Professional Documents
Culture Documents
Polarity Test
Polarity Test
Stephen Albrecht
Safety & Training Manager
MainPower New Zealand Limited
1. Problem
2. Transposition Implications
3. Key Legislation
4. De-energised and live testing
5. Polarity Testing ABCs
1. Problem
Misconception about polarity testing
(when and how)
Root Cause Analysis
1. Why? Not well understood
2. Why? Misuse of terms
3. Why? Misunderstanding of legislation
4. Why? Legislation not clear
5. Why? Key terms not defined
6. Why? ???
2. Transposition Implications
• Switches & protective devices bypassed
• Neutral & earth conductors live
• Earthed metal live
• Damage to property / equipment
• Electric shock
• Investigation (Police, ES, DoL)
• Prosecution (Police, ES, DoL)
• Complaint to EWRB – disciplinary process
• Profound affect on families / practitioner
Selection of Reported
Transpositions to Energy Safety
Date Voltage Equipment Type Event Type Causal Factor Referred
to EWRB
1 25-01-08 230 Distribution pillar Electric shock Failure to adequately test Yes
2 01-05-08 230 o/h service mains Electric shocks Failure to adequately test Yes
3 05-06-08 230 Mains to house Property damage Failure to adequately test Yes
5 18-07-08 230 Revenue metering Electric shocks Failure to adequately test Yes
6 04-08-08 230 Revenue metering Electric shocks Failure to adequately test Yes
7 11-09-08 230 Mains entry box Electric shock Failure to adequately test Yes
8 06-01-09 230 o/h service mains Electric shock Failure to test Yes
9 29-05-09 400 u/g mains to school Property damage (fire) Failure to adequately test Yes
10 31-08-09 230 u/g service mains Electric shocks Failure to test Yes
11 17-12-09 230 Repair to mains cable Electric shock Failure to adequately test Yes
12 05-04-10 230 Mains entry box Electric shock (fatal) Failure to adequately test Yes
Main/Sw CBs
Mains N-Bar
Link
E-Bar
Switched Socket
LV Installation with Correct Connections
POS
Works Installation
O/H POE MEN Switchboard
Transformer Fuse (Mains Entry Box)
Main/Sw CBs
Mains Mains N-Bar
Link
E-Bar
The Point of Supply (POS) location
can vary (refer to new definition
s2(3) of the Electricity Act 1992) Earth Electrode
P N
Revenue metering and load control
equipment not shown E
Switched Socket
Result of Transposition at O/H Point of Entry
POS
Works Installation
O/H POE MEN Switchboard
Transformer Fuse (Mains Entry Box)
Main/Sw CBs
Mains Mains N-Bar
Link
E-Bar
Mains phase & neutral
transposed ! ! ! !
All neutral & earth Earth Electrode
conductors beyond P N
transposition point E
within installation now
become Live to touch! Switched Socket
BUT WON’T THE FUSE BLOW?
POS
Works Installation
O/H POE MEN Switchboard
Transformer Fuse (Mains Entry Box)
Main/Sw CBs
Link
E-Bar
transposition point E
within installation now
become Live to touch! Switched Socket
Rewireable 60 2 120 2
Main/Sw CBs
Link
E-Bar
1. Ohm-meter
2. Battery Phasing
Ohm-meter Method
Mains
Ohm-meter Method
Mains
Ohm-meter Method
Mains
Temporary Lead
Ohm-meter Method
Mains
>999 MΩ
Ω
Temporary Lead
Ohm-meter Method
Mains
0.2 Ω
Temporary Lead
Ohm-meter Method
Mains
0.2 Ω
Temporary Lead
Ohm-meter Method
Mains
>999 MΩ
Ω
Temporary Lead
Ohm-meter Method
Mains
0.2 Ω
Temporary Lead
Ohm-meter Method
Mains
0.2 Ω
Temporary Lead
Ohm-meter Method
Mains
Mains
Battery Phasing Method
Mains
Mains 9V
-
Battery Phasing Method
+
Mains 9V
-
+9V
Mains 9V
-
-9V
Battery Phasing Method
+
Mains 9V
-
+9V
Mains 9V
-
+9V
Battery Phasing Method
Mains
• Popular method
• Has limitations
Notes
Fluke T120
230 to 120 volt LED indicator transition was at 23,000 Ω
Battery removal resulted in no resitance measurement capability, single point polarity indication, and no light.
However, LCD and LED voltage indication still functioned.
Apparatus
Iskra 250 V, 5 A, 1φ Variac
Conway Electronic Enterprises 6 - Decade Resistance Box
Thurlby Thandar 1906 Computing Multimeter
Selection of voltage instruments as specified in above table