WORK
Note: This scope covers requirements of tankage jobs only and the job scope of
pipeline / mechanical jobs will be as per the SOR.

Tank fabrication Works:

1.0 SCOPE OF WORK


1.1. Contractor’s Scope of Work :
The scope of work of Contractor shall include the following but not limited to the same. The
scope of work shall also include other items / works required to complete the work in all respects
as per specifications, standards, drawings, IS codes/API Standards & instructions of HPCL
whether specifically mentioned or not in the tender document :
i) The Contractor shall perform the work.

ii) Getting approvals from statutory authority/ local authority etc, if any required except
construction approvals from CCOE /local bodies which will be obtained by HPCL.

iii) The Shell and Wind Girders have been designed by HPCL as per API 650 (latest
Edition).The Contractor shall independently verify the above design and confirm his
verification and there upon the adequacy of the Free issue plates immediately upon
award of the contract.

iv) Preparation of all detailed and working drawings including plate cutting diagrams for various
components of storage tanks & getting the same reviewed and approved by HPCL.

v) Preparation, Submission for Review and obtaining approval from HPCL for Detailed Quality
Assurance System plans/ procedures developed by contractor basis Std. Inspection & Test
Plan furnished in this tender/ Scope of work/SOR/GTCC/SCC & other relevant codes. The
same shall be reviewed / approved by HPCL prior to commencement of work. The required
competent man power, machinery, tools, tackles, equipments, etc required to execute the
work as per the Approved Quality assurance plan (QAP) shall be the responsibility of
contractor. Due records will be maintained by contractor through out the work period as per
instructions of Engineer-in- Charge.

vi) Time is the essence of this contract. Monthly/weekly Execution Plans will be developed by
Contractor in consultation with Engineer- in- Charge & execution of work as per these plans
will be the sole responsibility of contractor.

vii) Procurement & Supply of materials & consumables as indicated in contractor’s scope of
supply.

viii) Loading, transportation and handling of all free issue materials from Owner’s stores to work
site/ Contractor’s store and fabrication yard as applicable including supply of all necessary
tools, tackles, transportation and handling equipments, etc.
ix) Stripping/Removal of vegetation for fabrication yard at Site.
x) (Deleted)
xi) Fabrication, erection and testing including vacuum box testing, liquid penetrant test, diesel
chalk test, etc of tank bottom-annular and sketch plates, shell, wind girders with gusset plate
stiffeners and all other plate attachments including cutting of plates and structural of required
size, edge preparation, rolling, fitting, aligning, welding etc. SHELL ERECTION SHALL
BE STRICTLY BY JACKING UP METHOD ONLY.
xii) Supply, Fabrication and erection of various shell appurtenances and nozzles.

xiii) Supply, Fabrication and erection of Inlet and outlet troughs for Inlet and Outlet nozzles.

xiv) Supply, Fabrication and erection of various Roof appurtenances and nozzles.

Supply & fabrication of stairways, handrails, landing platforms, curb


angle, bracing for foam dam, structural supports for wind girders, interconnecting walkways
etc.

xv) Supply, fabrication, installation and testing of various roof appurtenances.

xvi) Supply, fabrication & erection of Gauge hatch with still well, still wells for level transmitters,
level switch & temperature instruments etc.

xvii) Supply, fabrication & erection of earth connection as per respective IS code.

xvi) DP / Diesel chalk/ Vacuum box test/ any other test on various components of tanks as per
Specifications of this Tender document, requirements of IS/API standard & instructions from
Engineer-in-Charge.
xxvii) Calibration of tanks and getting approval from CPWD/Legal Metrology authorities of the
State Govt using contractor’s own tape etc.

xxviii) Carrying out hydrostatic / water fill up test in accordance to OISD 129/ Standard
Specifications of this Tender & keeping the records for same, pneumatic , vacuum & other
test as specified in code/ specifications & as per requirements of Engineer-in-Charge using
contractor’s own equipment.

xxix) Accomplishment of any other item of work required to make the storage tanks ready for
commissioning and as per instruction of Engineer-in- Charge.

xxx) Assistance to HPCL for commissioning of the tanks including supply of manpower,
supervision, labour with all required tools and spares. This commissioning assistance shall
extend up to 24 hrs beyond completion of first Pump-in of product in to the tanks.

xxxi) Supply of all equipment, machineries, tools, tackles etc, labour and supervision of all works
at site.

xxxii) Clean-up job at site for all surplus material, debris, scrap, construction equipment etc as per
direction of Engineer-in – charge.

xxxiii) Reconciliation of free issue steel / material and returning excess plates, off cuts and scrap as
per direction of Engineer-in – charge.

xxxiv) Supply of Power and Water required for the job shall be the responsibility of the
Contractor & will be in his scope. HPCL will not give any connection from their
existing electrical or Water supply system Surplus water declared by HPCL in writing
after Hydro test shall be disposed off by Contractor in an un-objectionable manner to HPCL
& its neighbors.
xxxv) Contractor has to perform work in running installation with HOT/ COLD Permit in
accordance to OISD 105 and HPCL operational requirements. Complying & meeting all the
safety rules & regulations as per standards & instructions of Engineer- in – Charge will be
the sole responsibility of contractor.

xxxvi) Supply of all required materials, supplying and providing Single/Double scaffolding
wherever required, Carrying out sand blasting and surface preparation, primer and finish
painting.

2.0 SCOPE OF SUPPLY

2.1 OWNER’S SCOPE OF SUPPLY

2.1.1 Subject to the provisions mentioned elsewhere in the tender document, HPCL will issue the
following materials free of charge from Stores at Site
for the Steel plates required only for the following components of the tanks:
- Bottom: Annular Ring & Sketch plates

- Shell plates
- Roof plates
- Reinforcing pads for all shell /roof openings and manholes except cleanout nozzle.
- Datum plates for gauge well pipe.
- Primary/Secondary wind girder (For all C/R tanks only) including plate gussets/ plate
stiffeners.

THE WEIGHT OF ABOVE PLATES WILL BE BASED ON SP. GR. OF STEEL @ 7.85. THAT
IS, UNIT WEIGHT SHALL BE 7850 KG/CU.M.

2.1.3) SCRAP/ CUTTING ALLOWANCES FOR OWNER’S FREE ISSUE


MATERIALS

The plates will be issued by HPCL to the Contractor on Theoretical weight basis. At the end of
the work, Reconciliation shall be also done on theoretical weight basis only.

A Tabulated statement showing the size wise plates issued and Total consumption will be
prepared as per HPCL instructions. Based on the Total consumption in MT as a sum of
individual size wise consumption for a particular site, generation of maximum 2.7%
Returnable accountable scrap is allowed. The Returnable Accountable scrap includes Off cuts
and plates smaller than 2400mm perimeter .Off cut plates shall be of minimum perimeter 2400
mm generated as per approved cutting Schedules. Plates smaller than 2400mm in perimeter are
also classified under Returnable Accountable Scrap. On an overall basis, the generation of
accountable scrap shall be limited to 2.7% of total net consumption taken as a sum of net
consumption for various sizes. However, the Contractor shall make an all out effort at the time
of preparation of Drawings/ BOQ to limit the generation of Returnable Accountable Scrap to a
minimum preferably less than 2.7%.It will be the responsibility of the Contractor to load,
transport the accountable scrap, weigh at weighbridge including payment of weighbridge
charges, return to HPCL Premises, Unloading and handing over to HPCL at their Store yard/
scrap yard as per instructions of HPCL Engineer-in-Charge. Apart from Accountable Scrap,
the Contractor shall be allowed a maximum of 0.30% of Burnout Losses.
In case, the actual generation of Returnable Accountable scrap on overall basis is higher than
2.7% or burnout losses being greater than 0.30% of Overall consumption(Theoretical tonnage),
then HPCL shall effect recovery @ Rs. 60,000/= per MT for excess scrap generation and/or
burnout loss. It shall be therefore the sole responsibility of the Contractor to plan the cutting
schedule to control his scrap generation within above limits.

2.2 CONTRACTOR’S SCOPE OF SUPPLY

The procurement and supply in sequence and at the appropriate time of all materials and
consumables including structural steel (Plates & sections) required for completion of works as
per drawings, specifications and standards shall entirely be the contractor’s responsibility. The
items to be supplied by the contractor are in general but not limited to following:

A) All steel plates required for the components other than those where HPCL will be supplying
plates vide SOR.

B) All consumables such as electrodes, filler wires, acetylene, grease, oil, gases, electricity etc.

C) All structural steel sections wherever required for curb angles, Top wind girders
Supports/stiffeners/ extensions for stairways, Self supporting truss of C/R, Secondary wind
girders, spiral stairways, landings , platforms, handrails, interconnecting walkway structurals,
Inlet and Outlet Nozzle Troughs, Gratings(which may be fabricated by the Contractor at a
workshop/ factory outside HPCL premises), etc.

D) All seamless pipes for nozzle necks 300mm NB and below, internal pipes, Nozzle necks for
openings more than 300mm,Materials for Inlet/ Outlet Nozzle troughs, vents, emergency
drain, extension piping for roof drain, etc.

E) All pipe fittings, flanges, matching flanges and blind covers wherever specified for all
nozzles, brass items etc.

F) Bolts nuts and gaskets for roof & shell manholes, nozzles with blind cover / matching flange,
bolts & nuts for roof structure and other structural works.

G) Gauge Hatch with cover.

H) Deleted

I) Pipes, fittings, flanges, orifice plates, Foam makers/ Pourers and deflectors on point of spray
on shell and structural supports for Piping for Foam system

J) MS Deflector plates including supporting arrangement required for cooling system.

K) Internal Bolts & Gaskets.

L) Strapping tapes & accessories for calibration.

M) Earth connections, support cleats for pipes, structurals & cables.


N) Any Blind flanges, valves, nipples, plugs, bolts, nuts, gaskets, etc required for conducting
hydrostatic testing and any other test required by HPCL.

O) All primer materials and painting materials, scaffolding, coarse sand for sand blasting and
related equipment for Painting.

Note:

1.Contractor should ascertain the exact quantity required as per drawings as well as in
consultation with the engineer in charge before procurement of the same.
2.The materials procured by contractor should be in line with the specifications mentioned
in the subsequent chapter ie.”Specifications for Materials in Contractor’s scope of supply”.

3.While every effort has been made to list all the supply items, it shall be the sole
responsibility of the Contractor to review the list and seek clarifications, if any at the time
of Unpriced Bid itself. HPCL undertakes to provide only Free Issue Steel plates for
Fabrication and all the other items shall be supplied by the Contractor only. No claims/
disputes by the Bidder/ Contractor shall be entertained by HPCL at a later date.

3.0 DOCUMENTS / FABRICATION DRAWING DETAILS


The Contractor shall submit the detail fabrication drawings/ documents in the following
sequence:

1. Drawing Index

2. General arrangement drawing of tank showing design data, basic dimensions, thickness,
nozzle & internal parts.

3. Bottom and annular ring layout.

4. Shell plate layout showing location of nozzles & their distances from weld seams.

5. Nozzle orientation on shell.

6. Details of wind girders.

7. Spiral stairway, ladder and platform.

8. Plate layout of Roof, roof support details, details of appurtenances on cone roof , etc.

9. Any other design calculations as per contract.

10. Orientation and details of nozzles on tank roof.

11. Details of shell & roof nozzles.

12. Details of tank internals like still wells, truss for self supporting roof
13. Deleted

15. Plate cutting diagram for Free Issue Plates along with indicating anticipated the critical scrap
i.e. Burn oil losses & Accountable losses.

16. Material test certificate for items supplied by contractor.

17. Welding procedures & welders qualification reports.

19. Final Inspection certificate and Hydrostatic test report.

20. Calibration Charts in hard and soft copies

21. As - Built drawing showing details as listed in Sr. No 1 to 15 above in HARD/ SOFT COPIES.