spares and replacement. Values such as
power, voltage, energy, and weight were found per string, per module, and in totality. The pack
needed to have enough capacity to ensure competition of the endurance competition and enough
power for proper speed. The design was constrained by FSAE rules and the reused BMS. The
max BMS voltage was 388V. (Lithium Ion Battery Management System - Orion BMS 2019) The team
started with three modules which failed constraints or desired variables. Two more combinations
were then evaluated, and the team agreed on a four (4) module battery with twenty-three (23)
series by eight (8) parallel connections. This satisfied all design constraints and subsystem
requirements. Key specifications of the system are a 331.2 Vdc nominal output with 6.622kWh
Constraints
Power 80kW
Voltage 600V
Voltage/segment 120V
BMS Taps 108
Energy/segment 6MJ
BMS Voltage 388V
13
Number of Bricks 4 5 6 4
Length x Width/brick
494.91x164.97 366.6x183.3 311.61x164.97
(mm)
14
Chosen Design
Number of Bricks 4
Volume/brick (cm^3)
15
MATLAB Calculations
After a few miscalculations were discovered, the necessary variables were then
implemented into a MATLAB code which took the characteristics of the individual Samsung
18650 cell along with the user-defined number of strings, parallel connections, and modules and
16
Figure 3: MATLAB Variable Output
The values gathered from the MATLAB script matched the values calculated in the Excel
spreadsheet.
17
Wire Gauge
Based on a maximum voltage drop of 3%, length of 3 feet, and a maximum possible
current of 200 amps, a voltage drop index (VDI) of 60.39 was calculated. Based on the VDI
table, the wire gauge between the battery and motor controller and the wiring between the motor
controller and motor should be 3/0 AWG. (Wire Sizing Chart and Formula) Due to pricing and
availability, a wire of 4/0 AWG will probably be used. The wiring must be orange or wrapped in
orange conduit per FSAE rules. The voltage loss in the 3/0 wire was found to be 0.105 volts and
a resistance of 0.077Ω/1000 feet at a power factor of 0.9. With this gauge and this short length, it
is seen that voltage drop and resistance of the line are negligible.
𝐴𝑚𝑝𝑠 × 𝐿𝑒𝑛𝑔𝑡ℎ(𝑓𝑒𝑒𝑡)
𝑉𝑜𝑙𝑡𝑎𝑔𝑒 𝐷𝑟𝑜𝑝 𝐼𝑛𝑑𝑒𝑥 (𝑉𝐷𝐼) =
% 𝐷𝑟𝑜𝑝 × 𝑉𝑜𝑙𝑡𝑎𝑔𝑒
200𝐴 × 3 𝑓𝑡
𝑉𝐷𝐼 = = 60.39 → 𝟑/𝟎𝑨𝑾𝑮 𝒘𝒊𝒓𝒆
3% × 331.2𝑉
18
Discharge Curves
The battery total statistics were input to a Simulink model which gives discharge curves
over a time. This analysis was done to see the idealized time that the battery could last. The
results of the simulation were a nominal current discharge of 34.78 amps for 2.08 hours.
19
Single Battery Discharge
20
Figure 6: Temperature During Full Discharge
21
¼ Load on One Module
One module, out of the four total was discharged with a constant 6.25kW load (1/4 of
22
Figure 9: Temperature During Full Discharge
23
25kW Load on Full Battery
The full battery details were input and a change of 10°C was found. The 25kW came
from a OptimumLap simulation on the FSAE Lincoln Course model done by Carson. This
temperature model for the full battery is likely inaccurate since it only is considering the battery
as one unit.
24
Figure 12: Temperature During Full Discharge
25
Bus Bar Dimensions
Another task was to investigate if the copper bus bars chosen and purchased by the
previous team could be smaller. The vehicle should only see about a 30°C rise in temperature
under the worst conditions, and the max amperage of the system is 180 amps. This current was
rounded up to 200 amps for a safety factor and to give some expansion room for future teams. It
was found that the bus could be 1/8”x3/4” or ¼”x1/2” in L x W. It was already planned to
shorten them by about 1/2" and this confirms that they could also be made thinner by about 1/4".
This now allows for a design where two bus bars can be placed into one 3D printed holder,
connecting one battery’s positive to the negative of the next. Space will be saved in the housing
and points of failure are now decreased when doing the parallel connections. (Ampacities and
26
Manufacturing
The battery modules will be connected to all the necessary BMS sensors and leads. The
modules will then be placed into HDPE containers per each of the four modules. These HDPE
containers will contain the batteries preventing arcing between the modules and the housing will
be lined with an electrically insulating paper that will contain any fires to one module. The
modules will then be placed inside of the aluminum accumulator housing where they will
terminate on terminal blocks. These terminal blocks will have a single cable off each out of the
container leading to the manual disconnect. After that, the battery will send power straight to the
Testing Plans
This test comprises of testing the high voltage battery module and housing to ensure it is
electrically insulated, and all arc potential is eliminated. The batteries were the source of failure
for the previous teams. Last year’s team had an arc fire due to the battery being improperly
insulated and not having shock protection. Testing will be simple, yet vastly important for safety.
It involves a multimeter, the insulation monitoring device, and a voltage detection pen. After the
battery modules are within their HDPE containers, potential and resistance will be measured
between the positive bus and outside of the container. There should be zero potential and infinite
resistance. This ensures that there are no shorts inside the HDPE. After the four HDPE modules
are inside the aluminum housing, the potential and resistance will be measured again to ensure
proper sealing of the containers. There will also be a visual inspection of all wiring connections
made to the batteries and the housing. Once the aluminum housing has been proven to show zero
27
voltage with respect to positive of the battery pack, it will be placed in the car’s chassis and
hooked up to the chassis-grounded insulation monitoring device (IMD). The IMD should output
12V when there is complete isolation between the chassis ground and negative contacts of the
battery pack. A 96kOhm resistor is to be placed in between the negative contacts and chassis
Data will be collected by reading the multimeter screen and verified by the test-conductor
to confirm zero volts and infinite resistance between the batteries and their housings. This test
must have multiple iterations during performance testing of the vehicle. During assembly of the
vehicle, this test helps to keep all persons working on the car safe. After operation, the batteries
will have suffered shocks and vibrations, and this test will need to be reconducted to ensure the
modules are still electrically insulated. Voltage/current cannot leave the housing by any means
The objective of this test will be to measure the endurance and power output of the
battery as well as the battery thermals. This integration test is designed because the battery must
be load tested to ensure that it can safely handle and deliver the desired load and capacity for
competition. This will be done through a load test of the battery using a dynamometer.
Prior to assembly, the previous years’ batteries were taken apart and individual 18650
cells were voltage tested with bad cells being discarded for proper recycling. The batteries have
been assembled, and the completed battery housing will be brought to Mr. Mike McAnnelly’s
lab at PCS 2000 for load testing. There, it will be connected to the motor and motor controller.
The motor will then be coupled to a dynamometer. This gives an accurate load-speed profile of
the motor and ensures that everything is good with the motor controller.
28
Data for individual cell testing was gathered using a LiitoKala Lii-500. A sample module
was put into a spreadsheet for extrapolation. This was done to see how many and how bad the
cells were from a battery pack. Data for the load test will be acquired by reading the output
to be analyzed later. Analysis will be done to determine a load v. speed profile as well as a load
v. thermal profile. This will allow the team to see how the battery performs under load and the IR
thermometer will find any hot spots and ensure that proper heat dissipation is occurring.
Tests Conducted
Single Cell Discharge Test
A single cell was discharged across different resistances that were available in the LCB
lab. The cell temperature was measured throughout using a Klein Tools IR thermometer. The
temperature change was negligible and can be attributed to ambient temperature changes as the
29
330Ω 0.0127A
Initial 75.7°F
2 minutes 75.4°F
5 minutes 75.2°F
100Ω 0.042A
Initial 75.2°F
2 minutes 74.5°F
5 minutes 73.9°F
10Ω 0.42A
Initial 73°F
2 minutes 76.6°F
5 minutes 75.6°F
7.5 minutes 73.6°F
15 minutes 75.4°F
10/100/330 0.48A
Initial 74.5°F
5 minutes 73.8°F
10 minutes 75.6°F
15 minutes 74°F
Table 5: Temperature over Time
series to get the designed pack voltage and capacity. The constant load tests could not go for as
long as desired due to electrical tape melting. The load bank used was overvolted by these
battery packs which could have contributed to this issue. The group ended up going pack to this
power lab the next week and doing an endurance test on one module around 45A and found it to
last 18 minutes before there was a heat issue where the plastic sheet began to melt. This load is
what is anticipated after the vehicle takes off to maintain max cruising speed. This test was also
30
Figure 16: Load Test Setup
Start Final
Start End Resistance Expected Measured
Module Temp Temp Time
Voltage Voltage (Ω) Current Current
(°F) (°F)
5
4 95 92 11.5 8.2A 8.4A 76.5 76.5
minutes
5
3 95 92 11.5 8.2A 8.4A 73 73
minutes
5
2 95 92 11.5 8.2A 8.4A 76.5 76.5
minutes
5
1 95 92 11.5 8.2A 8.4A 73 73
minutes
70
ALL 378 347 11.5 30A 34.5A 72.5 78
seconds
5
ALL 378 319 4.6 75A 72.8A 72.5 74.5
seconds
32
ALL 373.5 319 6 60A 60.2A 72.5 74.5
seconds
18
4 93 70.06 2 47.5A 44A 76 115
minutes
Table 6: Results from Battery Load Test
31
Setbacks as of Time of Writing
The first setback with the battery pack came under disassembly. It was underestimated
how much time it would take to disassemble the existing pack. This had to occur to recharge the
cells after most had sat around for two years, so they could be rearranged into a new style. The
multiple layers of strips had to be ripped off two to three at a time with a needle-nose pliers on
both sides of the battery modules. After this, the cells were broken up by series connections, and
the plastic separators were removed. Once the cells were individualized, they were placed into
the chargers to test the voltage on them. If it was below 3.5V, the cell was placed for disposal.
The team had four chargers that can measure four cells at a time.
There was then great debate among team members about whether to do copper or nickel.
All agreed that copper was the superior option, but there was no cost-effective way to weld the
strips. The existing welder that the team had could only weld nickel effectively. The team tried to
make new electrodes for the welder out of tungsten which worked to an extent but only on the
fixed spot-welder. The hand welder, which was the one needed, could not have its electrodes
changed.
After copper failed, there was no other cheap solution besides nickel. Jacob ordered a
good length of the nickel roll style connection to just go ahead with that despite hesitancy from
some team members. This was necessary as the team was now two weeks behind schedule due to
Now that the nickel rolls were cut to length, it was time to weld. After welding a few
cells and small sparks occurring, it was recognized that there was an issue. Upon further
investigation, it was determined that the cells needed to be of very similar voltage prior to
welding; otherwise, when welded, the cells would have a volatile reaction to equalize their
32
voltages. The modules were then taken apart again during Spring break and each cell was
charged individually. The cells were charged sixteen at a time in the chargers until they reached
a voltage of 4.19 or 4.20V. Ensuring minimal difference between cells decreases the risk of
Future Improvements
The main improvement recognized and recommended for future teams and designs is the
implementation of the Energus Power Solutions building blocks. Current strip welds are prone to
failure and have a low safety factor due to being homemade. The building blocks described
would fuse every eight cells and provide a dedicated BMS port and temperature monitoring- all
features not currently found or required in the existing design but better.
33
APPENDIX
34
Wiring Diagram
Figure 17: Wiring Diagram of the High Voltage System Made in Solidworks Electrical
35
Ideal Timeline
36
Testing Timeline
37
Figure 18: Variables Input for MATLAB Endurance Curves
38
Figure 20: VDI vs. Wire Gauge of Copper and Aluminum Conductors
39
P48 Spring Midterm Budget Status
Budget Remaining,
$910.97 , 31% Ewert Energy , $326.60 ,
11%
Digikey,
$68.29 ,
2%
Mouser, $252.32 , 9%
Timershop,
$26.02 , 1%
OSH Park, $209.35 , 7%
Arduino, $25.17 , 1%
40
Picture 1: Team Doing Interview with Entergy Media
41
Picture 2: Screenshot from ENGR Weekly 2/28/2022 of Team Entergy Check Presentation
42
Works Cited
Copper Development Association Inc. (2017, September 28). Ampacities and Mechanical
Properties of Rectangular Copper Busbars. copper.org. Retrieved January 23, 2022, from
https://www.copper.org/applications/electrical/busbar/bus_table3.html
Davey, J., & Dankoff, W. (n.d.). Wire Sizing Chart and Formula. RES Supply. Retrieved
November 22, 2021, from https://ressupply.com/learning-center/wire-sizing-chart-and-
formula
Energus Power Solutions. (n.d.). LI2X4P25R: Li-Ion Building Block 3.6v/20ah/18c. energusps.
Retrieved February 22, 2022, from https://www.energusps.com/shop/product/li2x4p25r-li-
ion-building-block-3-6v-20ah-18c-229
Ewert Energy Systems. (2019). Lithium Ion Battery Management System - Orion BMS.
orionbms.com. Retrieved November 12, 2021, from
https://www.orionbms.com/downloads/documents/orionbms2_specifications.pdf
Formula Society of Automotive Engineers. (2021, November 11). Formula SAE Rules 2022.
fsaeonline. Retrieved November 20, 2021, from
https://www.fsaeonline.com/cdsweb/gen/DownloadDocument.aspx?DocumentID=4d9d4c
4c-f82a-4810-9122-d66ff9138d26
Matador. (2016, November 13). Ampacity of Battery Metal Strips. endless-sphere. Retrieved
February 26, 2022, from https://www.endless-
sphere.com/forums/download/file.php?id=248217&sid=2173cfeb2ee010717857c132447ca
304
West, L., Shepherd, B., Karabon, N., Howell, J., & Pyrtko, M. (2016, December 12). Design
Report of the High Voltage Battery Pack for Formula SAE Electric. Wisconsin Racing.
Retrieved October 15, 2021, from https://www.wisconsinracing.org/wp-
content/uploads/2020/10/WR-217e_Accumulator_Design.pdf
43