Professional Documents
Culture Documents
For many years, risk management in construction projects has been approached using a
reductionist approach that produces poor results and limits the quality of project
management. For example, most of the times risk is handled through the application of
contingencies (money) or floats (time) that are not determined based on a comprehensive
analysis of the risks that can affect a particular project, and that in many cases are clearly
insufficient to cover the consequences of risks that do occur during the project
realization. Then, in most of the cases projects end with costs overrun and late.
Project risk management has been intensively discussed in recent years. Projects are
becoming shared efforts of multiple parties – construction industry is a good example of
an area, where the project outcome is delivered in an extremely complex actor network.
Still, research on how the project risk management should be adopted to the network
environment is scarce. This study's objective is to identify the risks that are caused by the
network structure and the ways to manage risks in the co-operation of the whole project
network. The focus of the study is put on the informal risk management means. The
purpose is to emphasize other than legally binding contracts as risk management means.
A lot of the risk management research is targeted to the construction projects, which are
seen as extremely risky projects with highly inflexible risk management by contracts.
Number of studies are stressing the importance and superiority of the co-operation and
less formal risk management means, but concrete methods are not introduced. In
addition, the use of already developed risk management methods is modest at
construction sites. The basic idea of the model is to take the advantage of higher-level
co-operation and to switch a project risk management in construction networks from
dyadic relationships more towards the network-level co-operation. According the
understanding gained during this study it is suggested that by enabling more co-operative
risk management methods, the project risk management will become more efficient and
identified inefficient and costly network governance practices – serving as a source for
risks – would be reduced.
We also propose a more socially sensitive approach to risk management, which considers
the needs of all stakeholders and recognizes how the activities of the construction and
facilities management industries affect society. This is important in all projects but
especially in large projects which arouse special community interest and expectation. In
particular, because many large projects are now procured via public– private partnerships,
there is an increasing pubic expectation that shared project ownership means shared
project information
Risk Identification:
The main goal of Identifying risks is to generate an organized and structured list of
identified risks, showing their characteristics, causes and consequences, so it can be used
during next phases or even in other projects. This is an iterative process since new risks
can occur during the project life cycle or in which existent risks become more obvious.,
Even if companies have the knowledge of the existing risks, the level of concern
regarding risk management is not high and many companies do not use routinely a
complete risk treatment. Companies mostly identify risks using the brainstorming
technique where an identification list of risks is produced in mutual agreement between
project stakeholders. (9)
Risk identification is an iterative process that involves the project team, stakeholders and
other managers affected by or who affect the project, and finally outside individuals who
can comment on the completeness of the risk identification based on their similar
experiences.(1)
Four techniques are commonly used to identify risks in construction projects:
1. Industrial checklists are typically prepared by a documentation specialist for various
project and product documents. Checklists often key into potential failure points in past
projects and thus are very useful in identifying risks. Interviewing project personnel from
each discipline and staff within the organization who have experience of similar projects
ensures that corporate knowledge and personal experience are utilized in the process of
identifying risks. This technique allows project personnel to identify the risks that they
can see in the project and gives them a feeling of involvement in the process and
ownership of the identified risks, which should then lead to a greater acceptance of any
measures implemented to reduce the risks.
2. Interviews with key project participants or analysis of historical data for similar
projects and examining similar current or previous projects, risk assessments, lessons
learned or project evaluations are other means of obtaining feedback about risks.
3. Examining historic data from previous similar projects utilizes corporate knowledge.
However, an organization may not have carried out a similar project, or the data from a
previous similar project may not have been recorded; thus, this technique can only be
successful in a limited number of cases. Database systems that actively manage and
report the progress of projects may be a useful source of information. However, such
systems are often limited in terms of the useable or relevant data that are stored.
4. Brainstorming with the project team may be valuable for projects involving new or
unusual risks, innovative management arrangements or to develop initial checklists. This
technique may be a useful element of risk management workshops.
Brainstorming sessions involve getting the key project stakeholders together to identify
and priorities the risks in the project. This technique enables the stakeholders to hear what
the other members of the project team see as risks and to use these ideas to inspire them
in identifying additional project risks. It is important to choose the people who comprise
the brainstorming group carefully because the right mix of project personnel with
appropriate experience and seniority is needed to ensure a successful session.
Types of Risks:
a) Technical risks
Inadequate site investigation
Incomplete design
Appropriateness of specifications
Uncertainty over the source and availability of materials
b) Logistical risks
Availability of sufficient transportation facilities
Availability of resources-particularly construction equipment spare parts, fuel and labor
c) Management related risks
Uncertain productivity of resources
Industrial relations problems
d) Environmental risks
Weather and seasonal implications
Natural disasters
e) Financial risks
Availability and fluctuation in foreign exchange
Delays in Payment
Inflation
Local taxes
f) Socio-political risks
Constraints on the availability and employment of expatriate staff
Customs and import restrictions and procedures
Difficulties in disposing of plant and equipment
Insistence on use of local firms and agents.(4)
Example for risk probability, a company may say that there is a 5 per cent probability that
labour costs on a project will increase by $100,000. This means that they have data,
experience or opinions to predict that on five projects out of every 100 projects labour
costs will increase by $100,000. This risk can be expressed in terms of a single figure,
which reflects its consequences for a project’s budget. This can then be included as a
contingency in that budget and is calculated by multiplying the probability of the event
by the consequence if it occurred. In this case, the risk can be expressed as:
Risk = Probability of event ×Magnitude of loss/gain
0.05 × $100,000 = $5000
Calculating risk allowances
By Expected monetary value method
The assessment identifies the impact of risks in terms of both the impact and the
probability of occurrence. This can be expressed as the simple formula:
Risk exposure = Impact x Probability.
It is important that all the potential risks and uncertainties which can affect the project
and are likely to act as constraints on the project be identified as early as possible. Once
the risks have been identified, the risks are then subjected to an assessment that
categorizes the risks into a subjective probability of occurrence and into three categories
of impaction on the project – optimistic, most likely and pessimistic outcome. Two rules
should be obeyed in the calculation: first, the most likely outcome must have the highest
value and, second, the total value of probability for the three outcomes must always equal
one. This method is simple and transparent and allows the consideration of more than one
risk. However it has the disadvantage that it is unable to consider linkages between risks.
(10)
Decision trees
Decision trees can be useful where the scenario is more complex. They are graphical
representations that are useful in assessing situations in which the probabilities of
particular events occurring depend on previous events and can be used to calculate
expected values in these more complex situations.
The decision tree in Figure 3 shows two risks – A (Adverse weather at the contractor’s
risk) and B (Potential claim from the client of delay damages – acceleration is thus
required to make up lost time).
Acceptable mitigation steps of treating risk must be employed once the project risks have
been known and analyzed. These mitigation steps are based mostly on the nature and
potential consequences involved in the risk. The main objective is to increase the level of
control of risk, reduce the negative impact of the risk and remove as much as possible the
potential impact. Measure becomes more effective when there is more control of one
mitigation measure on one risk. Six distinctive risk responses are retention, reduction,
control, sharing, transfer and avoidance. The choice of response must correspond to the
importance of the risk; it should be financially cost effective and realistic with regard to
the project timing; it also must be accepted by other parties involved.(3)
After classifying all risks that occur or may occur in the project actions need to be
undertaken to propose specific countermeasures for each of the identified risk. These
actions can be twofold. Firstly, they may aim to complete neutralization of negative
impacts on the project or focus on reducing the pejorative influence. These reactions can
be divided into four main groups:
Acceptance of risk (active, passive) – involving acceptance of project’s risk at a specific
level. We accept all the consequences arising both from lack of time as well as financial
resources.
Transfer of risk - associated with the transfer of hazard to another entity demonstrating
the ability to neutralize risk. One form of transfer is a direct transfer of losses effects to
another entity. The principal form of such an activity is insurance, which allows legal
transfer of occurring effects. An example of risk transfer is to commission an ‘uncertain’
task to the contractor or transport services to the shipping company.
Reduction, risk mitigation - are actions that reduce the probability of an event and
overcome the effects of risk, for example, through the creation of resources inventories or
balancing one risk by another and thus reducing the overall risk. The principle of risk
mitigation may be introduced at each stage of the project, from the planning period and
organizational activities.
Avoiding risk - involving either preventing the occurrence of risk or the
removal/elimination of risk from the entire research process. In this case we do not take
the risk that exceeds the acceptable level allowed by us.(5)
Risk response (Figure 4) is also associated with the production phase. Both the clients
and the contractors mostly manage risks in this phase. This is due to the traditional
approach in the construction industry: contractors do not put enough effort into
preventing problems and solve them as they appear in the project.
Fig 4 Risk response in the different phases
In the programme phase, similarly to the risk identification and assessment processes,
risk response is performed by the client. In the planning phase the client together with the
consultant responded to the project risks. In the procurement phase risk response is
performed mainly by the contractor. In the production phase the role of the contractor is
large and the degree of joint risk management is high.(6)
Monitoring and controlling:
The last process is Monitoring and Controlling Risks that consists in executing Risks
Responses Plans (being followed by the identification of risks), monitoring the residual
risks and identifying and assessing new ones, as well as the efficiency of all evaluation
during the project.1 Although risk responses are executed during the whole life cycle of
the project, the project must be continuously supervised in such a way to detect new risks
and possible changes. (9)
8. Martin Loosemore, John Raftery, Charlie Reilly, Dave Higgon Second edition Risk
Management in Projects.
10. Keith Potts and Nii Ankrah Construction Cost Management Learning from case studies
Second edition.